UNI-US 33I-00.00
UNI County · est $1.0M
Bid dateThursday, October 1—
UNI County · est $1.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 66 more items below.
| Item | Quantity | R1Shelly Company | R2Double Z Construction Company | R3Eagle Bridge CO | R4Complete General Construction Company | R5Rietschlin Construction INC | % of bid |
|---|---|---|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 1,729 CY | $110 | $110 | $100 | $110 | $126 | 22% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 1,258 CY | $140 | $140 | $135 | $140 | $161 | 20% |
| 622E10061 CONCRETE BARRIER, SINGLE SLOPE, TYPE B, AS PER PLA | 255 FT | $280 | $280 | $325 | $620 | $450 | 8% |
| 606E60028 |
| Item | Quantity | R1Shelly Company | R2Double Z Construction Company | R3Eagle Bridge CO | R4Complete General Construction Company | R5Rietschlin Construction INC |
|---|---|---|---|---|---|---|
| 202E32000 CURB REMOVED | 323 FT | $15.00 | $4.00 | $10.00 | $8.00 | $8.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 260 FT | $26.00 | $20.00 | $10.00 | $17.00 | $24.50 |
| 202E38001 GUARDRAIL REMOVED, AS PER PLAN | 1,775 FT | $2.80 | $2.00 | $2.00 | $2.00 | $4.50 |
| 202E42001 ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER PLAN |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 2 EACH |
| $28,000 |
| $35,000 |
| $28,350 |
| $31,320 |
| $35,850 |
| 6% |
| 624E10000 MOBILIZATION | 1 LS | $55,000 | $40,000 | $40,000 | $40,000 | $80,000 | 6% |
| 304E20000 AGGREGATE BASE | 1,413 CY | $37.50 | $70.00 | $40.00 | $52.00 | $70.00 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $45,000 | $40,000 | $65,000 | $90,000 | $64,000 | 5% |
| 202E30601 CONCRETE MEDIAN REMOVED, AS PER PLAN | 2,863 SY | $12.50 | $15.00 | $20.00 | $20.00 | $22.00 | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 1,843.75 FT | $15.80 | $17.20 | $17.20 | $17.20 | $20.00 | 3% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 1,852 SY | $15.25 | $9.00 | $25.00 | $12.00 | $17.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 1.5" | 22,342 SY | $1.15 | $2.00 | $1.00 | $1.15 | $1.40 | 3% |
| 251E01040 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 500 SY | $35.50 | $40.00 | $35.50 | $35.50 | $40.75 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 3" | 1,558 SY | $10.75 | $5.00 | $10.75 | $10.75 | $12.40 | 2% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 352 SY | $35.00 | $25.00 | $65.00 | $30.00 | $51.00 | 1% |
| 203E20001 EMBANKMENT, AS PER PLAN | 378 CY | $30.00 | $8.00 | $45.00 | $35.00 | $42.00 | 1% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $9,000 | $1,000 | $5,000 | $3,000 | $10,000 | 1% |
| 606E26151 ANCHOR ASSEMBLY, MGS TYPE E, AS PER PLAN (NCHRP350 | 4 EACH | $2,150 | $2,280 | $2,280 | $2,280 | $2,610 | 1% |
| 611E04600 12" CONDUIT, TYPE C | 200 FT | $42.00 | $70.00 | $60.00 | $70.00 | $50.00 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 2,571 GAL | $3.25 | $3.25 | $3.00 | $3.25 | $3.75 | 1% |
| 203E20000 EMBANKMENT | 263 CY | $30.50 | $8.00 | $20.00 | $30.00 | $31.00 | 1% |
| 6 EACH |
| $315 |
| $265 |
| $275 |
| $265 |
| $640 |
| 202E42011 ANCHOR ASSEMBLY REMOVED, TYPE E, AS PER PLAN | 1 EACH | $200 | $145 | $150 | $145 | $570 |
| 202E58200 INLET REMOVED | 4 EACH | $240 | $500 | $200 | $390 | $550 |
| 202E60010 MONUMENT ASSEMBLY REMOVED | 7 EACH | $240 | $50.00 | $50.00 | $125 | $340 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 65 FT | $74.00 | $20.00 | $30.00 | $21.00 | $65.00 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 240 FT | $21.50 | $20.00 | $10.00 | $27.00 | $15.00 |
| 204E10000 SUBGRADE COMPACTION | 6,353 SY | $0.75 | $1.00 | $1.00 | $2.75 | $1.50 |
| 204E45000 PROOF ROLLING | 4 HOUR | $185 | $100 | $125 | $275 | $170 |
| 209E10000 DITCH CLEANOUT | 485 FT | $15.75 | $7.00 | $10.00 | $12.00 | $5.00 |
| 209E60200 LINEAR GRADING | 20.5 STA | $100 | $70.00 | $50.00 | $320 | $512 |
| 209E98300 LINEAR GRADING, MISC.: SHOULDER GRADING | 695 SY | $6.00 | $3.00 | $2.50 | $3.00 | $8.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $925 | $1,020 | $1,020 | $1,020 | $1,170 |
| 606E98000 GUARDRAIL, MISC.: ALTERNATIVE GUARDRAIL PLACEMENT | 100 FT | $10.00 | $7.80 | $7.80 | $7.80 | $9.00 |
| 623E38501 MONUMENT ASSEMBLY, AS PER PLAN | 4 EACH | $1,050 | $800 | $600 | $880 | $950 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $3,750 | $3,000 | $7,500 | $9,000 | $11,000 |
| 659E00300 TOPSOIL | 231 CY | $30.00 | $20.00 | $50.00 | $32.00 | $48.00 |
| 659E10000 SEEDING AND MULCHING | 1,905 SY | $1.25 | $4.00 | $3.00 | $2.45 | $2.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 79 SY | $0.68 | $7.00 | $1.50 | $0.45 | $2.00 |
| 659E15000 INTER-SEEDING | 79 SY | $0.68 | $7.00 | $1.50 | $0.10 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.25 TON | $688 | $425 | $1,250 | $482 | $800 |
| 659E31000 LIME | 0.4 ACRE | $151 | $75.00 | $10.00 | $90.00 | $120 |
| 659E35000 WATER | 11 MGAL | $1.00 | $20.00 | $10.00 | $1.00 | $20.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 25 FT | $25.00 | $6.00 | $13.00 | $30.00 | $24.00 |
| 605E31100 AGGREGATE DRAINS | 50 FT | $18.00 | $20.00 | $10.00 | $10.00 | $16.00 |
| 611E01500 6" CONDUIT, TYPE F | 110 FT | $33.00 | $15.00 | $10.00 | $22.00 | $21.00 |
| 611E04400 12" CONDUIT, TYPE B, 706.02 | 5 FT | $127 | $100 | $160 | $155 | $510 |
| 611E98470 CATCH BASIN, NO. 2-2B | 2 EACH | $2,250 | $2,000 | $1,500 | $1,700 | $2,100 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $350 | $400 | $250 | $300 | $390 |
| 670E00700 DITCH EROSION PROTECTION | 248 SY | $1.45 | $2.00 | $3.00 | $2.85 | $5.00 |
| 609E98000 CURB, MISC.: VARIOUS TYPE CURB TRANSITION | 24 FT | $155 | $40.00 | $75.00 | $80.00 | $145 |
| 617E10100 COMPACTED AGGREGATE | 66 CY | $120 | $60.00 | $100 | $104 | $130 |
| 617E25000 WATER | 4 MGAL | $1.00 | $10.00 | $10.00 | $80.00 | $20.00 |
| 621E00100 RPM | 134 EACH | $40.00 | $34.95 | $34.95 | $34.95 | $44.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 134 EACH | $2.25 | $8.00 | $10.00 | $14.00 | $22.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, 1-WAY | 12 EACH | $10.00 | $10.00 | $7.50 | $7.50 | $9.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, 1-WAY | 25 EACH | $8.50 | $10.00 | $7.50 | $7.50 | $9.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 28 FT | $8.00 | $15.00 | $15.00 | $15.00 | $14.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 40 FT | $13.00 | $17.00 | $12.00 | $17.00 | $15.00 |
