FRA-US 40-20.10 (at S-Hamilton Rd)
FRA County · est $1.3M
Bid dateThursday, June 30—
FRA County · est $1.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 72 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Double Z Construction Company | R3Complete General Construction Company | R4Trucco Construction CO INC | % of bid |
|---|---|---|---|---|---|---|
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 718 CY | $215 | $215 | $215 | $233 | 14% |
| 609E26000 CURB, TYPE 6 | 4,827 FT | $23.60 | $32.00 | $42.00 | $34.00 | 11% |
| 611E05901 15" CONDUIT, TYPE B, AS PER PLAN | 508 FT | $125 | $135 | $280 | $178 | 6% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 1,500 SY | $42.00 | $49.00 | $72.00 | $48.00 | 6% |
| 305E14010 10" CONCRETE BASE, CLASS QC 1P, REINFORCED | 542 SY | $113 | $100 | $180 | $211 | 6% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 506 SY | $118 | $96.00 |
| Item | Quantity | R1Shelly & Sands INC | R2Double Z Construction Company | R3Complete General Construction Company | R4Trucco Construction CO INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,900 | $16,000 | $15,000 | $10,200 |
| 202E30000 WALK REMOVED | 6,770 SF | $1.00 | $2.50 | $4.00 | $3.00 |
| 202E32000 CURB REMOVED | 1,855 FT | $2.75 | $8.00 | $10.00 | $13.60 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 392 FT | $9.50 | $8.00 | $35.00 | $62.00 |
| 202E58300 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $140 |
| $190 |
| 6% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 17,007 SY | $3.50 | $3.50 | $3.50 | $1.90 | 6% |
| 202E23000 PAVEMENT REMOVED | 1,641 SY | $33.25 | $32.00 | $22.00 | $63.00 | 5% |
| 608E10000 4" CONCRETE WALK | 7,431 SF | $7.00 | $9.00 | $12.00 | $11.50 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $98,000 | $97,000 | $53,000 | 5% |
| 304E20000 AGGREGATE BASE | 382 CY | $117 | $100 | $80.00 | $124 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $45,000 | $40,000 | $40,000 | 4% |
| 203E10000 EXCAVATION | 604 CY | $65.50 | $75.00 | $45.00 | $120 | 4% |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 154 CY | $250 | $250 | $250 | $233 | 4% |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $3,200 | $1,200 | $3,000 | $4,500 | 4% |
| 611E04401 12" CONDUIT, TYPE B, AS PER PLAN | 312 FT | $119 | $110 | $140 | $174 | 3% |
| 611E08901 21" CONDUIT, TYPE B, AS PER PLAN | 156 FT | $163 | $145 | $300 | $223 | 2% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (61 CY | $410 | $410 | $410 | $420 | 2% |
| 659E00300 TOPSOIL | 318 CY | $75.00 | $48.00 | $50.00 | $91.00 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" AVG. | 3,682 SY | $6.00 | $6.00 | $6.00 | $1.90 | 2% |
| 11 EACH |
| $169 |
| $350 |
| $400 |
| $760 |
| 202E98200 REMOVAL MISC.:ABANDONED CULVERT | 350 FT | $23.00 | $35.00 | $40.00 | $116 |
| 203E20000 EMBANKMENT | 26 CY | $46.00 | $25.00 | $25.00 | $68.00 |
| 204E10000 SUBGRADE COMPACTION | 1,536 SY | $9.25 | $8.00 | $5.00 | $6.60 |
| 204E51000 GEOGRID | 1,030 SY | $1.25 | $2.00 | $4.00 | $6.80 |
| 608E52000 CURB RAMP | 236 SF | $38.00 | $21.00 | $6.00 | $24.00 |
| 608E53020 DETECTABLE WARNING | 48 SF | $47.50 | $34.00 | $45.00 | $48.00 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 11 EACH | $1,325 | $1,100 | $1,100 | $1,730 |
| 625E75500 LIGHT POLE FOUNDATION REMOVED | 1 EACH | $790 | $500 | $1,500 | $420 |
| 659E10000 SEEDING AND MULCHING | 880 SY | $3.50 | $8.00 | $5.00 | $7.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.12 TON | $1,400 | $1,400 | $1,050 | $600 |
| 659E31000 LIME | 0.18 ACRE | $80.00 | $80.00 | $100 | $29.00 |
| 659E35000 WATER | 2.38 MGAL | $1.00 | $1.00 | $50.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E06000 4" BASE PIPE UNDERDRAINS | 1,179 FT | $13.50 | $8.00 | $28.00 | $13.40 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 110 FT | $40.00 | $16.00 | $22.00 | $39.50 |
| 611E04601 12" CONDUIT, TYPE C, AS PER PLAN | 17 FT | $210 | $150 | $210 | $370 |
| 611E06101 15" CONDUIT, TYPE C, AS PER PLAN | 4 FT | $325 | $200 | $250 | $540 |
| 611E07401 18" CONDUIT, TYPE B, AS PER PLAN | 133 FT | $155 | $140 | $290 | $198 |
| 611E98150 CATCH BASIN, NO. 3 | 4 EACH | $4,186 | $5,000 | $5,000 | $6,500 |
| 611E98151 CATCH BASIN, NO. 3, AS PER PLAN | 1 EACH | $4,186 | $5,500 | $5,100 | $8,200 |
| 611E98180 CATCH BASIN, NO. 3A | 5 EACH | $3,288 | $3,500 | $4,200 | $5,200 |
| 611E98181 CATCH BASIN, NO. 3A, AS PER PLAN | 2 EACH | $3,288 | $4,000 | $4,500 | $6,900 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $1,102 | $1,000 | $1,500 | $1,150 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 39 CY | $117 | $150 | $125 | $184 |
