Figure 0.1 · BRIEFING
BID #260054 · ODOTRESULT · awarded Jan 29

JEF-US 22-06.99

JEF County · est $0.6M

Bid dateThursday, January 29
Awarded toTUCSON INC$507,908.63
read → connected → answeredcassandri

Project scope

Bid form · ODOT

37ITEMS
  • Earthwork22%
  • Erosion & Landscaping19%
  • Drainage11%
  • Guardrail & Barrier11%
  • Maintaining Traffic11%
  • Mobilization & General11%
  • Other16%

Top items by winning bid

ItemQtyUnit priceExtended%
601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE B538 CY$194$104k21%
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $222,590.53 2 $247,148.75 3 $220,914.33 4 $274,843.55 5 $316,859.50 6 $253,064.50 7 $250,765.56 8 $359,678.5080,000 EACH$1$80k16%
203E10000 EXCAVATION1,149 CY$55.75$64k13%
304E20000 AGGREGATE BASE Section 4 - PAVEMENT - Totals Awd $37,485.00 2 $40,278.00 3 $24,878.28 4 $39,984.00 5 $32,340.00 6 $33,810.00 7 $39,469.50 8 $52,920.00294 CY$127.5$37k7%
601E20000 CRUSHED AGGREGATE SLOPE PROTECTION604 SY$51.65$31k6%
503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN Section 6 - STRUCTURE REPAIR (JEF-22-06.980, L&R SFN - Totals Awd $26,650.00 2 $52,780.00 3 $103,118.05 4 $80,000.00 5 $43,000.00 6 $64,100.00 7 $135,186.00 8 $100,000.001 LS$26,650$27k5%
602E20000 CONCRETE MASONRY13 CY$1,790$23k5%
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $62,100.00 2 $42,734.85 3 $92,472.00 4 $95,750.00 5 $81,500.00 6 $88,959.00 7 $115,144.50 8 $117,100.001 LS$19,000$19k4%
619E16010 FIELD OFFICE, TYPE B7 MNTH$2,100$15k3%
611E13200 30" CONDUIT, TYPE A , 706.02, 707.33, OR 707.34 Section 3 - DRAINAGE - Totals Awd $38,060.00 2 $40,697.00 3 $33,806.91 4 $5,410.00 5 $20,520.00 6 $34,713.00 7 $28,794.75 8 $36,350.0039 FT$366$14k3%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 17 more items below.

