BID #260205 · ODOTRESULT · awarded Apr 23

MAH-Sheridan Rd (Poland)

MAH County · est $0.3M

Bid dateThursday, April 23
Awarded toECLIPSE CO LLC$349,999.98
read → connected → answeredcassandri

Project scope

Bid form · ODOT

51ITEMS
  • Earthwork25%
  • Drainage20%
  • Erosion & Landscaping10%
  • Mobilization & General8%
  • Removal & Demolition6%
  • Curb, Walk & Ramp6%
  • Other25%

Top items by winning bid

ItemQtyUnit priceExtended%
614E11000 MAINTAINING TRAFFIC1 LS$45,258$45k13%
441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG128 CY$353$45k13%
304E20000 AGGREGATE BASE295 CY$107.25$32k9%
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $95,643.42 2 $45,600.00 3 $97,804.00 4 $71,400.001 LS$29,020$29k8%
203E10000 EXCAVATION799 CY$31.5$25k7%
659E00300 TOPSOIL361 CY$58.5$21k6%
611E04600 12" CONDUIT, TYPE C203 FT$84$17k5%
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $56,857.75 2 $74,844.30 3 $69,733.50 4 $99,916.3513,000 EACH$1$13k4%
608E52001 CURB RAMP, AS PER PLAN864 SF$11.75$10k3%
619E16010 FIELD OFFICE, TYPE B6 MNTH$1,650$10k3%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 31 more items below.

Rank 1Eclipse CO LLC$350kRank 2Geauga Highway CO$381kRank 3Shelly & Sands INC$429kRank 4Parella-pannunzio INC$496k
ItemQuantityR1Eclipse CO LLCR2Geauga Highway COR3Shelly & Sands INCR4Parella-pannunzio INC
614E11000 MAINTAINING TRAFFIC1 LS$45,258$20,000$27,855$6,500
441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG128 CY$353$370$321$426
304E20000 AGGREGATE BASE295 CY$107$150$98.00$160
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $95,643.42 2 $45,600.00 3 $97,804.00 4 $71,400.001 LS$29,020$12,000$22,000$24,500
203E10000 EXCAVATION799 CY$31.50$45.00$43.00$90.00
659E00300 TOPSOIL361 CY$58.50$85.00$82.00$120
611E04600 12" CONDUIT, TYPE C203 FT$84.00$85.00$112$110
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $56,857.75 2 $74,844.30 3 $69,733.50 4 $99,916.3513,000 EACH$1.00$1.00$1.00$1.00
608E52001 CURB RAMP, AS PER PLAN864 SF$11.75$32.00$38.00$34.00
619E16010 FIELD OFFICE, TYPE B6 MNTH$1,650$500$4,000$1,500
659E10000 SEEDING AND MULCHING3,247 SY$2.50$4.90$2.50$3.75
611E98470 CATCH BASIN, NO. 2-2B2 EACH$3,901$4,600$3,000$2,900
643E00630 CROSSWALK LINE, 24" Section 5 - TRAFFIC CONTROL - Totals Awd $10,254.88 2 $4,877.00 3 $8,729.50 4 $6,920.50176 FT$43.75$12.00$40.00$28.00
452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS Section 4 - PAVEMENT - Totals Awd $83,920.00 2 $104,850.00 3 $78,088.60 4 $109,804.8071 SY$95.75$180$110$110
832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA1 LS$6,516$3,000$6,670$14,500
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$6,419$6,600$18,874$18,950
204E10000 SUBGRADE COMPACTION1,836 SY$3.00$2.25$5.00$3.00
611E04900 12" CONDUIT, TYPE D54 FT$95.75$90.00$100$165
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$5,046$4,000$5,075$12,450
611E04900 12" CONDUIT, TYPE D, 706.0236 FT$127$96.00$200$220
Show all 51 line items
ItemQuantityR1Eclipse CO LLCR2Geauga Highway COR3Shelly & Sands INCR4Parella-pannunzio INC
201E11000 CLEARING AND GRUBBING1 LS$2,000$10,000$15,000$12,000
202E23000 PAVEMENT REMOVED139 SY$30.00$25.00$25.00$25.00
202E30000 WALK REMOVED106 SF$17.00$3.75$5.00$7.00
202E98100 REMOVAL MISC.:BOLLARD9 EACH$60.00$250$105$50.00
202E98100 REMOVAL MISC.:INSPECTION WELL1 EACH$210$1,100$650$100
202E98200 REMOVAL MISC.:CONDUIT10 FT$30.00$12.50$50.00$40.00
203E20000 EMBANKMENT57 CY$16.25$25.00$201$150
203E20001 EMBANKMENT, AS PER PLAN50 CY$22.00$45.00$20.00$75.00
204E13000 EXCAVATION OF SUBGRADE25 CY$29.00$75.00$25.00$30.00
204E30010 GRANULAR MATERIAL, TYPE B25 CY$88.25$100$91.00$110
204E45001 PROOF ROLLING, AS PER PLAN2 HOUR$278$150$370$125
204E50000 GEOTEXTILE FABRIC73 SY$9.25$6.00$3.00$18.00
608E10000 4" CONCRETE WALK215 SF$11.50$15.50$14.00$19.00
690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS1 LS$2,404$6,500$5,000$5,000
690E98400 SPECIAL - SURVEY CONTROL VERIFICATION Section 1 - ROADWAY - Totals Awd $62,455.25 2 $107,202.00 3 $126,795.00 4 $157,160.001 LS$1,540$3,500$5,000$6,750
659E20000 COMMERCIAL FERTILIZER0.5 TON$1,033$12.00$1,010$975
659E35000 WATER20 MGAL$1.00$12.00$1.00$10.00
670E00500 SLOPE EROSION PROTECTION1,346 SY$1.75$5.50$1.50$3.10
832E15000 STORM WATER POLLUTION PREVENTION PLAN1 LS$2,860$2,600$2,800$3,500
832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS1 LS$2,354$2,000$7,000$8,560
602E20000 CONCRETE MASONRY0.42 CY$5,109$2,600$5,000$4,200
611E97400 CONDUIT, MISC.:TYPE B FOR DRAINAGE DISCHARGE CONTI5 FT$65.00$200$98.00$100
611E97400 CONDUIT, MISC.:TYPE C FOR DRAINAGE DISCHARGE CONTI5 FT$65.00$200$98.00$100
611E97400 CONDUIT, MISC.:TYPE E FOR DRAINAGE DISCHARGE CONTI5 FT$65.00$200$98.00$100
611E97400 CONDUIT, MISC.:TYPE F FOR DRAINAGE DISCHARGE CONTI5 FT$65.00$255$98.00$100
611E99720 INSPECTION WELL Section 3 - DRAINAGE - Totals Awd $40,619.93 2 $43,138.00 3 $46,646.00 4 $50,624.001 EACH$2,570$3,000$1,250$1,900
407E20000 NON-TRACKING TACK COAT92 GAL$3.25$5.00$3.05$2.90
630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST44 FT$47.50$35.00$23.00$20.00
630E80100 SIGN, FLAT SHEET1.5 SF$49.25$150$65.00$75.00
630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION4 EACH$97.75$250$145$250
616E10000 WATER Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $248.75 2 $50.00 3 $1,500.00 4 $500.005 MGAL$49.75$10.00$300$100

Project details

Description
MAH-Sheridan Rd (Poland)
Type of work
Safety

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →