ATH-GR CAL2019-20 DD
ATH County · est $0.5M
Bid dateThursday, June 21—
ATH County · est $0.5M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 3%
Bid form · ODOT
| Item | Qty |
|---|
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 36 more items below.
| Item | Quantity | R1Pdk Construction INC | R2Lake Erie Construction Company | R3Deangelo Brothers LLC | % of bid |
|---|---|---|---|---|---|
| 606E26100 ANCHOR ASSEMBLY, TYPE E | 60 EACH | $2,000 | $2,050 | $1,900 | 23% |
| 606E13001 GUARDRAIL, TYPE 5, AS PER PLAN | 3,000 FT | $17.00 | $15.80 | $18.00 | 10% |
| 606E26000 ANCHOR ASSEMBLY, TYPE B | 30 EACH | $1,700 | $1,760 | $1,600 | 10% |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 10 EACH | $4,000 | $4,120 | $4,100 | 8% |
| 606E15050 GUARDRAIL, TYPE MGS | 2,000 FT | $18.00 | $16.40 | $14.00 |
| Item | Quantity | R1Pdk Construction INC | R2Lake Erie Construction Company | R3Deangelo Brothers LLC |
|---|---|---|---|---|
| 202E38201 GUARDRAIL REMOVED FOR REUSE, AS PER PLAN | 100 FT | $2.00 | $2.40 | $1.00 |
| 202E38500 BRIDGE RAILING REMOVED | 100 FT | $2.00 | $2.00 | $30.00 |
| 202E38700 GUARDRAIL POST REMOVED | 5 EACH | $2.00 | $2.00 | $10.00 |
| 202E42807 ANCHOR ASSEMBLY REMOVED FOR REUSE, AS PER PLAN | 25 EACH | $50.00 | $50.00 | $300 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 5 EACH | $80.00 | $95.00 | $700 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $46,450 | $6,400 | 6% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 200 FT | $120 | $74.00 | $90.00 | 5% |
| 606E27851 ANCHOR ASSEMBLY REBUILT, TYPE E, AS PER PLAN | 20 EACH | $1,100 | $1,320 | $500 | 4% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 10 EACH | $2,000 | $2,090 | $1,900 | 4% |
| 606E98000 GUARDRAIL, MISC.:TUBULAR BACKUP | 200 FT | $90.00 | $75.00 | $6.00 | 3% |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 10 EACH | $1,700 | $1,845 | $1,600 | 3% |
| 614E13600 MAINTENANCE OF TRAFFIC, ONE LANE CLOSURE ON A TWO | 150 EACH | $100 | $135 | $860 | 3% |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 20 EACH | $700 | $645 | $600 | 3% |
| 202E42206 ANCHOR ASSEMBLY REMOVED | 100 EACH | $120 | $145 | $200 | 2% |
| 606E25000 ANCHOR ASSEMBLY, TYPE A | 10 EACH | $1,100 | $1,080 | $950 | 2% |
| 606E27861 ANCHOR ASSEMBLY REBUILT, MGS TYPE E, AS PER PLAN | 10 EACH | $1,100 | $1,370 | $500 | 2% |
| 606E60070 IMPACT ATTENUATOR REBUILT, TYPE 1 (BIDIRECTIONAL), | 5 EACH | $2,200 | $2,450 | $2,500 | 2% |
| 606E27841 ANCHOR ASSEMBLY REBUILT, TYPE B, AS PER PLAN | 10 EACH | $800 | $1,050 | $500 | 2% |
| 202E38000 GUARDRAIL REMOVED | 5,000 FT | $1.50 | $2.00 | $1.80 | 1% |
| 614E13900 MAINTENANCE OF TRAFFIC FOR SHOULDER CLOSURE | 100 EACH | $50.00 | $125 | $560 | 1% |
| 202E98100 REMOVAL MISC.:BRIDGE TERMINAL ASSEMBLY REMOVED FOR | 5 EACH | $100 | $80.00 | $100 |
| 202E98100 REMOVAL MISC.:IMPACT ATTENUATOR REMOVED FOR REUSE, | 5 EACH | $250 | $200 | $1,000 |
| 202E98100 REMOVAL MISC.:MPACT ATTENUATOR REMOVED | 5 EACH | $225 | $225 | $750 |
| 606E13050 GUARDRAIL, TYPE 5A | 100 FT | $19.00 | $19.60 | $19.00 |
| 606E15500 GUARDRAIL, BARRIER DESIGN, TYPE 5 | 200 FT | $22.00 | $27.80 | $23.00 |
| 606E16051 GUARDRAIL REBUILT, TYPE MGS, AS PER PLAN | 100 FT | $9.00 | $12.80 | $20.00 |
| 606E16501 GUARDRAIL REBUILT, TYPE 5, AS PER PLAN | 200 FT | $8.00 | $11.40 | $17.50 |
| 606E17290 GUARDRAIL, TYPE 5, LONG-SPAN | 100 FT | $22.00 | $21.20 | $35.00 |
| 606E17901 GUARDRAIL POST, AS PER PLAN | 10 EACH | $25.00 | $42.00 | $70.00 |
| 606E18501 GUARDRAIL POST, 9 FEET, AS PER PLAN | 50 EACH | $30.00 | $65.00 | $60.00 |
| 606E19001 GUARDRAIL POST, STEEL, AS PER PLAN | 20 EACH | $45.00 | $55.00 | $70.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 1 EACH | $1,200 | $1,180 | $850 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 5 EACH | $800 | $820 | $600 |
| 606E27801 ANCHOR ASSEMBLY REBUILT, TYPE A, AS PER PLAN | 5 EACH | $900 | $640 | $525 |
| 606E27847 ANCHOR ASSEMBLY REBUILT, MGS TYPE B, AS PER PLAN | 5 EACH | $900 | $1,075 | $500 |
| 606E32160 BRIDGE TERMINAL ASSEMBLY, TYPE TST | 2 EACH | $2,000 | $1,385 | $300 |
| 606E32171 BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE TST, AS PER | 3 EACH | $1,000 | $1,050 | $300 |
| 606E35000 BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 2 EACH | $2,000 | $1,020 | $1,100 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 2 EACH | $2,000 | $1,960 | $2,000 |
| 606E35010 BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 1 | 2 EACH | $1,000 | $750 | $300 |
| 606E35012 MGS BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 1 | 1 EACH | $1,000 | $900 | $300 |
| 606E35100 BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 2 EACH | $400 | $360 | $375 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 2 EACH | $400 | $385 | $375 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 5 EACH | $650 | $775 | $750 |
| 606E35150 BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 4 | 2 EACH | $500 | $550 | $750 |
| 606E39001 36" CONCRETE ANCHOR REMOVED AND REPLACED, AS PER P | 1 EACH | $1,000 | $520 | $550 |
| 606E50000 SPECIAL - RESHAPING BERM | 150 FT | $1.00 | $1.20 | $2.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1BARRIER REFLECTOR,TYPE 1 | 100 EACH | $7.00 | $5.00 | $7.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $50.00 | $45.00 | $50.00 |
| 614E13800 MAINTENANCE OF TRAFFIC, ONE LANE CLOSURE ON A 4 LA | 10 EACH | $40.00 | $115 | $800 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,300 | $4,340 | $7,000 |
| Unit price |
|---|
| Extended |
|---|
| % |
|---|
| 606E26100 ANCHOR ASSEMBLY, TYPE E | 60 EACH | $2,000 | $120k | 20% |
| 606E13001 GUARDRAIL, TYPE 5, AS PER PLAN | 3,000 FT | $17 | $51k | 9% |
| 606E26000 ANCHOR ASSEMBLY, TYPE B | 30 EACH | $1,700 | $51k | 9% |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 10 EACH | $4,000 | $40k | 7% |
| 606E15050 GUARDRAIL, TYPE MGS | 2,000 FT | $18 | $36k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 5% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 200 FT | $120 | $24k | 4% |
| 606E27851 ANCHOR ASSEMBLY REBUILT, TYPE E, AS PER PLAN | 20 EACH | $1,100 | $22k | 4% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 10 EACH | $2,000 | $20k | 3% |
| 606E98000 GUARDRAIL, MISC.:TUBULAR BACKUP | 200 FT | $90 | $18k | 3% |