| 630E80100 SIGN, FLAT SHEET | 20 SF | $17.50 | $27.50 | $20.00 | $27.50 | $33.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 9 EACH | $20.00 | $20.00 | $30.00 | $10.00 | $35.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 9 EACH | $20.00 | $20.00 | $30.00 | $15.00 | $40.00 |
| 644E00104 EDGE LINE, 6" | 1.3 MILE | $4,200 | $4,265 | $4,200 | $4,265 | $4,500 |
| 644E00204 LANE LINE, 6" | 0.99 MILE | $1,800 | $2,080 | $1,800 | $2,080 | $2,300 |
| 644E00300 CENTER LINE | 0.63 MILE | $8,000 | $7,270 | $8,000 | $7,270 | $5,300 |
| 644E00400 CHANNELIZING LINE, 8" | 446 FT | $3.00 | $1.60 | $3.00 | $1.60 | $5.00 |
| 644E00500 STOP LINE | 34 FT | $10.00 | $9.00 | $10.00 | $9.00 | $9.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 64 FT | $8.00 | $8.35 | $8.00 | $8.35 | $9.00 |
| 644E01300 LANE ARROW | 2 EACH | $120 | $105 | $120 | $105 | $172 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 32 HOUR | $65.00 | $65.00 | $80.00 | $85.00 | $75.00 |
| 614E12460 WORK ZONE MARKING SIGN | 4 EACH | $85.00 | $50.00 | $85.00 | $200 | $136 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $900 | $500 | $1,000 | $1,200 | $1,100 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 2.04 MILE | $1,200 | $380 | $1,200 | $740 | $2,500 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.28 MILE | $2,000 | $850 | $2,000 | $1,120 | $2,800 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.9 MILE | $1,500 | $580 | $1,500 | $935 | $2,700 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 1,092 FT | $2.00 | $0.45 | $2.00 | $0.70 | $0.75 |
| 614E24610 WORK ZONE DOTTED LINE, CLASS III, 4", 642 PAINT | 550 FT | $1.50 | $0.40 | $1.50 | $0.60 | $0.75 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 68 FT | $5.00 | $2.35 | $5.00 | $3.00 | $3.00 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 4 EACH | $100 | $56.00 | $100 | $60.00 | $63.00 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 100 SF | $60.00 | $60.00 | $90.00 | $115 | $125 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 100 SF | $60.00 | $60.00 | $90.00 | $115 | $125 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $6,000 | $20,000 | $11,000 | $18,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $6,250 | $15,000 | $15,000 | $12,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 1,729 CY | $110 | $190k | 19% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 1,258 CY | $140 | $176k | 17% |
| 622E10061 CONCRETE BARRIER, SINGLE SLOPE, TYPE B, AS PER PLA | 255 FT | $280 | $71k | 7% |
| 606E60028 IMPACT ATTENUATOR, TYPE 2 (BIDIRECTIONAL) (60 MPH, | 2 EACH | $28,000 | $56k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $55,000 | $55k | 5% |
| 304E20000 AGGREGATE BASE | 1,413 CY | $37.5 | $53k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $45,000 | $45k | 4% |
| 202E30601 CONCRETE MEDIAN REMOVED, AS PER PLAN | 2,863 SY | $12.5 | $36k | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 1,843.75 FT | $15.8 | $29k | 3% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 1,852 SY | $15.25 | $28k | 3% |