CLE-SIGNS FY2022
CLE County · est $2.7M
Bid dateThursday, April 28—
CLE County · est $2.7M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 14 more items below.
| Item | Quantity | R1Lake Erie Construction Company | R2M P Dory CO | R3A & A Safety INC | % of bid |
|---|---|---|---|---|---|
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 96,770 FT | $8.50 | $11.50 | $14.00 | 32% |
| 630E80100 SIGN, FLAT SHEET | 53,222 SF | $13.00 | $16.50 | $19.00 | 27% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 11,481 SF | $23.50 | $25.00 | $40.00 | 11% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 8,379 SF | $22.00 | $24.00 | $31.50 | 7% |
| 630E08600 SIGN POST REFLECTOR | 2,790 EACH | $33.00 | $32.50 | $40.00 |
| Item | Quantity | R1Lake Erie Construction Company | R2M P Dory CO | R3A & A Safety INC |
|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $2,000 | $5,000 | $3,000 |
| 202E38000 GUARDRAIL REMOVED | 400 FT | $2.40 | $2.50 | $5.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 400 FT | $24.20 | $22.00 | $55.00 |
| 690E98100 SPECIAL - TREE TRIMMING | 400 FT | $15.00 | $10.00 | $15.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 630E07000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 8,699 EACH | $10.00 | $10.00 | $10.00 | 3% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6,548 EACH | $10.00 | $15.00 | $10.00 | 3% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 78 EACH | $715 | $750 | $935 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $100,000 | $100,000 | 2% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 91 EACH | $420 | $2,000 | $1,420 | 2% |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 78 EACH | $425 | $415 | $520 | 1% |
| 630E80500 SIGN, DOUBLE FACED, STREET NAME | 250 EACH | $110 | $200 | $230 | 1% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $22,300 | $50,000 | $15,000 | 1% |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 193 EACH | $100 | $110 | $150 | 1% |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 577 FT | $29.50 | $21.50 | $27.00 | 1% |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 466 FT | $36.50 | $27.00 | $33.50 | 1% |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 599 FT | $27.00 | $20.50 | $26.00 | 1% |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 88 EACH | $165 | $350 | $240 | 1% |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 113 EACH | $120 | $150 | $125 | 1% |
| 630E08520 STREET NAME SIGN SUPPORT, NO. 3 POST | 1,162 FT | $11.50 | $15.00 | $14.00 | 1% |
| 99 FT |
| $44.00 |
| $38.00 |
| $47.50 |
| 630E08004 ONE WAY SUPPORT, NO. 3 POST | 332 FT | $12.50 | $15.00 | $21.00 |
| 630E79000 SIGN HANGER ASSEMBLY, SPAN WIRE | 31 EACH | $365 | $400 | $300 |
| 630E79610 SIGN SUPPORT ASSEMBLY, BARRIER MOUNTED | 2 EACH | $1,435 | $1,250 | $925 |
| 630E80600 SIGN, DOUBLE FACED, MILE MARKER | 252 EACH | $50.00 | $40.00 | $75.00 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 56 EACH | $165 | $350 | $250 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $37.50 | $78.00 | $75.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 1 SNMT | $2,575 | $2,000 | $850 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $13,000 | $35,000 | $30,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 96,770 FT | $8.5 | $823k | 31% |
| 630E80100 SIGN, FLAT SHEET | 53,222 SF | $13 | $692k | 26% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 11,481 SF | $23.5 | $270k | 10% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 8,379 SF | $22 | $184k | 7% |
| 630E08600 SIGN POST REFLECTOR | 2,790 EACH | $33 | $92k | 4% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 8,699 EACH | $10 | $87k | 3% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6,548 EACH | $10 | $65k | 2% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 78 EACH | $715 | $56k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 2% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 91 EACH | $420 | $38k | 1% |