D03-TSG Radar FY2026
D03 County · est $0.4M
Bid dateThursday, September 25—
D03 County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 7 more items below.
| Item | Quantity | R1Perram Electric INC | R2Asplundh Construction LLC | R3Miller Cable Company | R4Complete General Construction Company | R5U S Utility Contractor Company | R6Capital Electric Line Builders INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN, INSTALLATI | 36 EACH | $1,113 | $850 | $1,425 | $900 | $1,673 | $1,003 | 19% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN, INSTALLATION | 33 EACH | $1,193 | $850 | $1,425 | $1,100 | $1,673 | $1,003 | 19% |
| 625E31510 PULL BOX REMOVED | 113 EACH | $200 |
| Item | Quantity | R1Perram Electric INC | R2Asplundh Construction LLC | R3Miller Cable Company | R4Complete General Construction Company | R5U S Utility Contractor Company | R6Capital Electric Line Builders INC |
|---|---|---|---|---|---|---|---|
| 625E25400 CONDUIT, 2", 725.04 | 14 FT | $45.35 | $40.00 | $20.00 | $37.00 | $33.00 | $14.40 |
| 625E29000 TRENCH | 42 FT | $14.95 | $13.00 | $12.00 | $21.00 | $13.20 | $10.03 |
| 625E32000 GROUND ROD | 1 EACH | $340 | $342 | $265 | $325 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $347 |
| $335 |
| $450 |
| $330 |
| $737 |
| 11% |
| 632E72140 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13 | 1 EACH | $18,400 | $24,000 | $20,100 | $24,000 | $22,550 | $19,748 | 9% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 192 HOUR | $75.00 | $95.00 | $75.00 | $90.00 | $80.50 | $88.00 | 7% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 11 EACH | $920 | $1,453 | $1,325 | $1,175 | $1,144 | $992 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $16,780 | $7,500 | $10,000 | $15,475 | $58,236 | 5% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 1 EACH | $8,460 | $6,599 | $7,400 | $14,000 | $8,063 | $11,547 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,300 | $10,070 | $18,523 | $12,000 | $9,225 | $9,124 | 4% |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 13 EACH | $523 | $594 | $925 | $2,050 | $1,507 | $1,003 | 3% |
| 632E90500 SIGNALIZATION, MISC.: UNLASH AND RELASH MESSENGER | 945 FT | $6.47 | $6.00 | $5.00 | $3.50 | $8.61 | $4.86 | 3% |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 1,660 FT | $3.52 | $3.00 | $3.50 | $3.05 | $5.14 | $3.45 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,997 | $1,250 | $1,100 | $1,500 | $4,428 | $3,861 | 2% |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM FOR S | 5 EACH | $545 | $437 | $475 | $625 | $673 | $401 | 1% |
| 632E90008 PEDESTAL, 15', TRANSFORMER BASE | 2 EACH | $1,330 | $922 | $1,100 | $2,500 | $1,238 | $1,779 | 1% |
| 632E64020 PEDESTAL FOUNDATION | 2 EACH | $1,035 | $1,759 | $1,200 | $1,300 | $1,489 | $2,048 | 1% |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 625E30700 PULL BOX, 725.08, 18" | 1 EACH | $1,600 | $1,394 | $1,150 | $1,500 | $1,115 | $1,330 | 1% |
| 625E25500 CONDUIT, 3", 725.04 | 28 FT | $42.15 | $44.00 | $32.00 | $35.00 | $44.50 | $25.05 | 1% |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 270 FT | $3.60 | $4.00 | $3.80 | $3.85 | $5.37 | $3.31 | 0% |
| $298 |
| $211 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 42 FT | $1.30 | $2.00 | $2.50 | $2.00 | $2.07 | $1.10 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 7 EACH | $10.00 | $130 | $40.00 | $38.00 | $18.75 | $6.13 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: PULL BOX | 2 EACH | $320 | $322 | $500 | $260 | $308 | $862 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $100 | $5,506 | $3,180 | $1,000 | $2,875 | $4,224 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN, INSTALLATI | 36 EACH | $1,113 | $40k | 19% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN, INSTALLATION | 33 EACH | $1,193 | $39k | 19% |
| 625E31510 PULL BOX REMOVED | 113 EACH | $200 | $23k | 11% |
| 632E72140 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13 | 1 EACH | $18,400 | $18k | 9% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 192 HOUR | $75 | $14k | 7% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 11 EACH | $920 | $10k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 5% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 1 EACH | $8,460 | $8k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,300 | $8k | 4% |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 13 EACH | $523 | $7k | 3% |