FAI-US 22-09.42
FAI County · est $3.2M
Bid dateThursday, April 28—
FAI County · est $3.2M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 105 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Shelly Company | R3Axis Civil Construction LLC | R4Wolf Creek Contracting Company LLC | R5Trucco Construction CO INC | % of bid |
|---|---|---|---|---|---|---|---|
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 7,940 SY | $55.00 | $55.00 | $55.00 | $83.79 | $84.00 | 17% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1,829 CY | $155 | $155 | $155 | $200 | $155 | 11% |
| 304E20000 AGGREGATE BASE | 2,881 CY | $86.00 | $74.25 | $70.00 | $81.44 | $76.20 |
| Item | Quantity | R1Shelly & Sands INC | R2Shelly Company | R3Axis Civil Construction LLC | R4Wolf Creek Contracting Company LLC | R5Trucco Construction CO INC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $19,000 | $25,000 | $25,000 | $14,189 | $10,000 |
| 202E20010 HEADWALL REMOVED | 5 EACH | $150 | $310 | $700 | $170 | $1,067 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 327 FT | $15.00 | $44.00 | $27.00 | $18.60 | $25.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 97 FT | $28.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 10% |
| 659E98000 SEEDING, MISC.:ARTIFICIAL TURF | 1,913 SY | $125 | $90.00 | $100 | $125 | $146 | 9% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $160,000 | $170,000 | $125,000 | $82,613 | $335,000 | 6% |
| 832E30000 EROSION CONTROL | 157,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 6% |
| 609E26000 CURB, TYPE 6 | 6,281 FT | $18.75 | $18.50 | $18.50 | $21.28 | $18.50 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $90,000 | $100,000 | $33,442 | $100,000 | 4% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 1,095 SY | $85.00 | $90.00 | $90.00 | $72.54 | $92.60 | 4% |
| 203E10000 EXCAVATION | 7,314 CY | $12.50 | $22.00 | $23.00 | $31.44 | $43.00 | 4% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (531 CY | $171 | $171 | $171 | $236 | $171 | 4% |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 379 CY | $209 | $209 | $209 | $282 | $209 | 3% |
| 611E53100 43" X 68" CONDUIT, TYPE A, 706.04 | 128 FT | $600 | $585 | $1,200 | $534 | $959 | 3% |
| 611E53300 53" X 83" CONDUIT, TYPE A, 706.04 | 88 FT | $820 | $665 | $900 | $626 | $1,125 | 3% |
| 605E14000 6" BASE PIPE UNDERDRAINS | 5,048 FT | $12.75 | $15.50 | $15.00 | $11.61 | $12.65 | 3% |
| 202E23000 PAVEMENT REMOVED | 8,810 SY | $7.00 | $7.75 | $8.00 | $8.93 | $20.00 | 2% |
| 203E20000 EMBANKMENT | 7,703 CY | $6.25 | $23.75 | $23.00 | $15.69 | $16.00 | 2% |
| 625E10490 LIGHT POLE, CONVENTIONAL DESIGN AT6B35 | 15 EACH | $2,851 | $2,500 | $2,851 | $3,278 | $2,851 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,000 | $70,000 | $80,000 | $38,870 | $119,700 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 14 MNTH | $2,750 | $2,500 | $2,500 | $2,372 | $2,400 | 2% |
| $90.75 |
| $44.00 |
| $33.44 |
| $75.00 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $150 | $310 | $700 | $347 | $800 |
| 202E98100 REMOVAL MISC.:BILLBOARD | 1 EACH | $200 | $4,000 | $2,500 | $64.61 | $945 |
| 202E98100 REMOVAL MISC.:POST | 6 EACH | $75.00 | $117 | $60.00 | $23.63 | $100 |
| 202E98100 REMOVAL MISC.:ROCK | 1 EACH | $110 | $235 | $500 | $85.13 | $125 |
| 204E10000 SUBGRADE COMPACTION | 13,947 SY | $2.25 | $1.55 | $2.00 | $1.21 | $2.01 |
| 204E13000 EXCAVATION OF SUBGRADE | 470 CY | $20.00 | $22.50 | $23.00 | $29.55 | $29.10 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 470 CY | $58.00 | $56.75 | $77.00 | $62.30 | $64.95 |
| 204E45000 PROOF ROLLING | 7 HOUR | $500 | $205 | $250 | $742 | $200 |
| 204E51000 GEOGRID | 1,408 SY | $2.25 | $1.85 | $2.50 | $3.11 | $4.20 |
| 623E40520 RIGHT-OF-WAY MONUMENT | 2 EACH | $1,200 | $370 | $450 | $878 | $1,301 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 8 SY | $100 | $225 | $140 | $47.89 | $264 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 66 SY | $89.00 | $119 | $140 | $63.48 | $124 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 25 CY | $145 | $335 | $125 | $95.61 | $144 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 24 CY | $195 | $460 | $125 | $94.39 | $191 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $98.00 | $98.00 | $100 | $230 | $100 |
| 659E00301 TOPSOIL, AS PER PLAN | 2,121 CY | $10.00 | $30.25 | $30.00 | $22.60 | $12.08 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 14,474 SY | $0.88 | $0.87 | $1.50 | $1.44 | $1.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 724 SY | $0.79 | $0.78 | $1.50 | $1.15 | $1.50 |
| 659E15000 INTER-SEEDING | 724 SY | $0.79 | $0.78 | $1.50 | $0.01 | $1.50 |
| 659E20000 COMMERCIAL FERTILIZER | 2.02 TON | $916 | $916 | $800 | $1,725 | $800 |
| 659E31000 LIME | 2.99 ACRE | $153 | $154 | $80.00 | $230 | $80.00 |
| 659E35000 WATER | 81 MGAL | $1.00 | $1.00 | $1.00 | $1.15 | $1.00 |
| 670E00500 SLOPE EROSION PROTECTION | 4,622 SY | $1.34 | $1.34 | $1.95 | $2.70 | $1.95 |
| 670E00700 DITCH EROSION PROTECTION | 874 SY | $1.45 | $1.44 | $2.00 | $2.70 | $2.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,500 | $1,475 | $2,000 | $1,590 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $12,500 | $2,850 | $11,550 | $19,000 | $13,090 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $15,000 | $12,000 | $14,500 | $10,780 | $20,424 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 311 SY | $7.00 | $6.81 | $1.00 | $11.50 | $6.00 |
| 602E20000 CONCRETE MASONRY | 8 CY | $2,000 | $2,035 | $3,000 | $2,602 | $2,400 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 644 FT | $13.00 | $17.85 | $18.00 | $11.07 | $23.39 |
| 605E31100 AGGREGATE DRAINS | 20 FT | $30.00 | $21.00 | $15.00 | $6.73 | $35.72 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 242 FT | $35.00 | $58.50 | $25.00 | $13.87 | $20.36 |
| 611E03100 10" CONDUIT, TYPE B | 75 FT | $40.00 | $32.50 | $25.00 | $14.29 | $20.00 |
| 611E03600 10" CONDUIT, TYPE E | 75 FT | $38.00 | $23.50 | $25.00 | $14.29 | $15.00 |
| 611E03700 10" CONDUIT, TYPE F | 75 FT | $50.00 | $23.50 | $25.00 | $4.68 | $15.00 |
| 611E04400 12" CONDUIT, TYPE B | 333 FT | $85.00 | $69.00 | $75.00 | $31.75 | $99.62 |
| 611E04600 12" CONDUIT, TYPE C | 258 FT | $75.00 | $71.00 | $75.00 | $31.47 | $66.70 |
| 611E07600 18" CONDUIT, TYPE C | 17 FT | $92.00 | $81.00 | $130 | $67.74 | $83.00 |
| 611E10400 24" CONDUIT, TYPE B | 141 FT | $130 | $169 | $140 | $81.76 | $153 |
| 611E10600 24" CONDUIT, TYPE C | 118 FT | $110 | $121 | $140 | $81.07 | $125 |
| 611E10900 24" CONDUIT, TYPE D | 75 FT | $100 | $104 | $140 | $87.75 | $125 |
| 611E98150 CATCH BASIN, NO. 3 | 8 EACH | $4,200 | $3,600 | $4,500 | $3,274 | $4,778 |
| 611E98180 CATCH BASIN, NO. 3A | 8 EACH | $3,300 | $2,850 | $5.00 | $2,531 | $3,715 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $2,200 | $2,350 | $5,000 | $2,014 | $2,464 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $3,000 | $2,500 | $3,500 | $2,192 | $2,832 |
| 611E99574 MANHOLE, NO. 3 | 3 EACH | $3,500 | $3,400 | $4,500 | $1,685 | $4,611 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $295 | $275 | $350 | $419 | $314 |
| 407E20000 NON-TRACKING TACK COAT | 1,418 GAL | $3.50 | $3.50 | $3.50 | $5.18 | $3.50 |
| 609E22000 CURB, TYPE 3-B | 364 FT | $55.00 | $42.00 | $42.00 | $48.30 | $46.00 |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 48 FT | $35.50 | $18.50 | $18.50 | $21.28 | $16.88 |
| 609E31000 COMBINATION CURB AND GUTTER, TYPE 9 | 641 FT | $57.00 | $34.50 | $34.50 | $39.68 | $27.10 |
| 625E00450 CONNECTION, FUSED PULL APART | 51 EACH | $91.70 | $120 | $91.67 | $105 | $91.67 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 21 EACH | $97.80 | $140 | $97.80 | $112 | $97.80 |
| 625E10490 LIGHT POLE, CONVENTIONAL DESIGN AT8B35 | 2 EACH | $2,883 | $2,400 | $2,883 | $3,315 | $2,883 |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 17 EACH | $1,199 | $1,200 | $1,199 | $1,379 | $1,199 |
| 625E23302 NO. 6 AWG 2400 VOLT DISTRIBUTION CABLE | 753 FT | $2.36 | $3.00 | $2.36 | $2.71 | $2.36 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 2,103 FT | $1.55 | $1.75 | $1.55 | $1.78 | $1.55 |
| 625E24324 1-1/2" DUCT CABLE WITH THREE NO. 6 AWG 2400 VOLT C | 2,494 FT | $6.78 | $7.00 | $6.78 | $7.80 | $6.78 |
| 625E25400 CONDUIT, 2", 725.04 | 226 FT | $20.71 | $27.00 | $20.71 | $23.82 | $20.71 |
| 625E26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED) TYPE II | 17 EACH | $533 | $485 | $533 | $613 | $533 |
| 625E29002 TRENCH, 24" DEEP | 2,510 FT | $6.10 | $7.25 | $6.10 | $7.02 | $6.10 |
| 625E30700 PULL BOX, 725.08, 18" | 8 EACH | $906 | $1,150 | $906 | $1,042 | $906 |
| 625E30706 PULL BOX, 725.08, 24" | 1 EACH | $1,062 | $1,300 | $1,062 | $1,221 | $1,062 |
| 625E32000 GROUND ROD | 17 EACH | $328 | $310 | $328 | $377 | $328 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $5,977 | $1,800 | $5,977 | $6,874 | $5,977 |
| 625E34450 CONTROL CENTER CABINET, COMPLETE | 1 EACH | $3,936 | $9,000 | $3,936 | $4,526 | $3,936 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 2,510 FT | $0.14 | $2.10 | $0.14 | $0.16 | $0.14 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 313.1 FT | $12.00 | $12.00 | $12.00 | $13.80 | $12.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 529.1 FT | $13.00 | $13.00 | $13.00 | $14.95 | $13.00 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 51.6 FT | $14.50 | $14.50 | $14.50 | $16.68 | $14.50 |
| 630E08600 SIGN POST REFLECTOR | 14 EACH | $48.00 | $48.00 | $48.00 | $55.20 | $48.00 |
| 630E80100 SIGN, FLAT SHEET | 476.4 SF | $18.25 | $18.25 | $18.25 | $20.99 | $18.25 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 54 EACH | $10.00 | $10.00 | $10.00 | $11.50 | $10.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 37 EACH | $15.00 | $15.00 | $15.00 | $17.25 | $15.00 |