Rank 1Tucson INC$508kRank 2Rudzik Excavating INC$545kRank 3S.t.a.r.t., LLC$564kRank 4Mason Dixon Energy Services LLC$596kRank 5Xtreme Elements LLC$624kRank 6Shelly & Sands INC$661kRank 7Eclipse CO LLC$712kRank 8Dennison Bridge INC$797k
ItemQuantityR1Tucson INCR2Rudzik Excavating INCR3S.t.a.r.t., LLCR4Mason Dixon Energy Services LLCR5Xtreme Elements LLCR6Shelly & Sands INCR7Eclipse CO LLCR8Dennison Bridge INC
601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE B538 CY$194$242$197$250$375$242$225$425
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $222,590.53 2 $247,148.75 3 $220,914.33 4 $274,843.55 5 $316,859.50 6 $253,064.50 7 $250,765.56 8 $359,678.5080,000 EACH$1.00$1.00$1.00$1.00$1.00$1.00$1.00$1.00
203E10000 EXCAVATION1,149 CY$55.75$49.00$29.15$32.00$40.00$27.00$56.25$65.00
304E20000 AGGREGATE BASE Section 4 - PAVEMENT - Totals Awd $37,485.00 2 $40,278.00 3 $24,878.28 4 $39,984.00 5 $32,340.00 6 $33,810.00 7 $39,469.50 8 $52,920.00294 CY$128$137$84.62$136$110$115$134$180
601E20000 CRUSHED AGGREGATE SLOPE PROTECTION604 SY$51.65$49.00$38.91$80.00$43.00$48.00$59.25$65.00
503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN Section 6 - STRUCTURE REPAIR (JEF-22-06.980, L&R SFN - Totals Awd $26,650.00 2 $52,780.00 3 $103,118.05 4 $80,000.00 5 $43,000.00 6 $64,100.00 7 $135,186.00 8 $100,000.001 LS$26,650$52,780$103,118$80,000$43,000$64,100$135,186$100,000
602E20000 CONCRETE MASONRY13 CY$1,790$1,800$1,414$250$745$1,221$1,397$1,250
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $62,100.00 2 $42,734.85 3 $92,472.00 4 $95,750.00 5 $81,500.00 6 $88,959.00 7 $115,144.50 8 $117,100.001 LS$19,000$18,000$29,522$27,000$38,500$31,000$79,100$25,000
619E16010 FIELD OFFICE, TYPE B7 MNTH$2,100$800$3,200$250$1,200$5,274$1,733$2,000
611E13200 30" CONDUIT, TYPE A , 706.02, 707.33, OR 707.34 Section 3 - DRAINAGE - Totals Awd $38,060.00 2 $40,697.00 3 $33,806.91 4 $5,410.00 5 $20,520.00 6 $34,713.00 7 $28,794.75 8 $36,350.0039 FT$366$423$350$40.00$265$450$253$500
614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC Section 5 - MAINTENANCE OF TRAFFIC - Totals Awd $18,050.00 2 $12,015.00 3 $13,975.00 4 $23,500.00 5 $18,000.00 6 $22,125.00 7 $33,515.00 8 $11,900.0050 CY$277$150$205$300$200$368$590$160
614E11000 MAINTAINING TRAFFIC1 LS$11,000$5,245$1,250$50,000$3,500$4,045$3,245$3,100
607E23000 FENCE, TYPE CLT216 FT$48.35$58.90$33.75$60.00$72.00$34.00$37.25$52.00
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$8,700$5,690$8,500$10,000$12,000$3,679$9,047$10,000
201E11000 CLEARING AND GRUBBING1 LS$6,605$15,400$10,022$2,000$25,500$106,000$16,622$10,000
606E15050 GUARDRAIL, TYPE MGS200 FT$32.80$30.80$29.20$60.00$37.00$29.00$32.00$29.50
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$5,800$5,000$15,800$3,000$15,500$10,792$9,000$15,000
614E12420 DETOUR SIGNING1 LS$4,200$4,515$3,725$8,500$8,000$3,725$4,015$3,900
606E26150 ANCHOR ASSEMBLY, MGS TYPE E1 EACH$3,162$3,465$2,960$500$2,650$850$3,256$3,300
659E00300 TOPSOIL49 CY$60.00$20.00$106$80.00$95.00$109$92.50$45.00
Show all 37 line items
ItemQuantityR1Tucson INCR2Rudzik Excavating INCR3S.t.a.r.t., LLCR4Mason Dixon Energy Services LLCR5Xtreme Elements LLCR6Shelly & Sands INCR7Eclipse CO LLCR8Dennison Bridge INC
202E20010 HEADWALL REMOVED2 EACH$581$1,000$489$350$2,000$278$506$500
202E35200 PIPE REMOVED, OVER 24" DIAMETER , 30"31 FT$37.50$30.00$85.29$30.00$25.00$18.00$37.00$30.00
203E20000 EMBANKMENT83 CY$32.00$60.00$40.10$22.00$20.00$56.00$20.75$45.00
204E10000 SUBGRADE COMPACTION585 SY$2.65$3.00$4.39$12.00$4.00$3.00$1.50$5.00
204E45000 PROOF ROLLING1 HOUR$150$250$450$300$500$358$294$100
606E25550 ANCHOR ASSEMBLY, MGS TYPE A1 EACH$2,585$2,365$1,970$500$2,350$1,970$2,167$2,300
607E61200 GATE, TYPE CLT Section 1 - ROADWAY - Totals Awd $102,973.10 2 $109,166.40 3 $74,523.29 4 $76,354.00 5 $111,687.00 6 $163,842.00 7 $109,453.25 8 $118,807.001 EACH$2,880$2,838$2,980$850$3,000$2,980$3,278$2,700
601E11000 RIPRAP, TYPE D9 SY$141$550$417$65.00$235$473$324$600
659E00100 SOIL ANALYSIS TEST2 EACH$75.00$25.00$84.14$350$175$150$149$100
659E10000 SEEDING AND MULCHING442 SY$5.65$3.00$2.94$15.00$4.00$8.00$13.25$8.00
659E14000 REPAIR SEEDING AND MULCHING22 SY$1.50$0.05$11.19$6.00$2.00$8.00$11.75$8.00
659E15000 INTER-SEEDING22 SY$1.00$0.05$12.33$0.25$2.00$8.00$11.75$8.00
659E20000 COMMERCIAL FERTILIZER0.06 TON$1,050$800$2,999$750$800$1,250$973$1,000
659E31000 LIME0.09 ACRE$307$5.00$1,852$45.00$150$150$177$150
659E35000 WATER2 MGAL$10.00$0.05$5.00$1.00$50.00$1.00$1.00$1.00
518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC2 CY$258$400$894$300$250$645$395$300
100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY1 LS$2,900$3,200$15,000$4,000$3,600$2,525$2,625$50,000

Project details

Description
JEF-US 22-06.99
Type of work
Earthwork

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →