BEL-CR 46-02.48/02.79 (PART 1 AND PART 2)
BEL County · est $1.1M
Bid dateThursday, May 13—
BEL County · est $1.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 46 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Alan Stone CO INC | R3Dennison Bridge INC | R4Shelly & Sands INC | R5Suburban Maintenance & Construction | % of bid |
|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: W14X82, FURNISHED | 1,980 FT | $54.00 | $52.00 | $54.00 | $55.00 | $55.00 | 17% |
| 507E00400 STEEL PILES, MISC.: HP12X63, FURNISHED | 2,432 FT | $43.00 | $40.00 | $44.00 | $44.00 | $45.00 | 17% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 1,710 FT | $39.50 | $36.50 | $50.00 | $54.00 | $42.00 | 11% |
| 507E00400 |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Alan Stone CO INC | R3Dennison Bridge INC | R4Shelly & Sands INC | R5Suburban Maintenance & Construction |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,500 | $2,550 | $1,000 | $5,500 | $12,000 |
| 202E23000 PAVEMENT REMOVED | 548 SY | $12.00 | $5.00 | $17.00 | $6.00 | $8.00 |
| 203E10000 EXCAVATION | 167 CY | $32.00 | $17.00 | $25.00 | $25.00 | $15.00 |
| 203E20000 EMBANKMENT | 76 CY | $23.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 945 FT |
| $46.00 |
| $43.00 |
| $45.00 |
| $47.00 |
| $45.00 |
| 7% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 24" DIAMETER, UN | 900 FT | $41.00 | $37.00 | $50.00 | $64.00 | $42.00 | 6% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 1,562 FT | $23.00 | $39.00 | $50.00 | $52.00 | $55.00 | 6% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 760 FT | $44.00 | $48.50 | $60.00 | $69.00 | $75.00 | 5% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 675 FT | $40.00 | $40.00 | $65.00 | $50.00 | $45.00 | 4% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 440 FT | $51.00 | $62.50 | $60.00 | $90.00 | $90.00 | 4% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 24" DIAMETER, UN | 630 FT | $33.00 | $33.00 | $50.00 | $70.00 | $45.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $38,000 | $20,000 | $20,000 | $50,000 | 3% |
| 524E94605 DRILLED SHAFTS, 30" DIAMETER INTO BEDROCK, AS PER | 270 FT | $61.00 | $65.00 | $85.00 | $84.00 | $95.00 | 3% |
| 606E15201 GUARDRAIL, TYPE MGS HALF POST SPACING WITH LONG PO | 625 FT | $25.00 | $40.00 | $35.20 | $35.20 | $40.00 | 3% |
| 511E81300 CONCRETE, MISC.: 8"x24"x57" PRECAST CONCRETE LAGGI | 89 EACH | $165 | $153 | $180 | $225 | $250 | 2% |
| 304E20000 AGGREGATE BASE | 168 CY | $85.00 | $81.00 | $120 | $90.00 | $70.00 | 2% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 70 CY | $190 | $388 | $340 | $321 | $400 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $5,000 | $10,000 | $6,570 | $25,000 | 2% |
| 606E26151 ANCHOR ASSEMBLY, MGS TYPE E, AS PER PLAN | — | $2,500 | $3,000 | $2,600 | $2,600 | $3,000 | 1% |
| 304E20000 AGGREGATE BASE | 77 CY | $90.00 | $79.00 | $120 | $100 | $70.00 | 1% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 53 CY | $125 | $115 | $110 | $160 | $70.00 | 1% |
| $11.00 |
| $35.00 |
| $15.00 |
| $15.00 |
| 204E10000 SUBGRADE COMPACTION | 987 SY | $4.74 | $2.50 | $3.00 | $5.00 | $5.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 140 CY | $20.00 | $18.00 | $25.00 | $32.00 | $15.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 70 CY | $90.00 | $76.00 | $90.00 | $85.00 | $70.00 |
| 204E30040 GRANULAR MATERIAL, TYPE E | 70 CY | $90.00 | $56.00 | $90.00 | $75.00 | $70.00 |
| 204E45000 PROOF ROLLING | 2 HOUR | $125 | $133 | $100 | $200 | $5.00 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 2 EACH | $110 | $248 | $200 | $200 | $1,000 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 548 SY | $5.25 | $2.00 | $5.00 | $4.50 | $5.00 |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 34 GAL | $8.00 | $19.50 | $20.00 | $16.00 | $20.00 |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 1,096 SY | $3.00 | $2.50 | $20.00 | $2.25 | $15.00 |
| 423E00204 CRACK SEALING, TYPE II | 21 SY | $15.00 | $66.00 | $100 | $150 | $15.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 14 EACH | $35.00 | $10.00 | $8.00 | $8.50 | $10.00 |
| 202E98000 REMOVAL MISC.: PILING REMOVED | 1 LS | $1,500 | $3,600 | $2,500 | $4,500 | $5,000 |
| 616E10000 WATER | 5 MGAL | $10.00 | $0.20 | $10.00 | $40.00 | $1.00 |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,000 | $3,200 | $1,000 | $2,400 | $15,000 |
| 202E23000 PAVEMENT REMOVED | 174 SY | $15.00 | $4.00 | $18.00 | $8.50 | $8.00 |
| 203E10000 EXCAVATION | 68 CY | $20.00 | $10.50 | $25.00 | $15.00 | $15.00 |
| 203E20000 EMBANKMENT | 83 CY | $18.00 | $5.00 | $35.00 | $18.00 | $15.00 |
| 204E10000 SUBGRADE COMPACTION | 365 SY | $5.00 | $2.50 | $4.00 | $7.50 | $5.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 44 CY | $25.00 | $16.00 | $25.00 | $30.00 | $15.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 22 CY | $100 | $76.00 | $90.00 | $75.00 | $70.00 |
| 204E30040 GRANULAR MATERIAL, TYPE E | 22 CY | $100 | $70.00 | $90.00 | $75.00 | $70.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $125 | $266 | $100 | $200 | $75.00 |
| 606E15201 GUARDRAIL, TYPE MGS HALF POST SPACING WITH LONG PO | 237.5 FT | $25.00 | $40.00 | $35.20 | $35.20 | $40.00 |
| 606E26151 ANCHOR ASSEMBLY, MGS TYPE E, AS PER PLAN | — | $2,500 | $3,000 | $2,600 | $2,600 | $3,000 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 312 SY | $8.25 | $3.50 | $8.00 | $4.50 | $5.00 |
| 832E30000 EROSION CONTROL | 2,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 23 CY | $200 | $388 | $340 | $321 | $400 |
| 407E10000 TACK COAT | 48 GAL | $7.00 | $2.50 | $5.00 | $2.00 | $4.50 |
| 408E10001 PRIME COAT, AS PER PLAN | 26 GAL | $8.00 | $19.50 | $20.00 | $16.00 | $20.00 |
| 423E00204 CRACK SEALING, TYPE II | 7 SY | $15.00 | $200 | $200 | $150 | $15.00 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 26 CY | $220 | $473 | $400 | $391 | $450 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (13 CY | $250 | $550 | $475 | $455 | $400 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 7 EACH | $35.00 | $10.50 | $8.00 | $8.50 | $10.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.12 MILE | $6,000 | $7,000 | $6,500 | $5,750 | $6,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.06 MILE | $11,000 | $13,000 | $12,000 | $10,990 | $11,000 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $2,500 | $500 | $1,500 | $4,200 | $15,000 |
| 503E22201 UNCLASSIFIED EXCAVATION, INCLUDING ROCK AND/OR SHA | 241 CY | $15.00 | $24.50 | $45.00 | $17.00 | $15.00 |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 17 CY | $385 | $367 | $400 | $450 | $250 |
| 616E10000 WATER | 5 MGAL | $10.00 | $0.20 | $10.00 | $25.00 | $1.00 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,400 | $7,000 | $7,000 | $6,500 | $15,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,500 | $16,000 | $4,500 | $12,500 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: W14X82, FURNISHED | 1,980 FT | $54 | $107k | 14% |
| 507E00400 STEEL PILES, MISC.: HP12X63, FURNISHED | 2,432 FT | $43 | $105k | 14% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 1,710 FT | $39.5 | $68k | 9% |
| 507E00400 STEEL PILES, MISC.: W16X67, FURNISHED | 945 FT | $46 | $43k | 6% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 24" DIAMETER, UN | 900 FT | $41 | $37k | 5% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 1,562 FT | $23 | $36k | 5% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 760 FT | $44 | $33k | 4% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 675 FT | $40 | $27k | 4% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 440 FT | $51 | $22k | 3% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 24" DIAMETER, UN | 630 FT | $33 | $21k | 3% |