Pulled plans1 prime · 3 subs
Likely also biddingOH signals regulars · 8
Confirmed = pulled plans on this letting (revealed interest, from the agency portal). Likely = firms that bid OH signalswork in the last 3 years, ranked by where and how recently they bid it — firms most active in this project’s county and ODOT district rank first. Win rate is historical — the share of bids that firm entered and won, not a prediction of this letting.
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
Bid form · ODOT
36 advertised pay items from the ODOT bid form. Open a category to see its items — unit prices appear here once bids open.
| 201E11000 | CLEARING AND GRUBBING | Lump sum |
| 202E23000 | PAVEMENT REMOVED | 314 SY |
| 203E10000 | EXCAVATION | 192 CY |
| 203E20000 | EMBANKMENT | 86 CY |
| 204E10000 | SUBGRADE COMPACTION | 1,131 SY |
| 204E13000 | EXCAVATION OF SUBGRADE12" DEPTH | 399 CY |
| 204E30010 | GRANULAR MATERIAL, TYPE B 12" DEPTH | 399 CY |
| 204E45000 | PROOF ROLLING | 1 HOUR |
| 204E50000 | GEOTEXTILE FABRIC | 1,197 SY |
| 623E50000 | PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND REPORT NR) | Lump sum |
| 623E51000 | POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND REPORT | Lump sum |
| 616E10000 | WATER | 1 MGAL |
| 659E00300 | TOPSOIL | 86 CY |
| 659E00500 | SEEDING AND MULCHING, CLASS 1 | 770 SY |
| 659E14000 | REPAIR SEEDING AND MULCHING | 39 SY |
| 659E15000 | INTER-SEEDING | 39 SY |
| 659E20000 | COMMERCIAL FERTILIZER | 0.1 TON |
| 659E31000 | LIME | 0.16 ACRE |
| 659E35000 | WATER | 4 MGAL |
| 832E30000 | EROSION CONTROL | 5,000 EACH |
| 254E01000 | PAVEMENT PLANING, ASPHALT CONCRETE1.25" DEPTH | 72 SY |
| 301E56000 | ASPHALT CONCRETE BASE, PG64-22, (449) | 119 CY |
| 304E20000 | AGGREGATE BASE | 201 CY |
| 407E20000 | NON-TRACKING TACK COAT | 70 GAL |
| 441E70000 | ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG64-22 | 39 CY |
| 618E40100 | RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 876 FT |
| 630E03100 | GROUND MOUNTED SUPPORT, NO. 3 POST | 43 FT |
| 630E08600 | SIGN POST REFLECTOR | 4 EACH |
| 630E80100 | SIGN, FLAT SHEET | 13 SF |
| 630E84900 | REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH |
| 630E86002 | REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSAL | 2 EACH |
| 103E05000 | PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYMENT BOND | Lump sum |
| 614E11000 | MAINTAINING TRAFFIC | Lump sum |
| 623E10000 | CONSTRUCTION LAYOUT STAKES AND SURVEYING | Lump sum |
| 624E10000 | MOBILIZATION | Lump sum |
| 605E31100 | AGGREGATE DRAINS | 185 FT |