GAL-SR 218-10.26
GAL County · est $0.6M
Bid dateThursday, October 14—
GAL County · est $0.6M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.
| Item | Quantity | R1Allard Excavation LLC | R2D G M INC | R3Skeens Excavating INC | R4Alan Stone CO INC | R5Craig Edward Susany INC | R6Shelly & Sands INC | R7Ohio-west Virginia Excavating CO | R8George J Igel & CO INC | R9Dot Construction CORP | R10Rock Forge Bridge Company, LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES W21x101 | 1,750 FT | $98.10 | $94.00 | $91.00 | $101 | $88.00 | $90.00 | $79.25 | $105 | $100 | $95.17 | 32% |
| Item | Quantity | R1Allard Excavation LLC | R2D G M INC | R3Skeens Excavating INC | R4Alan Stone CO INC | R5Craig Edward Susany INC | R6Shelly & Sands INC | R7Ohio-west Virginia Excavating CO | R8George J Igel & CO INC | R9Dot Construction CORP | R10Rock Forge Bridge Company, LLC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,200 | $11,000 | $2,500 | $5,000 | $1,000 | $1,000 | $3,725 | $1,500 | $5,000 | $3,416 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE |
| 1,092 FT |
| $65.75 |
| $87.00 |
| $91.00 |
| $76.00 |
| $91.00 |
| $70.00 |
| $69.75 |
| $87.50 |
| $175 |
| $66.87 |
| 13% |
| 530E00400 SPECIAL - STRUCTURES - PRECAST CONCRETE PANEL | 187 EACH | $261 | $295 | $135 | $208 | $140 | $350 | $226 | $280 | $300 | $282 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $8,000 | $7,900 | $23,000 | $10,000 | $20,000 | $45,400 | $35,000 | $35,000 | $100,173 | 6% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 271 CY | $90.00 | $70.00 | $150 | $63.00 | $90.00 | $125 | $78.50 | $100 | $100 | $141 | 5% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 79 CY | $265 | $350 | $300 | $265 | $280 | $265 | $233 | $278 | $265 | $301 | 4% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 36" DIAMETER, UN | 260 FT | $75.00 | $87.00 | $91.00 | $77.50 | $91.00 | $90.00 | $70.00 | $87.50 | $175 | $85.53 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $19,000 | $23,500 | $5,500 | $24,000 | $9,700 | $15,000 | $39,250 | $40,000 | $60,000 | $39,645 | 4% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 233 FT | $80.00 | $87.00 | $91.00 | $76.00 | $91.00 | $93.00 | $84.50 | $148 | $175 | $311 | 3% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 196 SY | $80.00 | $70.00 | $135 | $70.50 | $65.00 | $74.00 | $67.25 | $56.00 | $68.50 | $77.84 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 65 CY | $240 | $315 | $300 | $240 | $250 | $240 | $230 | $250 | $240 | $273 | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 600 FT | $19.50 | $20.00 | $20.00 | $26.00 | $22.00 | $20.00 | $33.50 | $27.75 | $20.00 | $32.36 | 2% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 20 CY | $560 | $300 | $800 | $514 | $300 | $400 | $297 | $435 | $700 | $1,688 | 2% |
| 203E20000 EMBANKMENT | 694 CY | $16.00 | $12.50 | $20.00 | $13.00 | $30.00 | $14.00 | $39.75 | $16.00 | $40.00 | $38.81 | 2% |
| 524E95000 DRILLED SHAFTS, MISC.: EXTENSION | 14 FT | $732 | $87.00 | $91.00 | $28.00 | $91.00 | $35.00 | $238 | $87.50 | $125 | $1,208 | 2% |
| 202E98500 REMOVAL MISC.: ROCK SLOPE PROTECTION REMOVED | 500 CY | $20.00 | $6.00 | $20.00 | $24.00 | $30.00 | $17.00 | $23.35 | $23.00 | $20.00 | $30.62 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $9,500 | $3,000 | $2,000 | $13,300 | $19,000 | $17,000 | $12,975 | $15,000 | $5,000 | $6,250 | 2% |
| 304E20000 AGGREGATE BASE | 85 CY | $88.00 | $75.00 | $125 | $86.50 | $100 | $90.00 | $81.50 | $90.00 | $100 | $130 | 1% |
| 606E15050 GUARDRAIL, TYPE MGS | 287.5 FT | $25.42 | $27.00 | $30.00 | $25.42 | $28.00 | $32.50 | $37.00 | $27.00 | $27.60 | $28.89 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,525 | $4,500 | $3,000 | $5,000 | $3,500 | $7,500 | $2,250 | $8,000 | $5,000 | $3,238 | 1% |
| 202E23000 PAVEMENT REMOVED |
| 380 SY |
| $12.00 |
| $8.00 |
| $20.00 |
| $7.50 |
| $15.00 |
| $20.00 |
| $19.25 |
| $20.50 |
| $25.00 |
| $38.05 |
| 202E38000 GUARDRAIL REMOVED | 338 FT | $3.30 | $1.00 | $2.00 | $3.00 | $3.00 | $2.50 | $4.25 | $4.50 | $2.00 | $3.62 |
| 203E10000 EXCAVATION | 92 CY | $11.50 | $20.00 | $20.00 | $19.50 | $30.00 | $5.00 | $26.50 | $21.00 | $25.00 | $46.24 |
