| Item | Quantity | R1Beaver Excavating Company | R2Miller Bros Const INC | R3Rietschlin Construction INC | R4Eagle Bridge CO | % of bid |
|---|---|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 8,312 SF | $34.50 | $38.15 | $32.25 | $41.00 | 84% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10,000 | $20,000 | $10,000 | 3% |
| 607E23005 FENCE REBUILT, TYPE CLT, AS PER PLAN | 12 FT | $500 | $233 | $650 | $125 | 2% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 88 HOUR | $65.00 | $65.00 | $66.00 | $75.00 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,500 |
| Item | Quantity | R1Beaver Excavating Company | R2Miller Bros Const INC | R3Rietschlin Construction INC | R4Eagle Bridge CO |
|---|---|---|---|---|---|
| 659E00100 SOIL ANALYSIS TEST | 1 EACH | $50.00 | $50.00 | $55.00 | $200 |
| 659E20000 COMMERCIAL FERTILIZER | 0.02 TON | $600 | $600 | $850 | $1,250 |
| 659E31000 LIME | 0.31 ACRE | $30.00 | $30.00 | $100 | $10.00 |
| 659E35000 WATER | 8 MGAL | $1.00 | $1.00 | $20.00 | $10.00 |
| 611E00410 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1,000 |
| $40,500 |
| $2,000 |
| 2% |
| 659E10000 SEEDING AND MULCHING | 1,500 SY | $2.15 | $2.15 | $2.50 | $3.00 | 1% |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 1 MILE | $3,000 | $3,000 | $3,300 | $1,002 | 1% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $3,000 | $15,000 | $14,000 | $12,500 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $1,500 | $3,300 | $4,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,500 | $5,000 | $5,000 | $4,000 | 1% |
| 606E10810 SPECIAL - NOISE BARRIERPOST REMOVAL | 3 EACH | $545 | $400 | $790 | $1,500 | 0% |
| 606E10920 SPECIAL - NOISE BARRIERPANEL REMOVAL | 240 SF | $6.00 | $20.00 | $10.00 | $20.00 | 0% |
| 670E00701 DITCH EROSION PROTECTION, AS PER PLAN | 676 SY | $2.00 | $2.00 | $3.75 | $5.00 | 0% |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 1 SNMT | $1,000 | $1,200 | $1,320 | $1,700 | 0% |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 18 CY | $30.00 | $40.00 | $62.00 | $40.00 | 0% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 4 CY | $130 | $200 | $410 | $155 | 0% |
| 605E05200 4" UNCLASSIFIED PIPE UNDERDRAINS | 50 FT | $10.00 | $8.00 | $19.00 | $10.00 | 0% |
| 659E00300 TOPSOIL | 17 CY | $20.00 | $50.00 | $43.00 | $15.00 | 0% |
| 203E20000 EMBANKMENT | 4 CY | $50.00 | $40.00 | $180 | $125 | 0% |
| 30 FT |
| $5.00 |
| $12.00 |
| $31.00 |
| $15.00 |
| 616E10000 WATER | 5 MGAL | $40.00 | $100 | $20.00 | $20.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 606E10210 SPECIAL - NOISE BARRIER (REFLECTIVE) | 8,312 SF | $34.5 | $287k | 84% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 607E23005 FENCE REBUILT, TYPE CLT, AS PER PLAN | 12 FT | $500 | $6k | 2% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1 | $6k | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 88 HOUR | $65 | $6k | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,500 | $6k | 2% |
| 659E10000 SEEDING AND MULCHING | 1,500 SY | $2.15 | $3k | 1% |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 1 MILE | $3,000 | $3k | 1% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $3,000 | $3k | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $3k | 1% |