| 253E01000 PAVEMENT REPAIR | 200 SY | $65.00 | $180 | $110 | $310 |
| 407E20000 NON-TRACKING TACK COAT | 1,300 GAL | $3.50 | $3.50 | $3.50 | $3.50 |
| 452E14010 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 95 SY | $153 | $110 | $145 | $270 |
| 609E72000 CONCRETE MEDIAN | 35 SY | $279 | $235 | $90.00 | $1,230 |
| 609E98000 CURB, MISC.: REMOVABLE CURB, AS PER PLAN | 4 FT | $184 | $1,200 | $500 | $225 |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 750 LB | $4.00 | $4.00 | $4.00 | $0.70 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $7,500 | $9,730 | $4,000 | $15,000 |
| 638E98000 WATER WORK, MISC.: 807-CURB BOXES ADJUSTED TO GRAD | 7 EACH | $712 | $300 | $450 | $350 |
| 638E98000 WATER WORK, MISC.: 807-VALVE BOXES ADJUSTED TO GRA | 7 EACH | $407 | $350 | $250 | $225 |
| 638E98000 WATER WORK, MISC.: 809-WATER HYDRANT, RELOCATED, P | 3 EACH | $3,520 | $6,000 | $2,500 | $2,600 |
| 638E98100 WATER WORK, MISC.: SURVEY COORDINATES, PER COC | 1 LS | $1,205 | $300 | $850 | $700 |
| 638E98600 WATER WORK, MISC.: 801-6 INCH WATER PIPE AND FITTI | 4 FT | $1,115 | $640 | $900 | $890 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 85 FT | $15.40 | $20.00 | $15.40 | $15.40 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 148 FT | $17.50 | $22.00 | $17.50 | $17.50 |
| 630E80100 SIGN, FLAT SHEET | 84.3 SF | $20.00 | $25.00 | $20.00 | $20.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 11 EACH | $10.00 | $30.00 | $10.00 | $10.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $65.00 | $125 | $65.00 | $65.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 12 EACH | $15.00 | $30.00 | $15.00 | $15.00 |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 2 EACH | $135 | $100 | $135 | $135 |
| 630E89810 REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP | 1 EACH | $2,920 | $3,000 | $2,920 | $2,900 |
| 644E00100 EDGE LINE, 4" | 0.61 MILE | $4,150 | $4,150 | $5,000 | $4,200 |
| 644E00200 LANE LINE, 4" | 1.04 MILE | $2,211 | $2,211 | $2,500 | $2,210 |
| 644E00300 CENTER LINE | 0.24 MILE | $8,965 | $8,965 | $9,979 | $9,000 |
| 644E00400 CHANNELIZING LINE, 8" | 1,697 FT | $1.95 | $1.95 | $1.45 | $2.00 |
| 644E00500 STOP LINE | 219 FT | $8.00 | $8.00 | $8.00 | $8.00 |
| 644E00620 CROSSWALK LINE, 12" | 539 FT | $3.85 | $3.85 | $4.00 | $3.90 |
| 644E01300 LANE ARROW | 21 EACH | $104 | $104 | $100 | $100 |
| 644E01400 WORD ON PAVEMENT, 72" | 12 EACH | $141 | $141 | $130 | $130 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 4 EACH | $2,300 | $2,300 | $2,500 | $2,300 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD, AS PER PLAN, PE | 4 EACH | $1.00 | $1.00 | $125 | $1.00 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG, AS PER PLAN | 800 FT | $2.00 | $2.00 | $6.00 | $2.00 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: VEHI | 4 EACH | $250 | $250 | $225 | $250 |
| 633E99000 CONTROLLER ITEM, MISC.: REPROGRAMMING CONTROLLER, | 1 EACH | $1,200 | $1,200 | $4,750 | $1,200 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $75.00 | $65.00 | $81.00 | $141 |
| 614E20100 WORK ZONE LANE LINE, CLASS I, 4", 642 PAINT | 1.12 MILE | $550 | $550 | $550 | $550 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.72 MILE | $1,860 | $1,860 | $1,860 | $1,860 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 0.48 MILE | $1,075 | $1,075 | $1,075 | $1,080 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 1,320 FT | $0.70 | $0.70 | $0.70 | $0.70 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 120 FT | $1.80 | $1.80 | $1.80 | $1.80 |
| 614E30200 WORK ZONE ARROW, CLASS I, 642 PAINT | 14 EACH | $135 | $135 | $135 | $135 |
| 616E10000 WATER | 3 MGAL | $80.00 | $95.00 | $1,250 | $163 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $10,000 | $10,000 | $12,700 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $17,500 | $20,000 | $30,000 | $20,900 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 718 CY | $215 | $154k | 11% |
| 609E26000 CURB, TYPE 6 | 4,827 FT | $23.6 | $114k | 8% |
| 611E05901 15" CONDUIT, TYPE B, AS PER PLAN | 508 FT | $125.25 | $64k | 5% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 1,500 SY | $42 | $63k | 5% |
| 305E14010 10" CONCRETE BASE, CLASS QC 1P, REINFORCED | 542 SY | $113.25 | $61k | 4% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 506 SY | $117.75 | $60k | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 17,007 SY | $3.5 | $60k | 4% |
| 202E23000 PAVEMENT REMOVED | 1,641 SY | $33.25 | $55k | 4% |
| 608E10000 4" CONCRETE WALK | 7,431 SF | $7 | $52k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $50k | 4% |