| 204E10000 SUBGRADE COMPACTION | 428 SY | $3.00 | $3.00 | $5.00 | $2.50 | $3.00 | $5.00 | $1.25 | $4.00 | $3.00 | $3.48 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 50 FT | $27.36 | $29.00 | $30.00 | $27.36 | $30.00 | $35.00 | $45.35 | $29.00 | $30.40 | $31.09 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $92.00 | $150 | $200 | $890 | $150 | $100 | $269 | $200 | $500 | $401 |
| 659E10000 SEEDING AND MULCHING | 825 SY | $2.00 | $2.50 | $2.00 | $3.50 | $6.00 | $3.25 | $3.55 | $3.40 | $4.90 | $3.57 |
| 659E20000 COMMERCIAL FERTILIZER | 0.12 TON | $985 | $650 | $400 | $705 | $800 | $730 | $850 | $750 | $325 | $1,827 |
| 659E31000 LIME | 0.17 ACRE | $950 | $80.00 | $400 | $869 | $400 | $180 | $85.29 | $185 | $50.00 | $557 |
| 659E35000 WATER | 5 MGAL | $1.00 | $1.00 | $10.00 | $123 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.14 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 24 FT | $15.00 | $25.00 | $20.00 | $74.50 | $8.00 | $20.00 | $33.50 | $38.00 | $50.00 | $192 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 4 FT | $3.25 | $25.00 | $20.00 | $67.00 | $25.00 | $55.00 | $27.75 | $62.50 | $100 | $244 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $250 | $250 | $500 | $341 | $125 | $225 | $180 | $280 | $500 | $535 |
| 407E20000 NON-TRACKING TACK COAT | 138 GAL | $3.05 | $9.00 | $10.00 | $3.05 | $4.00 | $3.05 | $2.00 | $3.25 | $3.05 | $3.47 |
| 408E10000 PRIME COAT | 121 GAL | $3.75 | $10.00 | $10.00 | $3.75 | $4.00 | $3.75 | $2.00 | $4.00 | $3.75 | $4.26 |
| 617E10100 COMPACTED AGGREGATE | 5 CY | $81.00 | $250 | $200 | $120 | $100 | $115 | $153 | $340 | $100 | $144 |
| 621E00100 RPM | 9 EACH | $350 | $350 | $375 | $350 | $390 | $350 | $504 | $375 | $335 | $398 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 9 EACH | $3.00 | $1.00 | $50.00 | $30.50 | $10.00 | $25.00 | $33.50 | $10.50 | $50.00 | $72.42 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 7 EACH | $12.00 | $12.00 | $20.00 | $12.00 | $12.00 | $10.00 | $12.25 | $12.50 | $7.00 | $13.64 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.26 MILE | $3,650 | $3,800 | $6,000 | $3,650 | $4,000 | $3,650 | $3,700 | $3,850 | $1,500 | $4,148 |
| 642E00300 CENTER LINE, TYPE 1 | 0.13 MILE | $6,675 | $6,800 | $6,000 | $6,675 | $7,000 | $6,675 | $6,800 | $7,000 | $2,300 | $7,585 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,900 | $2,000 | $2,100 | $6,200 | $2,200 | $2,200 | $2,520 | $2,200 | $2,840 | $2,500 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 2 EACH | $750 | $1,000 | $1,000 | $1,600 | $13,000 | $7,500 | $2,600 | $11,500 | $5,000 | $38,182 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 12 EACH | $15.00 | $20.00 | $20.00 | $28.00 | $12.00 | $7.00 | $28.25 | $14.75 | $20.00 | $31.82 |
| 614E13360 OBJECT MARKER, TWO WAY | 12 EACH | $15.00 | $20.00 | $20.00 | $30.00 | $12.00 | $12.00 | $30.25 | $24.50 | $30.00 | $34.09 |
| 616E10000 WATER | 1 MGAL | $1.00 | $1.00 | $10.00 | $1.00 | $1.00 | $35.00 | $55.00 | $110 | $1.00 | $5.68 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 302 FT | $3.70 | $15.00 | $20.00 | $6.50 | $8.00 | $4.50 | $3.75 | $6.50 | $25.00 | $30.18 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $10,000 | $7,000 | $5,200 | $20,000 | $4,588 | $8,110 | $5,000 | $10,000 | $13,250 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES W21x101 | 1,750 FT | $98.1 | $172k | 30% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,092 FT | $65.75 | $72k | 12% |
| 530E00400 SPECIAL - STRUCTURES - PRECAST CONCRETE PANEL | 187 EACH | $261 | $49k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 5% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 271 CY | $90 | $24k | 4% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 79 CY | $265 | $21k | 4% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 36" DIAMETER, UN | 260 FT | $75 | $20k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $19,000 | $19k | 3% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 233 FT | $80 | $19k | 3% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 196 SY | $80 | $16k | 3% |