WAS-IR 77-06.02
WAS County · est $0.3M
Bid dateFriday, June 1—
WAS County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Foill INC | R3R C Construction Company And Son | R4INC Parker Corporation | % of bid |
|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 19,813 CY | $11.50 | $13.61 | $11.00 | $16.00 | 72% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,000 | $2,728 | $10,000 | $35,000 | 8% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $12,000 | $7,227 | $35,000 | $10,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $23,630 | $15,000 | $10,650 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,655 | $8,352 | $15,000 | $10,000 | 3% |
| 659E10000 SEEDING AND MULCHING | 9,069 SY | $0.80 | $1.43 | $5.00 | $1.00 | 2% |
| Item | Quantity | R1Shelly & Sands INC | R2Foill INC | R3R C Construction Company And Son | R4INC Parker Corporation |
|---|---|---|---|---|---|
| 659E35000 WATER | 25 MGAL | $2.00 | $1.65 | $1.00 | $0.05 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (1 WAY) | 3 EACH | $9.00 | $64.17 | $50.00 | $6.40 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $60.00 | $93.50 | $125 | $85.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 601E26000 DUMPED ROCK FILL, TYPE B |
| 70 CY |
| $100 |
| $118 |
| $75.00 |
| $75.00 |
| 2% |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $5,000 | $6,380 | $8,000 | $10,000 | 2% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 606E16500 GUARDRAIL REBUILT, TYPE 5 | 108 FT | $22.50 | $28.16 | $30.00 | $25.60 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $1,750 | $5,777 | $18,000 | $6,500 | 1% |
| 606E35010 BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 1 | 1 EACH | $1,500 | $1,628 | $1,500 | $1,480 | 0% |
| 606E27840 ANCHOR ASSEMBLY REBUILT, TYPE B | 1 EACH | $1,200 | $1,678 | $16,000 | $1,525 | 0% |
| 203E20000 EMBANKMENT | 32 CY | $31.00 | $24.62 | $20.00 | $16.00 | 0% |
| 202E38200 GUARDRAIL REMOVED FOR REUSE | 108 FT | $5.00 | $2.20 | $3.00 | $2.00 | 0% |
| 202E47200 BRIDGE TERMINAL ASSEMBLY REMOVED FOR REUSE | 1 EACH | $500 | $121 | $500 | $110 | 0% |
| 659E20000 COMMERCIAL FERTILIZER | 0.82 TON | $400 | $803 | $1,200 | $1,220 | 0% |
| 202E42806 ANCHOR ASSEMBLY REMOVED FOR REUSE | 1 EACH | $250 | $237 | $500 | $215 | 0% |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 1 EACH | $200 | $143 | $125 | $130 | 0% |
| 659E31000 LIME | 1.88 ACRE | $60.00 | $99.00 | $800 | $532 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E10000 EXCAVATION | 19,813 CY | $11.5 | $228k | 72% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,000 | $25k | 8% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $12,000 | $12k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,655 | $10k | 3% |
| 659E10000 SEEDING AND MULCHING | 9,069 SY | $0.8 | $7k | 2% |
| 601E26000 DUMPED ROCK FILL, TYPE B | 70 CY | $100 | $7k | 2% |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $5,000 | $5k | 2% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1 | $3k | 1% |
| 606E16500 GUARDRAIL REBUILT, TYPE 5 | 108 FT | $22.5 | $2k | 1% |