GEA-US 422-17.35 Intersection
GEA County · est $0.5M
Bid dateThursday, February 1—
GEA County · est $0.5M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 90 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Eclipse CO LLC | R3Burton Scot Contractors LLC | R4Mr Excavator INC | R5S E T INC | % of bid |
|---|---|---|---|---|---|---|---|
| 202E56001 BUILDING DEMOLISHED, AS PER PLAN PARCEL 5-WD, 2-ST | 1 LS | $45,000 | $29,038 | $30,975 | $10,150 | $42,900 | 12% |
| 632E80602 SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 12 | 4 EACH | $9,200 | $8,969 | $9,500 | $11,089 | $10,900 | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $30,000 | $36,000 | $16,437 | $50,000 | 7% |
| 638E06401 10" STEEL PIPE ENCASEMENT, OPEN CUT, AS PER PLAN |
| Item | Quantity | R1Shelly & Sands INC | R2Eclipse CO LLC | R3Burton Scot Contractors LLC | R4Mr Excavator INC | R5S E T INC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $6,114 | $10,000 | $1,693 | $19,500 |
| 202E23000 PAVEMENT REMOVED | 329 SY | $11.00 | $13.00 | $20.00 | $8.05 | $15.00 |
| 202E30000 WALK REMOVED | 1,849 SF | $0.60 | $1.00 | $1.50 | $0.60 | $3.00 |
| 202E32000 CURB REMOVED | 339 FT | $3.00 | $4.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 74 FT |
| $350 |
| $260 |
| $275 |
| $263 |
| $420 |
| 7% |
| 442E20001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 94 CY | $260 | $268 | $300 | $321 | $320 | 6% |
| 809E69100 STOP-BAR RADAR DETECTION | 3 EACH | $8,000 | $7,217 | $8,000 | $9,338 | $6,900 | 6% |
| 611E99575 MANHOLE, NO. 3, AS PER PLAN | 2 EACH | $10,000 | $2,916 | $7,500 | $4,440 | $2,800 | 5% |
| 614E11500 WORKSITE TRAFFIC SUPERVISOR | 7 MNTH | $2,500 | $3,863 | $2,500 | $15,758 | $600 | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1-1/2" | 2,019 SY | $8.00 | $3.85 | $5.00 | $4.84 | $5.00 | 4% |
| 809E69000 ADVANCE RADAR DETECTION | 2 EACH | $8,000 | $7,835 | $8,500 | $9,922 | $7,200 | 4% |
| 608E52000 CURB RAMP | 559 SF | $27.00 | $15.00 | $12.00 | $13.80 | $18.00 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $6,500 | $7,150 | $8,346 | $15,500 | 4% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 4 EACH | $3,700 | $7,062 | $4,500 | $5,253 | $4,500 | 4% |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 6 MNTH | $2,300 | $700 | $1,500 | $1,973 | $1,800 | 4% |
| 625E25900 CONDUIT, JACKED OR DRILLED ,4" | 254 FT | $50.00 | $49.50 | $58.00 | $67.70 | $45.00 | 3% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 14 SNMT | $900 | $1,083 | $1,050 | $1,109 | $1,200 | 3% |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 5,000 LB | $2.15 | $2.50 | $1.50 | $4.22 | $0.50 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 74 CY | $140 | $224 | $250 | $350 | $350 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $20,000 | $20,000 | $9,802 | $65,000 | 3% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC1 | 140 SY | $65.00 | $76.00 | $65.00 | $80.37 | $76.00 | 2% |
| $5.00 |
| $2.24 |
| $9.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 24 FT | $37.00 | $18.50 | $100 | $25.38 | $25.00 |
| 202E52990 SPECIAL - PARKING BLOCK REMOVED | 6 EACH | $40.00 | $16.50 | $100 | $50.75 | $50.00 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $360 | $296 | $1,000 | $711 | $600 |
| 202E66000 SPECIAL - DRILLED WATER WELL ABANDONED | 1 EACH | $1,200 | $2,328 | $2,000 | $520 | $1,423 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 5 FT | $90.00 | $63.00 | $150 | $102 | $75.00 |
| 202E75000 FENCE REMOVED | 74 FT | $6.00 | $6.50 | $10.00 | $16.44 | $10.00 |
| 202E98000 REMOVAL MISC.:WOOD RAMP AND STEPS | 1 LS | $920 | $494 | $1,500 | $1,218 | $1,750 |
| 202E98200 REMOVAL MISC.:WOOD BORDER | 69 FT | $15.00 | $3.50 | $10.00 | $10.15 | $8.00 |
| 203E10000 EXCAVATION | 253 CY | $33.00 | $30.00 | $50.00 | $15.01 | $40.00 |
| 203E20000 EMBANKMENT | 55 CY | $10.00 | $16.50 | $50.00 | $18.05 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 446 SY | $2.00 | $5.00 | $5.00 | $2.03 | $2.50 |
| 608E10000 4" CONCRETE WALK | 1,228 SF | $6.00 | $5.50 | $5.00 | $8.27 | $7.00 |
| 608E15000 8" CONCRETE WALK | 178 SF | $7.50 | $9.00 | $8.00 | $10.50 | $9.00 |
| 608E52001 CURB RAMP, AS PER PLAN | 89 SF | $27.00 | $18.00 | $15.00 | $19.05 | $18.00 |
| 608E98000 WALKWAY, MISC.:, 10" CONCRETE WALK | 83 SF | $9.00 | $10.00 | $15.00 | $16.14 | $12.00 |
| 623E39500 MONUMENT BOX ADJUSTED TO GRADE | 1 EACH | $60.00 | $354 | $650 | $584 | $650 |
| 623E40520 RIGHT-OF-WAY MONUMENT | 6 EACH | $125 | $215 | $500 | $700 | $120 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $80.00 | $155 | $100 | $175 | $100 |
| 659E00300 TOPSOIL | 92 CY | $40.00 | $68.00 | $60.00 | $72.37 | $80.00 |
| 659E10000 SEEDING AND MULCHING | 825 SY | $5.00 | $3.00 | $3.21 | $3.27 | $4.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 42 SY | $0.40 | $3.00 | $3.00 | $3.27 | $3.00 |
| 659E15000 INTER-SEEDING | 42 SY | $0.15 | $3.00 | $3.00 | $3.27 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.12 TON | $635 | $1,856 | $625 | $2,101 | $700 |
| 659E31000 LIME | 0.17 ACRE | $106 | $773 | $100 | $875 | $110 |
| 659E35000 WATER | 5 MGAL | $1.00 | $82.50 | $1.00 | $93.38 | $6.00 |
| 832E30000 EROSION CONTROL | 8,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E06000 4" BASE PIPE UNDERDRAINS | 339 FT | $20.00 | $11.00 | $20.00 | $11.11 | $12.00 |
| 611E01400 6" CONDUIT, TYPE E | 50 FT | $16.00 | $25.50 | $25.00 | $31.83 | $10.00 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $18.00 | $25.50 | $25.00 | $31.83 | $9.00 |
| 611E04400 12" CONDUIT, TYPE B | 84 FT | $60.00 | $76.00 | $170 | $147 | $85.00 |
| 611E04600 12" CONDUIT, TYPE C | 71 FT | $70.00 | $60.50 | $150 | $118 | $65.00 |
| 611E05900 15" CONDUIT, TYPE B | 24 FT | $90.00 | $90.00 | $235 | $133 | $100 |
| 611E98180 CATCH BASIN, NO. 3A | 2 EACH | $2,000 | $1,666 | $3,000 | $2,030 | $2,550 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,500 | $1,266 | $2,500 | $1,464 | $1,580 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $600 | $478 | $800 | $717 | $950 |
| 304E20000 AGGREGATE BASE | 51 CY | $92.00 | $94.50 | $80.00 | $57.01 | $95.00 |
| 407E20000 NON-TRACKING TACK COAT | 179 GAL | $3.00 | $3.10 | $2.50 | $13.43 | $12.00 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (12 CY | $200 | $357 | $350 | $350 | $360 |
| 609E26000 CURB, TYPE 6 | 315 FT | $25.00 | $21.50 | $30.00 | $28.60 | $24.00 |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 240 LB | $0.60 | $5.00 | $6.74 | $3.50 | $5.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 26 FT | $15.00 | $15.50 | $12.00 | $14.01 | $15.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 20 EACH | $190 | $222 | $55.00 | $64.20 | $65.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 12 EACH | $50.00 | $51.50 | $55.00 | $64.20 | $65.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $16.00 | $15.50 | $35.00 | $40.85 | $50.00 |
| 644E00500 STOP LINE | 96 FT | $10.00 | $6.50 | $6.00 | $7.00 | $8.00 |
| 644E00600 CROSSWALK LINE | 423 FT | $5.00 | $4.50 | $2.75 | $4.09 | $4.00 |
| 644E01300 LANE ARROW | 6 EACH | $80.00 | $77.50 | $105 | $105 | $130 |
| 646E10010 EDGE LINE, 6" | 0.06 MILE | $16,000 | $60,390 | $22,000 | $25,680 | $26,000 |
| 646E10110 LANE LINE, 6" | 0.04 MILE | $16,000 | $59,679 | $18,000 | $21,011 | $22,000 |
| 646E10200 CENTER LINE | 0.04 MILE | $16,000 | $62,045 | $25,000 | $29,181 | $29,000 |
| 646E10300 CHANNELIZING LINE, 8" | 109 FT | $3.00 | $5.50 | $1.90 | $2.22 | $3.00 |
| 611E00400 4" CONDUIT, TYPE E | 40 FT | $3.00 | $2.00 | $5.00 | $5.84 | $20.00 |
| 625E25400 CONDUIT, 2", 725.04 | 75 FT | $16.00 | $20.50 | $12.00 | $14.01 | $18.00 |
| 625E25600 CONDUIT, 4", 725.04 | 7 FT | $32.00 | $41.00 | $18.00 | $21.01 | $65.00 |
| 625E29000 TRENCH | 82 FT | $6.50 | $15.50 | $12.00 | $14.01 | $15.00 |
