BEL-SR 147-25.40 (PART 1 AND PART 2)
BEL County · est $0.3M
Bid dateThursday, March 8—
BEL County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 43 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Ohio-west Virginia Excavating CO | R3Alan Stone CO INC | R4Suburban Maintenance & Construction | R5R C Construction Company And Son | % of bid |
|---|---|---|---|---|---|---|---|
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN(PART 1 AND PART 2 | 1 LS | $55,250 | $59,000 | $80,000 | $50,000 | $80,000 | 17% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 500 FT | $80.00 | $79.00 | $85.00 | $135 | $175 | 12% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 600 FT | $50.00 | $44.98 | $80.00 | $20.00 | $125 | 9% |
| 507E00400 STEEL PILES, MISC.: W16X45 STEEL BEAMS, FURNISHED | 1,100 FT | $25.00 | $28.00 | $23.00 | $29.00 | $40.00 | 8% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 151 SY | $145 | $178 | $135 | $95.00 | $150 | 7% |
| Item | Quantity | R1Shelly & Sands INC | R2Ohio-west Virginia Excavating CO | R3Alan Stone CO INC | R4Suburban Maintenance & Construction | R5R C Construction Company And Son |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,200 | $4,500 | $10,000 | $10,000 | $7,500 |
| 202E38000 GUARDRAIL REMOVED | 100 FT | $2.00 | $6.00 | $8.50 | $5.00 | $5.00 |
| 203E20000 EMBANKMENT | 13 CY | $55.00 | $118 | $11.00 | $15.00 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 174 SY | $2.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 220 FT |
| $90.00 |
| $80.00 |
| $61.00 |
| $130 |
| $175 |
| 6% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 320 FT | $60.00 | $48.00 | $64.00 | $35.00 | $125 | 6% |
| 507E00400 STEEL PILES, MISC.: W16X45 STEEL BEAMS, FURNISHED | 600 FT | $25.00 | $29.00 | $23.00 | $29.00 | $40.00 | 5% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 89 SY | $150 | $160 | $134 | $95.00 | $150 | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 47 CY | $262 | $320 | $315 | $387 | $325 | 4% |
| 611E02601 8" CONDUIT, TYPE F, AS PER PLAN | 350 FT | $35.00 | $40.00 | $16.00 | $10.00 | $55.00 | 4% |
| 304E20000 AGGREGATE BASE | 139 CY | $80.00 | $105 | $90.00 | $65.00 | $75.00 | 3% |
| 624E10000 MOBILIZATION(PART 1 AND PART 2) | 1 LS | $10,000 | $6,500 | $40,000 | $63,000 | $30,000 | 3% |
| 202E23000 PAVEMENT REMOVED | 350 SY | $25.00 | $23.00 | $15.00 | $20.00 | $40.00 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 22 CY | $312 | $300 | $315 | $387 | $325 | 2% |
| 304E20000 AGGREGATE BASE | 68 CY | $90.00 | $145 | $96.00 | $65.00 | $75.00 | 2% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (16 CY | $366 | $365 | $368 | $365 | $525 | 2% |
| 202E23000 PAVEMENT REMOVED | 185 SY | $30.00 | $28.00 | $22.00 | $20.00 | $40.00 | 2% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 12 CY | $445 | $435 | $447 | $450 | $600 | 2% |
| 507E00200 STEEL PILES HP12X53, FURNISHED | 150 FT | $35.00 | $28.00 | $30.00 | $33.00 | $40.00 | 2% |
| $6.00 |
| $3.00 |
| $5.00 |
| $2.00 |
| 606E15150 GUARDRAIL, TYPE MGS HALF POST SPACING | 100 FT | $32.60 | $39.00 | $35.00 | $45.00 | $45.00 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 194 SY | $6.50 | $7.00 | $7.00 | $2.50 | $20.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98471 CATCH BASIN, NO. 2-2B, AS PER PLAN | 1 EACH | $2,000 | $2,500 | $2,940 | $5,000 | $3,500 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 408 FT | $1.50 | $2.50 | $6.50 | $4.00 | $7.00 |
| 407E10000 TACK COAT | 9 GAL | $2.00 | $26.00 | $3.00 | $3.00 | $15.00 |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 6 CY | $554 | $535 | $447 | $425 | $600 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (8 CY | $423 | $440 | $368 | $350 | $525 |
