PAU-US 24-13.52
PAU County · est $2.2M
Bid dateThursday, June 16—
PAU County · est $2.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 34 more items below.
| Item | Quantity | R1Miller Bros Const INC | R2Vernon Nagel INC | R3Ohio-west Virginia Excavating CO | R4Miller Contracting Group INC | % of bid |
|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: W18X106 STEEL BEAM, FURNISHED, | 5,191 FT | $101 | $105 | $115 | $112 | 25% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 5,271 FT | $84.00 | $90.02 | $63.45 | $145 | 21% |
| 203E20001 EMBANKMENT, AS PER PLAN | 38,774 CY | $10.10 | $7.00 | $16.93 | $16.00 | 19% |
| 203E10000 EXCAVATION | 26,366 CY | $10.10 | $13.00 | $5.53 | $19.00 | 13% |
| 452E15050 12.5" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1 | 1,183 SY | $92.00 | $88.00 | $121 | $121 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $136,510 |
| Item | Quantity | R1Miller Bros Const INC | R2Vernon Nagel INC | R3Ohio-west Virginia Excavating CO | R4Miller Contracting Group INC |
|---|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" AND UNDER | 1,074 FT | $1.00 | $3.00 | $8.00 | $7.50 |
| 202E38000 GUARDRAIL REMOVED | 1,204 FT | $1.60 | $1.62 | $5.99 | $6.00 |
| 204E10000 SUBGRADE COMPACTION | 1,296 SY | $1.00 | $1.00 | $1.48 | $1.50 |
| 209E10000 DITCH CLEANOUT | 100 FT | $6.00 | $20.00 | $9.83 | $8.00 |
| 606E35003 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $370,010 |
| 5% |
| 601E28000 DUMPED ROCK FILL, TYPE D | 589 CY | $65.00 | $72.00 | $82.18 | $76.00 | 2% |
| 606E15051 GUARDRAIL, TYPE MGS, AS PER PLAN | 1,175 FT | $25.80 | $26.20 | $41.32 | $39.00 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,440 FT | $18.00 | $20.00 | $38.44 | $38.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,750 | $20,000 | $36,827 | $35,000 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $15,000 | $41,919 | $16,000 | 1% |
| 609E24000 CURB, TYPE 4-A | 1,004 FT | $14.50 | $15.00 | $15.29 | $8.00 | 1% |
| 611E05200 12" CONDUIT, TYPE F, 707.05 TYPE C OR 707.21 | 181 FT | $75.00 | $92.00 | $54.30 | $95.00 | 1% |
| 659E10000 SEEDING AND MULCHING | 14,197 SY | $0.95 | $1.50 | $1.92 | $2.15 | 1% |
| 304E20000 AGGREGATE BASE | 216 CY | $61.00 | $65.00 | $53.94 | $40.00 | 1% |
| 652E10000 PLACING STOCKPILED TOPSOIL | 1,576 CY | $8.00 | $3.00 | $4.95 | $5.00 | 1% |
| 607E35000 FENCE REMOVED AND REBUILT | 883 FT | $13.30 | $13.92 | $17.97 | $17.00 | 1% |
| 202E23000 PAVEMENT REMOVED | 1,125 SY | $9.25 | $15.00 | $18.53 | $14.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $20,000 | $11,977 | $10,000 | 0% |
| 605E06000 4" BASE PIPE UNDERDRAINS | 977 FT | $10.00 | $10.00 | $20.72 | $9.50 | 0% |
| 1 EACH |
| $3,420 |
| $3,475 |
| $2,419 |
| $2,300 |
| 651E10000 TOPSOIL STOCKPILED | 1,576 CY | $6.00 | $2.00 | $2.97 | $3.50 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 43 SY | $54.00 | $55.00 | $107 | $74.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 9 CY | $250 | $110 | $173 | $85.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $25.00 | $25.00 | $120 | $365 |
| 659E20000 COMMERCIAL FERTILIZER | 2 TON | $600 | $600 | $1,677 | $600 |
| 659E31000 LIME | 3 ACRE | $10.00 | $10.00 | $95.81 | $25.00 |
| 659E35000 WATER | 77 MGAL | $5.00 | $5.00 | $1.20 | $1.00 |
| 832E30000 EROSION CONTROL | 7,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.7 CY | $3,800 | $2,800 | $4,646 | $3,200 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 20 FT | $40.00 | $15.00 | $23.30 | $47.00 |
| 611E01500 6" CONDUIT, TYPE F | 10 FT | $35.00 | $10.00 | $44.60 | $89.00 |
| 611E06700 15" CONDUIT, TYPE F, 707.05 TYPE C OR 707.21 | 86 FT | $80.00 | $110 | $64.22 | $99.00 |
| 611E98180 CATCH BASIN, NO. 3A | 2 EACH | $2,600 | $3,200 | $4,657 | $2,000 |
| 618E40200 RUMBLE STRIPS, SHOULDER (CONCRETE) | 1,007 FT | $6.00 | $6.00 | $7.19 | $5.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE-WAY | 24 EACH | $8.90 | $8.90 | $13.17 | $17.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.23 MILE | $4,218 | $3,500 | $4,192 | $3,900 |
| 642E00204 LANE LINE, 6", TYPE 1 (BLACK CONTRAST) | 0.55 MILE | $1,204 | $1,000 | $1,198 | $1,200 |
| 642E00204 LANE LINE, 6", TYPE 1 (WHITE) | 0.55 MILE | $1,263 | $1,500 | $1,797 | $1,700 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 30 HOUR | $75.00 | $65.00 | $180 | $95.00 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,100 | $2,480 | $3,434 | $3,450 |
| 614E12484 WORK ZONE INCREASED PENALTIES SIGN | 2 EACH | $285 | $250 | $299 | $280 |
| 614E12600 REPLACEMENT DRUM | 10 EACH | $55.00 | $64.00 | $76.65 | $72.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 29 EACH | $8.82 | $8.00 | $9.58 | $9.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 29 EACH | $15.61 | $12.00 | $14.37 | $14.00 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.55 MILE | $2,811 | $3,500 | $4,192 | $3,900 |
| 616E10000 WATER | 152 MGAL | $35.00 | $1.00 | $11.98 | $11.00 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 6 SNMT | $850 | $950 | $1,138 | $1,100 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $2,000 | $1,000 | $3,593 | $900 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,250 | $4,500 | $43,716 | $7,400 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: W18X106 STEEL BEAM, FURNISHED, | 5,191 FT | $100.5 | $522k | 24% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 5,271 FT | $84 | $443k | 21% |
| 203E20001 EMBANKMENT, AS PER PLAN | 38,774 CY | $10.1 | $392k | 18% |
| 203E10000 EXCAVATION | 26,366 CY | $10.1 | $266k | 12% |
| 452E15050 12.5" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1 | 1,183 SY | $92 | $109k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 5% |
| 601E28000 DUMPED ROCK FILL, TYPE D | 589 CY | $65 | $38k | 2% |
| 606E15051 GUARDRAIL, TYPE MGS, AS PER PLAN | 1,175 FT | $25.8 | $30k | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,440 FT | $18 | $26k | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,750 | $16k | 1% |