| 625E30700 PULL BOX, 725.08, 18" | 1 EACH | $900 | $851 | $800 | $934 | $1,200 |
| 625E30706 PULL BOX, 725.08, 24" | 3 EACH | $1,000 | $1,031 | $900 | $1,051 | $1,350 |
| 625E30710 PULL BOX, 725.08, 32" | 1 EACH | $1,900 | $2,165 | $1,800 | $2,101 | $1,850 |
| 625E32000 GROUND ROD | 8 EACH | $185 | $243 | $155 | $181 | $150 |
| 625E36000 PLASTIC CAUTION TAPE | 336 FT | $0.25 | $0.50 | $1.00 | $1.17 | $0.50 |
| 630E09102 SURFACE PREPARATION, NEW SUPPORT SECTION | 4 EACH | $212 | $1.00 | $50.00 | $58.36 | $1.00 |
| 630E09106 COATING, EPOXY INTERMEDIATE COAT, SUPPORT SECTION | 4 EACH | $212 | $1.00 | $50.00 | $58.36 | $1.00 |
| 630E09108 COATING, URETHANE TOP COAT, SUPPORT SECTION | 4 EACH | $212 | $1.00 | $50.00 | $58.36 | $1.00 |
| 630E09120 COATING, ORGANIC ZINC PRIME COAT, SUPPORT SECTION | 4 EACH | $212 | $1.00 | $50.00 | $58.36 | $1.00 |
| 632E05007 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 6 EACH | $900 | $1,005 | $950 | $1,109 | $775 |
| 632E05087 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 2 EACH | $1,200 | $1,547 | $1,200 | $1,401 | $1,300 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 8 EACH | $700 | $593 | $525 | $613 | $600 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 8 EACH | $11.00 | $41.00 | $40.00 | $46.69 | $50.00 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 8 EACH | $11.00 | $31.00 | $40.00 | $46.69 | $40.00 |
| 632E26000 PEDESTRIAN PUSHBUTTON | 4 EACH | $212 | $134 | $175 | $204 | $180 |
| 632E40200 SIGNAL CABLE, 2 CONDUCTOR, NO. 14 AWG | 704 FT | $2.00 | $2.00 | $1.50 | $1.76 | $2.50 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 870 FT | $2.50 | $2.50 | $1.85 | $2.16 | $2.50 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 933 FT | $2.50 | $2.50 | $2.25 | $2.63 | $3.00 |
| 632E64020 PEDESTAL FOUNDATION | 3 EACH | $700 | $825 | $700 | $817 | $950 |
| 632E68300 POWER CABLE, 3 CONDUCTOR, NO. 6 AWG | 52 FT | $6.00 | $2.00 | $3.00 | $3.50 | $3.00 |
| 632E69800 SERVICE CABLE, 3 CONDUCTOR, NO. 6 AWG | 90 FT | $6.00 | $2.00 | $3.00 | $3.50 | $3.00 |
| 632E70000 POWER SERVICE | 1 EACH | $1,600 | $1,289 | $2,800 | $3,268 | $2,500 |
| 632E90000 PEDESTAL, 11', TRANSFORMER BASE | 3 EACH | $700 | $593 | $800 | $934 | $600 |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 1 EACH | $2,100 | $2,938 | $2,500 | $2,918 | $2,200 |
| 633E01651 CONTROLLER UNIT, TYPE 2070E WITH 2070-1C CPU AND A | 1 EACH | $4,200 | $3,866 | $5,200 | $6,070 | $4,500 |
| 633E65520 CABINET, TYPE 332 | 1 EACH | $8,000 | $9,072 | $7,500 | $8,754 | $8,000 |
| 633E67100 CABINET FOUNDATION | 1 EACH | $1,600 | $2,578 | $2,500 | $2,918 | $1,300 |
| 633E67200 CONTROLLER WORK PAD | 1 EACH | $370 | $467 | $700 | $817 | $325 |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 1 EACH | $5,900 | $5,670 | $5,500 | $6,420 | $6,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 60 HOUR | $70.00 | $67.00 | $65.00 | $81.71 | $50.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $17,000 | $8,000 | $6,029 | $10,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 202E56001 BUILDING DEMOLISHED, AS PER PLAN PARCEL 5-WD, 2-ST | 1 LS | $45,000 | $45k | 8% |
| 632E80602 SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 12 | 4 EACH | $9,200 | $37k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $27k | 5% |
| 638E06401 10" STEEL PIPE ENCASEMENT, OPEN CUT, AS PER PLAN | 74 FT | $350 | $26k | 5% |
| 442E20001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 94 CY | $260 | $24k | 4% |
| 809E69100 STOP-BAR RADAR DETECTION | 3 EACH | $8,000 | $24k | 4% |
| 611E99575 MANHOLE, NO. 3, AS PER PLAN | 2 EACH | $10,000 | $20k | 4% |
| 614E11500 WORKSITE TRAFFIC SUPERVISOR | 7 MNTH | $2,500 | $18k | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1-1/2" | 2,019 SY | $8 | $16k | 3% |
| 809E69000 ADVANCE RADAR DETECTION | 2 EACH | $8,000 | $16k | 3% |