WAR-GEN SIGNS FY2020
WAR County · est $0.9M
Bid dateThursday, July 2—
WAR County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 18 more items below.
| Item | Quantity | R1Lake Erie Construction Company | R2A & A Safety INC | R3M P Dory CO | R4Cleveland Barricading Systems LLC | R5Security Fence Group INC | % of bid |
|---|---|---|---|---|---|---|---|
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 20,380 FT | $8.50 | $9.00 | $8.50 | $7.53 | $7.50 | 21% |
| 630E80100 SIGN, FLAT SHEET | 10,561 SF | $11.50 | $12.00 | $12.00 | $8.95 | $10.00 | 15% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 5,431 SF | $14.50 | $16.00 | $17.50 | $15.80 | $25.50 | 10% |
| 630E75000 |
| Item | Quantity | R1Lake Erie Construction Company | R2A & A Safety INC | R3M P Dory CO | R4Cleveland Barricading Systems LLC | R5Security Fence Group INC |
|---|---|---|---|---|---|---|
| 625E32000 GROUND ROD | 3 EACH | $280 | $300 | $475 | $575 | $575 |
| 690E98100 SPECIAL - MISC.: TREE TRIMMING | 160 FT | $14.40 | $20.00 | $25.00 | $15.00 | $45.00 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 367 FT | $18.00 | $12.50 | $10.50 | $20.20 | $20.00 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 175 FT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 161 EACH |
| $470 |
| $420 |
| $650 |
| $399 |
| $480 |
| 9% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 65 EACH | $875 | $850 | $750 | $1,440 | $1,500 | 7% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 3,395 SF | $14.00 | $15.00 | $16.50 | $17.30 | $21.00 | 6% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $28,700 | $1,800 | $20,000 | $37,500 | $30,000 | 4% |
| 630E79610 SIGN SUPPORT ASSEMBLY, BARRIER MOUNTED | 52 EACH | $485 | $450 | $250 | $550 | $595 | 3% |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 99 EACH | $230 | $390 | $325 | $360 | $380 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $22,270 | $20,000 | $20,000 | $56,700 | $20,000 | 3% |
| 630E21000 OVERHEAD SIGN SUPPORT, TYPE TC-12.30, DESIGN 10 | 1 EACH | $21,650 | $15,855 | $18,950 | $24,200 | $22,300 | 3% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1,961 EACH | $10.00 | $8.00 | $10.00 | $13.00 | $15.00 | 2% |
| 630E08601 SIGN POST REFLECTOR, AS PER PLAN | 549 EACH | $35.00 | $35.00 | $35.00 | $22.45 | $35.50 | 2% |
| 630E08000 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W12X30 | 422 FT | $45.00 | $36.00 | $30.50 | $37.00 | $42.00 | 2% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $1,400 | $900 | $500 | $650 | $1,500 | 2% |
| 630E84510 RIGID OVERHEAD SIGN SUPPORT FOUNDATION | 3 EACH | $5,050 | $4,690 | $5,500 | $5,750 | $5,700 | 2% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1,461 EACH | $10.00 | $12.00 | $12.00 | $17.00 | $25.00 | 2% |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 78 EACH | $180 | $245 | $250 | $280 | $275 | 2% |
| 632E80302 SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 3 | 2 EACH | $6,180 | $6,460 | $6,750 | $6,900 | $7,550 | 2% |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 55 EACH | $165 | $275 | $250 | $125 | $550 | 1% |
| $20.00 |
| $13.50 |
| $11.00 |
| $19.45 |
| $20.50 |
| 630E07500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X22 | 105 FT | $35.00 | $26.50 | $22.50 | $29.30 | $32.00 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 292 FT | $22.00 | $16.00 | $13.50 | $20.90 | $23.00 |
| 630E08004 ONE WAY SUPPORT, NO. 3 POST | 320 FT | $10.00 | $12.00 | $13.50 | $7.60 | $10.00 |
| 630E79000 SIGN HANGER ASSEMBLY, SPAN WIRE | 20 EACH | $295 | $275 | $375 | $220 | $250 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 38 EACH | $135 | $120 | $100 | $100 | $57.00 |
| 630E80600 SIGN, DOUBLE FACED, MILE MARKER | 80 EACH | $85.00 | $32.50 | $35.00 | $29.00 | $158 |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 60 EACH | $145 | $125 | $100 | $250 | $150 |
| 630E86310 REMOVAL OF STRUCTURE MOUNTED SIGN AND DISPOSAL | 3 EACH | $220 | $300 | $500 | $480 | $325 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 53 EACH | $15.00 | $20.00 | $20.00 | $32.00 | $25.00 |
| 630E89902 REMOVAL OF MISCELLANEOUS TRAFFIC CONTROL ITEM: BAR | 104 EACH | $10.00 | $15.00 | $20.00 | $22.00 | $17.50 |
| 630E89902 REMOVAL OF MISCELLANEOUS TRAFFIC CONTROL ITEM: BAR | 49 EACH | $15.00 | $35.00 | $50.00 | $75.00 | $20.00 |
| 614E11111 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $48.00 | $75.00 | $62.00 | $85.00 | $80.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,500 | $6,310 | $5,500 | $5,500 | $15,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,850 | $12,000 | $7,500 | $19,500 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 20,380 FT | $8.5 | $173k | 20% |
| 630E80100 SIGN, FLAT SHEET | 10,561 SF | $11.5 | $121k | 14% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 5,431 SF | $14.5 | $79k | 9% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 161 EACH | $470 | $76k | 9% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 65 EACH | $875 | $57k | 6% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 3,395 SF | $14 | $48k | 5% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $28,700 | $29k | 3% |
| 630E79610 SIGN SUPPORT ASSEMBLY, BARRIER MOUNTED | 52 EACH | $485 | $25k | 3% |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 99 EACH | $230 | $23k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $22,270 | $22k | 3% |