TUS-SR-SR 416-08.93
TUS County · est $0.2M
Bid dateThursday, July 12—
TUS County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 33 more items below.
| Item | Quantity | R1Stanley Miller Construction Company | R2Shelly & Sands INC | R3Tucson INC | R4Lockhart Concrete CO | R5Dennison Bridge INC | R6Rudzik Excavating INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 203E20000 EMBANKMENT | 1,716 CY | $20.00 | $12.00 | $20.00 | $12.00 | $31.00 | $36.00 | 17% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 76 CY | $266 | $375 | $300 | $275 | $350 | $305 | 10% |
| 611E11700 27" CONDUIT, TYPE A, 706.02, 707.01 | 82 FT | $220 | $209 | $205 |
| Item | Quantity | R1Stanley Miller Construction Company | R2Shelly & Sands INC | R3Tucson INC | R4Lockhart Concrete CO | R5Dennison Bridge INC | R6Rudzik Excavating INC |
|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 2 EACH | $200 | $250 | $650 | $100 | $200 | $600 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 54 FT | $10.00 | $18.00 | $35.00 | $10.00 | $25.00 | $22.00 |
| 202E38000 GUARDRAIL REMOVED | 590 FT | $3.00 | $1.85 | $2.50 | $5.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $759 |
| $300 |
| $258 |
| 9% |
| 304E20000 AGGREGATE BASE | 106 CY | $146 | $103 | $120 | $50.00 | $130 | $92.15 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $15,172 | $10,000 | $10,000 | $15,000 | $7,500 | $14,573 | 7% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $13,000 | $28,200 | $15,000 | $1,000 | $30,000 | $40,400 | 6% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 25 CY | $445 | $475 | $325 | $375 | $700 | $450 | 5% |
| 203E10000 EXCAVATION | 940 CY | $11.00 | $12.00 | $17.00 | $12.00 | $22.00 | $44.00 | 5% |
| 606E15050 GUARDRAIL, TYPE MGS | 437.5 FT | $20.78 | $19.60 | $22.00 | $20.00 | $21.00 | $22.00 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,565 | $9,750 | $7,000 | $17,500 | $4,000 | $4,500 | 4% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,588 | $4,850 | $7,000 | $5,000 | $7,000 | $7,700 | 4% |
| 659E00300 TOPSOIL | 190 CY | $33.00 | $6.00 | $50.00 | $25.00 | $35.00 | $30.00 | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (14 CY | $423 | $475 | $300 | $350 | $500 | $627 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,333 | $5,500 | $12,000 | $19,000 | $2,000 | $5,850 | 3% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 2 EACH | $2,567 | $2,125 | $2,350 | $2,000 | $2,100 | $2,500 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25" DEPTH) | 444 SY | $11.12 | $10.90 | $17.00 | $5.00 | $20.00 | $28.00 | 2% |
| 659E10000 SEEDING AND MULCHING | 1,709 SY | $2.50 | $1.35 | $2.00 | $1.00 | $2.00 | $2.60 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $2,500 | $4,000 | $9,700 | $3,500 | $4,235 | 1% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 125 FT | $21.39 | $22.80 | $25.00 | $19.00 | $22.00 | $26.00 | 1% |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 275 SY | $8.70 | $11.00 | $10.00 | $10.00 | $14.00 | $18.00 | 1% |
| $2.00 |
| $2.05 |
| 204E10000 SUBGRADE COMPACTION | 344 SY | $1.00 | $5.00 | $6.00 | $2.00 | $3.00 | $5.00 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 2 CY | $340 | $260 | $325 | $125 | $250 | $400 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $100 | $88.00 | $85.00 | $1,000 | $50.00 | $150 |
| 659E14000 REPAIR SEEDING AND MULCHING | 85 SY | $2.00 | $0.69 | $2.00 | $1.00 | $2.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.23 TON | $600 | $675 | $2,000 | $600 | $1,000 | $594 |
| 659E31000 LIME | 0.35 ACRE | $400 | $156 | $2,000 | $400 | $100 | $88.00 |
| 659E35000 WATER | 9 MGAL | $1.00 | $1.00 | $1.00 | $50.00 | $10.00 | $5.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1.1 CY | $1,531 | $2,100 | $1,850 | $1,500 | $2,000 | $2,695 |
| 605E31100 AGGREGATE DRAINS | 90 FT | $20.00 | $18.00 | $20.00 | $12.00 | $35.00 | $35.75 |
| 611E00900 6" CONDUIT, TYPE B | 50 FT | $5.00 | $20.00 | $40.00 | $12.00 | $5.00 | $31.30 |
| 611E01400 6" CONDUIT, TYPE E | 50 FT | $5.00 | $16.50 | $40.00 | $12.00 | $5.00 | $31.30 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $5.00 | $16.50 | $40.00 | $12.00 | $5.00 | $31.30 |
| 407E10000 TACK COAT | 53 GAL | $5.60 | $2.00 | $3.00 | $5.00 | $4.00 | $3.85 |
| 408E10001 PRIME COAT, AS PER PLAN | 74 GAL | $8.90 | $14.00 | $7.00 | $5.00 | $13.00 | $30.00 |
| 621E00100 RPM | 3 EACH | $200 | $300 | $775 | $75.00 | $500 | $900 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $15.00 | $37.50 | $75.00 | $15.00 | $50.00 | $100 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 9 EACH | $9.17 | $12.00 | $8.00 | $10.00 | $10.00 | $7.50 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.1 MILE | $8,700 | $7,800 | $8,500 | $7,000 | $15,000 | $14,025 |
| 642E00300 CENTER LINE, TYPE 1 | 0.05 MILE | $11,556 | $10,400 | $16,500 | $11,000 | $12,000 | $11,000 |
| 407E10000 TACK COAT | 15 GAL | $10.00 | $1.50 | $3.00 | $5.00 | $10.00 | $20.00 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $40.00 | $100 | $125 | $50.00 | $35.00 | $300 |
| 410E13000 TRAFFIC COMPACTED SURFACE, TYPE C | 10 CY | $40.00 | $100 | $115 | $50.00 | $40.00 | $300 |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 10 CY | $200 | $475 | $400 | $375 | $500 | $800 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $100 | $180 | $400 | $160 | $250 | $200 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.05 MILE | $1,000 | $12,070 | $16,000 | $13,000 | $15,000 | $15,000 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.1 MILE | $1,000 | $9,055 | $13,000 | $10,000 | $10,000 | $11,000 |
| 616E10000 WATER | 16 MGAL | $1.00 | $10.00 | $1.00 | $50.00 | $10.00 | $30.00 |
| 617E10100 COMPACTED AGGREGATE | 15 CY | $40.00 | $140 | $125 | $50.00 | $35.00 | $285 |
| 617E25000 WATER | 1 MGAL | $100 | $75.00 | $1.00 | $50.00 | $10.00 | $100 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E20000 EMBANKMENT | 1,716 CY | $20 | $34k | 16% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 76 CY | $266 | $20k | 9% |
| 611E11700 27" CONDUIT, TYPE A, 706.02, 707.01 | 82 FT | $220 | $18k | 8% |
| 304E20000 AGGREGATE BASE | 106 CY | $146 | $15k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $15,172 | $15k | 7% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $13,000 | $13k | 6% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 25 CY | $445 | $11k | 5% |
| 203E10000 EXCAVATION | 940 CY | $11 | $10k | 5% |
| 606E15050 GUARDRAIL, TYPE MGS | 437.5 FT | $20.78 | $9k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,565 | $9k | 4% |