BEL-SR 147-16.14
BEL County · est $0.3M
Bid dateThursday, October 14—
BEL County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Alan Stone CO INC | R3Shelly & Sands INC | R4Rock Forge Bridge Company, LLC | % of bid |
|---|---|---|---|---|---|---|
| 507E00201 STEEL PILES HP12X53, FURNISHED, AS PER PLAN | 905 FT | $45.00 | $50.00 | $46.00 | $49.00 | 19% |
| 511E81300 CONCRETE, MISC.: 8"x24"x57" PRECAST CONCRETE LAGGI | 105 EACH | $200 | $195 | $225 | $260 | 10% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 85 CY | $230 | $255 | $255 | $290 | 9% |
| 503E21101 UNCLASSIFIED EXCAVATION, AS PER PLAN | 222 CY | $75.00 | $29.50 | $30.00 | $47.00 | 8% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 288 FT | $57.00 | $53.00 | $93.00 | $105 | 8% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 414 FT | $30.00 | $41.00 | $55.00 |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Alan Stone CO INC | R3Shelly & Sands INC | R4Rock Forge Bridge Company, LLC |
|---|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 250 FT | $5.00 | $3.50 | $2.00 | $4.40 |
| 203E10000 EXCAVATION | 41 CY | $35.00 | $19.50 | $9.00 | $73.00 |
| 203E20000 EMBANKMENT | 82 CY | $33.00 | $8.00 | $24.00 | $59.00 |
| 204E10000 SUBGRADE COMPACTION | 374 SY | $3.00 | $2.50 | $5.00 | $8.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $73.00 |
| 6% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 26 CY | $450 | $377 | $425 | $890 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $10,500 | $11,000 | $10,000 | $100,900 | 5% |
| 606E15151 GUARDRAIL, TYPE MGS HALF POST SPACING, AS PER PLAN | 162.5 FT | $47.00 | $57.00 | $43.20 | $52.00 | 4% |
| 304E20000 AGGREGATE BASE | 70 CY | $100 | $110 | $95.00 | $130 | 3% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 35 CY | $200 | $100 | $210 | $165 | 3% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 59 CY | $95.00 | $170 | $200 | $170 | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (16 CY | $340 | $395 | $395 | $450 | 3% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 12 CY | $400 | $570 | $570 | $650 | 2% |
| 202E23000 PAVEMENT REMOVED | 319 SY | $15.00 | $6.00 | $14.00 | $36.00 | 2% |
| 606E15201 GUARDRAIL, TYPE MGS HALF POST SPACING WITH LONG PO | 87.5 FT | $53.00 | $64.50 | $46.80 | $59.00 | 2% |
| 617E10100 COMPACTED AGGREGATE | 35 CY | $120 | $131 | $125 | $225 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,500 | $4,900 | $6,000 | $6,920 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $2,000 | $2,550 | $5,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $4,800 | $4,720 | $3,240 | 2% |
| $250 |
| $136 |
| $146 |
| $225 |
| 659E00300 TOPSOIL | 40 CY | $25.00 | $24.50 | $25.00 | $325 |
| 659E10000 SEEDING AND MULCHING | 356 SY | $3.00 | $4.50 | $6.55 | $11.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.05 TON | $700 | $680 | $775 | $4,510 |
| 659E31000 LIME | 0.07 ACRE | $100 | $989 | $165 | $4,620 |
| 659E35000 WATER | 5 MGAL | $1.00 | $124 | $1.00 | $1.10 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99711 PRECAST REINFORCED CONCRETE OUTLET, AS PER PLAN | 1 EACH | $350 | $311 | $225 | $1,340 |
| 407E10000 TACK COAT | 55 GAL | $10.00 | $2.00 | $2.00 | $2.30 |
| 408E10001 PRIME COAT, AS PER PLAN | 22 GAL | $5.00 | $29.00 | $29.00 | $33.00 |
| 621E00100 RPM | 7 EACH | $400 | $495 | $400 | $455 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 7 EACH | $65.00 | $44.50 | $25.00 | $72.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 4 EACH | $12.00 | $15.00 | $10.00 | $14.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.05 MILE | $7,650 | $9,500 | $7,650 | $8,690 |
| 642E00300 CENTER LINE, TYPE 1 | 0.05 MILE | $7,925 | $9,800 | $7,925 | $9,010 |
| 614E12420 DETOUR SIGNING | 1 LS | $3,000 | $3,600 | $3,000 | $3,350 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.05 MILE | $9,700 | $12,000 | $9,650 | $11,000 |
| 616E10000 WATER | 10 MGAL | $1.00 | $12.50 | $25.00 | $1.10 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 180 FT | $15.00 | $7.50 | $5.00 | $33.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 6 FT | $25.00 | $39.50 | $40.00 | $175 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $3,000 | $5,000 | $5,000 | $3,240 |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $750 | $500 | $3,000 | $3,750 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00201 STEEL PILES HP12X53, FURNISHED, AS PER PLAN | 905 FT | $45 | $41k | 17% |
| 511E81300 CONCRETE, MISC.: 8"x24"x57" PRECAST CONCRETE LAGGI | 105 EACH | $200 | $21k | 9% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 85 CY | $230 | $20k | 8% |
| 503E21101 UNCLASSIFIED EXCAVATION, AS PER PLAN | 222 CY | $75 | $17k | 7% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 288 FT | $57 | $16k | 7% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 414 FT | $30 | $12k | 5% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 26 CY | $450 | $12k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $10,500 | $11k | 4% |
| 606E15151 GUARDRAIL, TYPE MGS HALF POST SPACING, AS PER PLAN | 162.5 FT | $47 | $8k | 3% |
| 304E20000 AGGREGATE BASE | 70 CY | $100 | $7k | 3% |