ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 35 more items below.
| Item | Quantity | R1Mike Pusateri Excavating INC | R2Shelly & Sands INC | R3S E T INC | R4R C Construction Company And Son INC | % of bid |
|---|---|---|---|---|---|---|
| 204E30010 GRANULAR MATERIAL, TYPE B | 802 CY | $55.00 | $50.00 | $66.13 | $75.00 | 19% |
| 622E41000 PORTABLE BARRIER, 32" | 610 FT | $51.00 | $25.00 | $40.00 | $25.00 | 14% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 193 SY | $124 | $70.00 | $131 | $195 | 10% |
| 204E13000 EXCAVATION OF SUBGRADE | 802 CY | $19.00 | $24.00 | $25.00 | $20.00 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 60 CY | $242 | $300 | $200 | $375 | 6% |
| 304E20000 AGGREGATE BASE | 97 CY | $120 | $75.00 | $61.00 | $75.00 |
| Item | Quantity | R1Mike Pusateri Excavating INC | R2Shelly & Sands INC | R3S E T INC | R4R C Construction Company And Son INC |
|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $300 | $450 | $400 | $1,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 91 FT | $29.00 | $34.00 | $30.00 | $250 |
| 202E38000 GUARDRAIL REMOVED | 112.5 FT | $5.45 | $6.00 | $3.00 | $5.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $250 | $450 | $300 | $1,000 |
| 204E10000 SUBGRADE COMPACTION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 5% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 4 EACH | $2,600 | $1,900 | $2,070 | $2,000 | 5% |
| 203E20000 EMBANKMENT | 402 CY | $23.00 | $26.00 | $20.00 | $50.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,680 | $41,000 | $15,100 | $30,000 | 4% |
| 660E20000 SODDING REINFORCED | 59 SY | $125 | $10.00 | $21.00 | $250 | 3% |
| 611E10400 24" CONDUIT, TYPE B | 48 FT | $146 | $100 | $97.00 | $200 | 3% |
| 659E00300 TOPSOIL | 213 CY | $30.00 | $18.00 | $60.00 | $50.00 | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (16 CY | $396 | $410 | $600 | $450 | 3% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 11 CY | $495 | $580 | $850 | $450 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,350 | $10,000 | $5,000 | $10,000 | 2% |
| 202E23000 PAVEMENT REMOVED | 376 SY | $14.00 | $11.00 | $14.00 | $40.00 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $5,000 | $10,000 | $39,000 | $20,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,250 | $8,145 | $4,000 | $15,000 | 2% |
| 203E10000 EXCAVATION | 177 CY | $24.00 | $33.00 | $15.00 | $20.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,960 | $2,000 | $5,040 | $22,000 | 2% |
| 412 SY |
| $2.00 |
| $1.80 |
| $2.00 |
| $2.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $250 | $210 | $250 | $100 |
| 606E15050 GUARDRAIL, TYPE MGS | 112.5 FT | $28.00 | $31.00 | $40.00 | $55.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 2 CY | $400 | $310 | $80.00 | $750 |
| 659E10000 SEEDING AND MULCHING | 637 SY | $3.00 | $5.00 | $7.00 | $5.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 32 SY | $3.00 | $0.75 | $1.00 | $0.25 |
| 659E20000 COMMERCIAL FERTILIZER | 0.1 TON | $800 | $520 | $600 | $2,000 |
| 659E31000 LIME | 0.1 ACRE | $750 | $100 | $115 | $1,000 |
| 659E35000 WATER | 4 MGAL | $6.00 | $1.00 | $2.00 | $1.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.5 CY | $2,500 | $1,600 | $1,863 | $2,500 |
| 605E06000 4" BASE PIPE UNDERDRAINS | 102 FT | $26.00 | $13.00 | $14.00 | $75.00 |
| 605E31100 AGGREGATE DRAINS | 21 FT | $35.00 | $50.00 | $32.00 | $20.00 |
| 611E00100 4" CONDUIT, TYPE B | 27 FT | $35.00 | $31.00 | $22.00 | $20.00 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 25 FT | $35.00 | $32.00 | $24.00 | $50.00 |
| 611E07600 18" CONDUIT, TYPE C | 8 FT | $86.85 | $165 | $115 | $275 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $2,850 | $1,700 | $1,414 | $3,500 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $175 | $400 | $319 | $150 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 60 FT | $9.00 | $4.00 | $3.00 | $50.00 |
| 407E10000 TACK COAT | 19 GAL | $27.50 | $2.00 | $5.00 | $10.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 26 GAL | $55.00 | $3.00 | $22.00 | $25.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 3 EACH | $30.00 | $5.00 | $6.00 | $20.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.2 MILE | $5,875 | $5,500 | $8,173 | $12,500 |
| 642E00300 CENTER LINE, TYPE 1 | 0.1 MILE | $11,670 | $11,000 | $8,360 | $12,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 14 EACH | $56.00 | $53.00 | $10.00 | $20.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 14 EACH | $56.00 | $53.00 | $15.00 | $20.00 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.08 MILE | $22,475 | $9,500 | $9,900 | $65,000 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.41 MILE | $8,870 | $6,400 | $6,700 | $12,500 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 24 FT | $14.00 | $4.00 | $5.00 | $50.00 |
| 615E10001 ROADS FOR MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $3,800 | $5,000 | $18,000 | $15,000 |
| 616E10000 WATER | 5 MGAL | $2.00 | $100 | $2.00 | $1.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 204E30010 GRANULAR MATERIAL, TYPE B | 802 CY | $55 | $44k | 16% |
| 622E41000 PORTABLE BARRIER, 32" | 610 FT | $51 | $31k | 12% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 193 SY | $124 | $24k | 9% |
| 204E13000 EXCAVATION OF SUBGRADE | 802 CY | $19 | $15k | 6% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 60 CY | $242 | $15k | 5% |
| 304E20000 AGGREGATE BASE | 97 CY | $120 | $12k | 4% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 4 EACH | $2,600 | $10k | 4% |
| 203E20000 EMBANKMENT | 402 CY | $23 | $9k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,680 | $9k | 3% |
| 660E20000 SODDING REINFORCED | 59 SY | $125 | $7k | 3% |