BEL-US 250-09.18
BEL County · est $0.1M
Bid dateThursday, August 23—
BEL County · est $0.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 11 more items below.
| Item | Quantity | R1Dennison Bridge INC | R2Ohio-west Virginia Excavating CO | R3S E T INC | R4Shelly & Sands INC | R5Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $27,000 | $33,800 | $25,000 | $38,075 | $50,000 | 17% |
| 511E71100 CONCRETE, MISC.: CLASS QC1 CONCRETE FOR 6" REINFOR | 12 CY | $2,000 | $850 | $1,200 | $3,300 | $1,375 | 15% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 264 FT | $75.00 | $37.50 | $65.00 | $95.00 | $95.00 | 12% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 21 CY | $600 | $275 | $475 | $344 | $473 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $12,000 | $12,250 | $35,000 | $10,000 | $40,000 | 8% |
| 507E00100 STEEL PILES HP10X42, FURNISHED |
| Item | Quantity | R1Dennison Bridge INC | R2Ohio-west Virginia Excavating CO | R3S E T INC | R4Shelly & Sands INC | R5Alan Stone CO INC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $5,000 | $11,500 | $6,000 | $20,000 |
| 202E23000 PAVEMENT REMOVED | 101 SY | $14.00 | $20.00 | $15.00 | $27.50 | $14.00 |
| 203E10000 EXCAVATION | 15 CY | $55.00 | $25.00 | $85.00 | $24.00 | $30.00 |
| 203E20000 EMBANKMENT | 12 CY | $42.00 | $40.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 400 FT |
| $26.00 |
| $30.00 |
| $25.00 |
| $27.50 |
| $32.00 |
| 7% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 9 CY | $1,000 | $640 | $650 | $965 | $630 | 6% |
| 530E00600 SPECIAL - STRUCTURES, MISC.; 6" x 6" x 45" HARDWOO | 390 SF | $18.00 | $53.00 | $21.00 | $50.00 | $50.00 | 4% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 80 FT | $85.00 | $112 | $200 | $120 | $150 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,255 LB | $4.00 | $3.00 | $2.00 | $5.00 | $4.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.25" | 143 SY | $30.00 | $18.00 | $33.00 | $25.00 | $32.00 | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (5 CY | $700 | $590 | $550 | $496 | $525 | 2% |
| 202E98000 REMOVAL MISC.: RETAINING WALL | 1 LS | $2,500 | $8,500 | $10,500 | $6,700 | $26,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,500 | $2,430 | $5,000 | $2,100 | $2,500 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,500 | $555 | $5,000 | $5,200 | $7,000 | 2% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 70 SY | $34.00 | $32.00 | $28.00 | $50.00 | $50.00 | 2% |
| 304E20000 AGGREGATE BASE | 19 CY | $120 | $148 | $125 | $95.00 | $110 | 1% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 209 SY | $8.00 | $5.00 | $11.00 | $8.70 | $8.00 | 1% |
| 513E20000 WELDED STUD SHEAR CONNECTORS (3/4" x 3-3/16") | 80 EACH | $20.00 | $74.50 | $8.00 | $25.00 | $82.00 | 1% |
| 503E21100 UNCLASSIFIED EXCAVATION | 28 CY | $55.00 | $115 | $100 | $55.00 | $92.00 | 1% |
| $45.00 |
| $22.00 |
| $25.00 |
| 204E10000 SUBGRADE COMPACTION | 122 SY | $8.00 | $4.00 | $4.00 | $6.00 | $2.50 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 140 FT | $7.00 | $7.00 | $9.00 | $5.00 | $36.00 |
| 407E10000 TACK COAT | 18 GAL | $20.00 | $2.00 | $2.50 | $2.00 | $2.50 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.02 MILE | $25,000 | $2,500 | $25,000 | $22,500 | $23,616 |
| 642E00300 CENTER LINE, TYPE 1 | 0.03 MILE | $30,000 | $5,000 | $27,000 | $24,500 | $25,715 |
| 530E00600 SPECIAL - STRUCTURES, MISC.; 6" x 6" x 57" HARDWOO | 56 SF | $18.00 | $60.00 | $30.00 | $55.00 | $65.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $27,000 | $27k | 16% |
| 511E71100 CONCRETE, MISC.: CLASS QC1 CONCRETE FOR 6" REINFOR | 12 CY | $2,000 | $24k | 14% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 264 FT | $75 | $20k | 12% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 21 CY | $600 | $13k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $12,000 | $12k | 7% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 400 FT | $26 | $10k | 6% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 9 CY | $1,000 | $9k | 5% |
| 530E00600 SPECIAL - STRUCTURES, MISC.; 6" x 6" x 45" HARDWOO | 390 SF | $18 | $7k | 4% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 80 FT | $85 | $7k | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,255 LB | $4 | $5k | 3% |