| 644E00104 EDGE LINE, 6" | 1.64 MILE | $6,995 | $6,995 | $6,995 | $8,044 | $6,311 |
| 644E00300 CENTER LINE | 0.37 MILE | $11,958 | $11,958 | $11,958 | $13,752 | $8,111 |
| 644E01514 DOTTED LINE, 8" | 279 FT | $2.65 | $2.65 | $2.65 | $3.05 | $1.75 |
| 644E20800 YIELD LINE | 112 FT | $19.25 | $19.25 | $19.25 | $22.14 | $10.20 |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 200 SY | $74.00 | $49.50 | $45.00 | $67.85 | $74.00 |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 200 SY | $155 | $155 | $60.00 | $121 | $155 |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 40 CY | $395 | $385 | $200 | $299 | $396 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $75.00 | $65.00 | $65.00 | $57.50 | $75.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 2,120 FT | $0.26 | $1.00 | $0.53 | $1.15 | $0.70 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,340 | $2,485 | $2,200 | $2,875 | $2,340 |
| 614E12420 DETOUR SIGNING | 1 LS | $17,500 | $16,600 | $24,600 | $19,090 | $26,445 |
| 614E12600 REPLACEMENT DRUM | 25 EACH | $80.00 | $80.00 | $75.00 | $92.00 | $80.63 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 43 EACH | $6.00 | $24.00 | $8.00 | $27.60 | $16.13 |
| 614E13360 OBJECT MARKER, TWO WAY | 43 EACH | $16.00 | $32.00 | $14.00 | $36.80 | $26.88 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 45 SNMT | $800 | $1,650 | $720 | $1,898 | $774 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.95 MILE | $4,200 | $2,215 | $1,850 | $4,830 | $2,381 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 3.69 MILE | $2,055 | $1,500 | $1,200 | $2,363 | $1,613 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 380 FT | $3.95 | $1.50 | $0.70 | $4.54 | $1.61 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 50 FT | $12.00 | $5.00 | $3.00 | $13.80 | $5.38 |
| 614E30200 WORK ZONE ARROW, CLASS I, 642 PAINT | 5 EACH | $200 | $90.00 | $130 | $230 | $96.75 |
| 616E10000 WATER | 37 MGAL | $35.00 | $1.00 | $1.00 | $1.06 | $50.00 |
| 617E10100 COMPACTED AGGREGATE | 30 CY | $110 | $250 | $120 | $28.75 | $121 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,120 FT | $17.00 | $17.00 | $32.00 | $61.85 | $21.50 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.5 MILE | $2,200 | $850 | $8.50 | $2,530 | $850 |
| 642E00300 CENTER LINE, TYPE 1 | 0.25 MILE | $4,400 | $1,500 | $1,500 | $5,060 | $150 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,000 | $18,500 | $22,000 | $26,951 | $24,679 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $35,000 | $68,000 | $40,000 | $28,750 | $64,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 7,940 SY | $55 | $437k | 13% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1,829 CY | $155 | $283k | 8% |
| 304E20000 AGGREGATE BASE | 2,881 CY | $86 | $248k | 7% |
| 659E98000 SEEDING, MISC.:ARTIFICIAL TURF | 1,913 SY | $125 | $239k | 7% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $160,000 | $160k | 5% |
| 832E30000 EROSION CONTROL | 157,000 EACH | $1 | $157k | 5% |
| 609E26000 CURB, TYPE 6 | 6,281 FT | $18.75 | $118k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 3% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 1,095 SY | $85 | $93k | 3% |
| 203E10000 EXCAVATION | 7,314 CY | $12.5 | $91k | 3% |