| 621E00100 RPM | 4 EACH | $325 | $390 | $342 | $1,250 | $1,300 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 4 EACH | $30.00 | $100 | $11.00 | $50.00 | $50.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 3 EACH | $6.40 | $14.00 | $7.00 | $10.00 | $20.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.06 MILE | $9,100 | $10,500 | $9,552 | $9,100 | $10,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.02 MILE | $26,300 | $31,500 | $27,604 | $26,300 | $27,000 |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,200 | $4,600 | $4,025 | $10,000 | $7,500 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 10 FT | $35.00 | $184 | $41.00 | $50.00 | $40.00 |
| 202E38000 GUARDRAIL REMOVED | 150 FT | $2.00 | $8.00 | $5.50 | $5.00 | $5.00 |
| 203E20000 EMBANKMENT | 32 CY | $35.00 | $47.00 | $17.00 | $15.00 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 368 SY | $2.50 | $3.00 | $2.00 | $5.00 | $2.00 |
| 606E15150 GUARDRAIL, TYPE MGS HALF POST SPACING | 125 FT | $32.60 | $40.00 | $35.00 | $45.00 | $45.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 1 EACH | $1,345 | $1,600 | $1,412 | $1,500 | $2,100 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 394 SY | $6.00 | $6.50 | $7.00 | $2.50 | $20.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E04400 12" CONDUIT, TYPE B | 8 FT | $130 | $300 | $209 | $100 | $125 |
| 611E98471 CATCH BASIN, NO. 2-2B, AS PER PLAN | 1 EACH | $2,000 | $2,500 | $2,940 | $5,000 | $3,500 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 648 FT | $1.50 | $3.50 | $6.00 | $5.00 | $7.00 |
| 407E10000 TACK COAT | 18 GAL | $2.00 | $32.00 | $3.00 | $3.00 | $15.00 |
| 621E00100 RPM | 6 EACH | $325 | $390 | $342 | $1,100 | $1,000 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 6 EACH | $20.00 | $100 | $11.00 | $500 | $50.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 4 EACH | $6.50 | $15.00 | $7.00 | $10.00 | $20.00 |
| 630E85101 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION, AS | 1 EACH | $345 | $102 | $363 | $200 | $75.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.12 MILE | $4,875 | $5,800 | $5,117 | $4,875 | $5,500 |
| 642E00300 CENTER LINE, TYPE 1 | 0.05 MILE | $11,000 | $13,000 | $11,546 | $11,000 | $12,500 |
| 503E21101 UNCLASSIFIED EXCAVATION, AS PER PLAN | 39 CY | $80.00 | $129 | $21.00 | $15.00 | $40.00 |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 3 CY | $375 | $668 | $806 | $750 | $250 |
| 511E71100 CONCRETE, MISC.: CAST-IN-PLACE CONCRETE LAGGING | 1 CY | $3,000 | $2,200 | $3,601 | $2,200 | $2,500 |
| 511E81300 CONCRETE, MISC.: 8"x24"x45" PRECAST CONCRETE LAGGI | 12 EACH | $300 | $434 | $292 | $400 | $250 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 8 CY | $185 | $340 | $400 | $70.00 | $75.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,900 | $6,100 | $4,000 | $10,000 | $22,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING(PART 1 AN | 1 LS | $4,847 | $1,800 | $11,000 | $7,000 | $20,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN(PART 1 AND PART 2 | 1 LS | $55,250 | $55k | 14% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 500 FT | $80 | $40k | 10% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 600 FT | $50 | $30k | 8% |
| 507E00400 STEEL PILES, MISC.: W16X45 STEEL BEAMS, FURNISHED | 1,100 FT | $25 | $28k | 7% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 151 SY | $145 | $22k | 6% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 220 FT | $90 | $20k | 5% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 320 FT | $60 | $19k | 5% |
| 507E00400 STEEL PILES, MISC.: W16X45 STEEL BEAMS, FURNISHED | 600 FT | $25 | $15k | 4% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 89 SY | $150 | $13k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 47 CY | $262 | $12k | 3% |