BID #260164 · ODOTRESULT · awarded Mar 26

D12-LG FY2026

D12 County · est $1.3M

Bid dateThursday, March 26
Awarded toRUHLIN COMPANY$1.40M
read → connected → answeredcassandri

Project scope

Bid form · ODOT

42ITEMS
  • Signals & Lighting62%
  • Maintaining Traffic5%
  • Mobilization & General5%
  • Earthwork2%
  • Guardrail & Barrier2%
  • Erosion & Landscaping2%
  • Other21%

Top items by winning bid

ItemQtyUnit priceExtended%
625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE95,268 FT$4$381k27%
625E34001 POWER SERVICE, AS PER PLAN9 EACH$16,500$149k11%
625E10495 LIGHT POLE, LOW MAST, AS PER PLAN, ALM4536 EACH$3,350$121k9%
625E10490 LIGHT POLE, CONVENTIONAL, AT18B3520 EACH$5,300$106k8%
614E11000 MAINTAINING TRAFFIC1 LS$83,500$84k6%
624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $160,100.00 2 $156,000.00 3 $301,081.581 LS$70,000$70k5%
625E00480 CONNECTION, UNFUSED PERMANENT244 EACH$215$52k4%
625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA37 EACH$1,195$44k3%
625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP21 EACH$2,100$44k3%
625E00451 CONNECTION, FUSED PULL APART, AS PER PLAN174 EACH$238$41k3%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 22 more items below.

Rank 1Ruhlin Company$1.40MRank 2Miller Cable Company$1.50MRank 3Perram Electric INC$2.14M
ItemQuantityR1Ruhlin CompanyR2Miller Cable CompanyR3Perram Electric INC
625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE95,268 FT$4.00$5.00$5.84
625E34001 POWER SERVICE, AS PER PLAN9 EACH$16,500$17,500$26,270
625E10495 LIGHT POLE, LOW MAST, AS PER PLAN, ALM4536 EACH$3,350$3,500$9,632
625E10490 LIGHT POLE, CONVENTIONAL, AT18B3520 EACH$5,300$4,425$4,945
614E11000 MAINTAINING TRAFFIC1 LS$83,500$94,000$160,980
624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $160,100.00 2 $156,000.00 3 $301,081.581 LS$70,000$48,000$100,000
625E00480 CONNECTION, UNFUSED PERMANENT244 EACH$215$120$178
625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA37 EACH$1,195$950$3,005
625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP21 EACH$2,100$3,200$3,127
625E00451 CONNECTION, FUSED PULL APART, AS PER PLAN174 EACH$238$120$217
625E10490 LIGHT POLE, CONVENTIONAL, AT15B405 EACH$4,530$3,800$4,220
625E25910 CONDUIT CLEANED AND CABLES REMOVED31,916 FT$0.70$2.00$0.55
625E75400 LIGHT POLE REMOVED58 EACH$355$400$539
614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST150 HOUR$120$75.00$153
625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER25 EACH$684$525$795
625E23400 NO. 10 AWG POLE AND BRACKET CABLE8,405 FT$2.00$3.00$2.16
625E00461 CONNECTION, UNFUSED PULL APART, AS PER PLAN64 EACH$227$120$212
625E26263 LUMINAIRE, HIGH MAST, SOLID STATE (LED), AS PER PL8 EACH$1,613$300$3,540
625E75511 POWER SERVICE REMOVED, AS PER PLAN11 EACH$1,100$600$808
625E29002 TRENCH, 24" DEEP571 FT$21.00$12.00$23.60
Show all 42 line items
ItemQuantityR1Ruhlin CompanyR2Miller Cable CompanyR3Perram Electric INC
201E11000 CLEARING AND GRUBBING1 LS$6,000$500$12,925
606E27501 ANCHOR ASSEMBLY REBUILT, AS PER PLAN1 EACH$7,475$4,975$9,495
607E61200 GATE, TYPE CLT Section 1 - ROADWAY - Totals Awd $24,615.00 2 $10,475.00 3 $39,040.004 EACH$2,785$1,250$4,155
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $1,000.00 2 $1,000.00 3 $1,000.001,000 EACH$1.00$1.00$1.00
202E98100 REMOVAL MISC.:CONTROL CENTER AND DISCONNECT11 EACH$750$600$540
625E23300 NO. 2 AWG 2400 VOLT DISTRIBUTION CABLE440 FT$6.00$5.75$6.22
625E24100 1-1/2" DUCT CABLE WITH TWO NO. 4 AWG 2400 VOLT CAB325 FT$25.00$11.00$15.40
625E24300 1-1/2" DUCT CABLE WITH TWO NO. 2 AWG 2400 VOLT CAB205 FT$30.00$14.00$20.05
625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C41 FT$35.00$15.00$26.90
625E30700 PULL BOX, 725.08, 18"1 EACH$1,795$1,200$1,870
625E30706 PULL BOX, 725.08, 24"3 EACH$1,975$1,500$2,330
625E31510 PULL BOX REMOVED14 EACH$500$300$135
625E32000 GROUND ROD32 EACH$345$300$428
625E34001 POWER SERVICE, AS PER PLAN, (LOCATION 1 & 2)2 EACH$4,233$3,000$10,030
625E36010 UNDERGROUND WARNING MARKING TAPE571 FT$3.00$3.00$2.05
625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING1 LS$10,000$22,000$635
625E50400 REPAIR INTEGRAL LUMINAIRE LOWERING MECHANISM OF TO2 EACH$5,100$19,400$7,040
625E75500 LIGHT POLE FOUNDATION REMOVED21 EACH$380$650$808
625E75506 LUMINAIRE REMOVED72 EACH$100$150$67.30
625E98200 LIGHTING, MISC.:TEST CIRCUITS Section 3 - LIGHTING - Totals Awd $1,190,292.20 2 $1,315,907.00 3 $1,774,337.421 LS$3,000$18,500$4,580
630E97800 SIGNING, MISC.: ADDITIONAL SIGNS, GROUND MOUNTED, Section 4 - MAINTENANCE OF TRAFFIC - Totals Awd $23,000.00 2 $16,450.00 3 $29,215.00100 SF$50.00$52.00$63.40
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$6,600$14,000$40,102

Project details

Description
D12-LG FY2026
Type of work
Signals

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →