OTT-SR 105-04.11 Slide repair
OTT County · est $0.2M
Bid dateThursday, February 25—
OTT County · est $0.2M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 5 more items below.
| Item | Quantity | R1Mark Haynes Construction INC | R2Great Lakes Demolition Company | R3Eclipse CO LLC | R4Geddis Paving & Excavating INC | R5Vernon Nagel INC | R6Mason Dixon Energy Services LLC | R7Unilliance INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 601E21100 SLOPE PROTECTION, MISC.:GREENLOXX NON-MSE LIVING W | 305 SY | $240 | $332 | $307 | $360 | $458 | $585 | $628 | 45% |
| 601E28101 DUMPED ROCK FILL, AS PER PLAN | 164 CY | $95.00 | $110 | $82.50 | $140 | $125 | $70.00 | $244 | 9% |
| Item | Quantity | R1Mark Haynes Construction INC | R2Great Lakes Demolition Company | R3Eclipse CO LLC | R4Geddis Paving & Excavating INC | R5Vernon Nagel INC | R6Mason Dixon Energy Services LLC | R7Unilliance INC |
|---|---|---|---|---|---|---|---|---|
| 202E38200 GUARDRAIL REMOVED FOR REUSE | 150 FT | $3.00 | $4.00 | $2.50 | $2.50 | $4.00 | $20.00 | $4.50 |
| 304E20000 AGGREGATE BASE | 12 CY | $32.00 | $70.00 | $79.50 | $108 | $125 | $68.00 | $400 |
| 407E20000 NON-TRACKING TACK COAT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 10 CY |
| $780 |
| $467 |
| $355 |
| $650 |
| $650 |
| $750 |
| $1,300 |
| 5% |
| 624E10000 MOBILIZATION | 1 LS | $7,625 | $14,500 | $34,593 | $13,500 | $10,000 | $25,000 | $85,000 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,000 | $4,000 | $7,500 | $15,000 | $20,000 | $10,000 | $110,000 | 4% |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 67 CY | $100 | $75.00 | $65.50 | $70.00 | $50.00 | $50.00 | $385 | 4% |
| 609E10000 ASPHALT CONCRETE CURB, TYPE 1 | 90 FT | $72.00 | $23.50 | $45.00 | $71.00 | $60.00 | $90.00 | $120 | 4% |
| 661E99930 PLANTING, MISC.:CONTAINER TREES AS PER PLAN | 200 SY | $30.00 | $34.00 | $54.00 | $52.00 | $52.00 | $30.00 | $75.00 | 4% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 4 CY | $1,440 | $539 | $520 | $1,200 | $1,200 | $1,300 | $2,400 | 4% |
| 606E15101 GUARDRAIL, TYPE MGS WITH LONG POSTS, AS PER PLAN | 150 FT | $38.00 | $27.00 | $36.00 | $37.00 | $27.00 | $55.00 | $31.50 | 3% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 203E10000 EXCAVATION | 82 CY | $40.00 | $20.00 | $39.00 | $22.00 | $40.00 | $65.00 | $300 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,000 | $4,500 | $11,000 | $10,000 | $2,500 | $19,922 | $75,000 | 2% |
| 203E22000 EMBANKMENT, USING NATURAL SOILS, 703.16.A | 67 CY | $40.00 | $20.00 | $64.00 | $36.00 | $100 | $65.00 | $300 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $2,500 | $1,000 | $1,872 | $27,500 | $10,000 | $800 | $100,000 | 2% |
| 203E57000 SPECIAL - SCALPING | 400 SY | $4.00 | $10.00 | $12.00 | $4.00 | $18.00 | $55.00 | $75.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $1,600 | $10,000 | $5,000 | $3,000 | $4,500 | $6,832 | $10,000 | 1% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 200 SY | $7.00 | $2.00 | $18.50 | $18.00 | $22.00 | $25.00 | $175 | 1% |
| 202E23000 PAVEMENT REMOVED | 24 SY | $35.00 | $15.00 | $44.00 | $75.00 | $50.00 | $30.00 | $200 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $600 | $2,500 | $9,500 | $3,000 | $2,500 | $4,000 | $15,000 | 0% |
| 5 GAL |
| $1.25 |
| $5.00 |
| $16.00 |
| $1.00 |
| $1.00 |
| $12.00 |
| $2.00 |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 30 LB | $12.00 | $30.00 | $15.50 | $10.00 | $10.00 | $12.00 | $20.00 |
| 662E30000 LANDSCAPE WATERING | 1 MGAL | $10.00 | $20.00 | $260 | $250 | $250 | $75.00 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 601E21100 SLOPE PROTECTION, MISC.:GREENLOXX NON-MSE LIVING W | 305 SY | $240 | $73k | 44% |
| 601E28101 DUMPED ROCK FILL, AS PER PLAN | 164 CY | $95 | $16k | 9% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 10 CY | $780 | $8k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $7,625 | $8k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,000 | $7k | 4% |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 67 CY | $100 | $7k | 4% |
| 609E10000 ASPHALT CONCRETE CURB, TYPE 1 | 90 FT | $72 | $6k | 4% |
| 661E99930 PLANTING, MISC.:CONTAINER TREES AS PER PLAN | 200 SY | $30 | $6k | 4% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 4 CY | $1,440 | $6k | 3% |
| 606E15101 GUARDRAIL, TYPE MGS WITH LONG POSTS, AS PER PLAN | 150 FT | $38 | $6k | 3% |