CUY-LG FY2023
CUY County · est $0.9M
Bid dateThursday, May 11—
CUY County · est $0.9M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Miller Cable Company | R2Ruhlin Company | R3Yates Electric LLC | % of bid |
|---|---|---|---|---|---|
| 625E10495 LIGHT POLE, LOW MAST, AS PER PLAN B, ALM45 | 59 EACH | $3,325 | $3,526 | $6,006 | 24% |
| 625E10495 LIGHT POLE, LOW MAST, AS PER PLAN A, ALM40 | 49 EACH | $3,800 | $4,195 | $6,440 | 23% |
| 625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA | 59 EACH | $940 | $1,130 | $1,637 | 7% |
| 625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA | 56 EACH | $940 | $1,130 | $1,615 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $46,165 | $17,190 | $660,981 | 6% |
| 625E34001 POWER SERVICE, AS PER PLAN A | 3 EACH | $14,250 | $9,900 | $15,523 | 5% |
| 625E75401 LIGHT POLE REMOVED, AS PER PLAN | 104 EACH | $400 | $200 | $773 | 5% |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 14,313 FT | $1.50 | $1.90 | $2.07 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $38,533 | 2% |
| 625E29002 TRENCH, 24" DEEP | 1,525 FT | $13.00 | $12.00 | $48.52 | 2% |
| 625E98000 LIGHTING, MISC.: EXTENSION OF MEDIAN BARRIER ANCHO | 39 EACH | $460 | $1,170 | $739 | 2% |
| 625E24100 1-1/2" DUCT CABLE WITH TWO NO. 4 AWG 2400 VOLT CAB | 1,355 FT | $12.00 | $16.00 | $33.60 | 2% |
| 625E34001 POWER SERVICE, AS PER PLAN B | 1 EACH | $14,250 | $29,000 | $23,626 | 2% |
| 202E75704 REMOVAL OF EXISTING CONTROL CENTER AND FOUNDATION | 5 EACH | $2,600 | $805 | $1,473 | 2% |
| 625E00451 CONNECTION, FUSED PULL APART, AS PER PLAN | 137 EACH | $90.00 | $170 | $183 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 150 HOUR | $75.00 | $95.00 | $134 | 1% |
| 625E27503 LUMINAIRE, UNDERPASS, SOLID STATE (LED), AS PER PL | 16 EACH | $630 | $800 | $1,084 | 1% |
| 607E61201 GATE, TYPE CLT, AS PER PLAN | 3 EACH | $3,125 | $3,200 | $3,162 | 1% |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 530 FT | $15.00 | $18.00 | $36.02 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,719 | $3,650 | $21,500 | 1% |
| Item | Quantity | R1Miller Cable Company | R2Ruhlin Company | R3Yates Electric LLC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $650 | $3,700 | $3,844 |
| 202E30000 WALK REMOVED | 225.5 SF | $20.00 | $9.70 | $15.80 |
| 608E10000 4" CONCRETE WALK | 225.5 SF | $20.00 | $12.00 | $23.70 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 625E00461 CONNECTION, UNFUSED PULL APART, AS PER PLAN | 81 EACH | $90.00 | $160 | $156 |
| 625E00480 CONNECTION, UNFUSED PERMANENT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 26 EACH |
| $80.00 |
| $170 |
| $142 |
| 625E10490 LIGHT POLE, CONVENTIONAL, AT15B41 | 1 EACH | $3,225 | $3,547 | $5,211 |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 1 EACH | $2,500 | $2,175 | $3,931 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 360 FT | $4.60 | $3.50 | $5.89 |
| 625E25500 CONDUIT, 3", 725.04 | 80 FT | $29.00 | $32.00 | $35.04 |
| 625E25906 CONDUIT, JACKED OR DRILLED, 725.051, 3" | 125 FT | $28.00 | $71.00 | $294 |
| 625E27503 LUMINAIRE, UNDERPASS, SOLID STATE (LED), AS PER PL | 6 EACH | $630 | $800 | $1,084 |
| 625E30700 PULL BOX, 725.08, 18" | 1 EACH | $1,275 | $1,175 | $3,383 |
| 625E30706 PULL BOX, 725.08, 24" | 1 EACH | $1,650 | $1,275 | $3,622 |
| 625E32000 GROUND ROD | 1 EACH | $440 | $350 | $437 |
| 625E35100 REERECT EXISTING LUMINAIRE | 1 EACH | $50.00 | $200 | $671 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 1,550 FT | $4.00 | $1.80 | $2.02 |
| 625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING | 1 LS | $500 | $4,915 | $57.51 |
| 625E75500 LIGHT POLE FOUNDATION REMOVED | 1 EACH | $300 | $400 | $742 |
| 625E75506 LUMINAIRE REMOVED | 8 EACH | $50.00 | $100 | $373 |
| 625E75511 POWER SERVICE REMOVED, AS PER PLAN | 4 EACH | $450 | $405 | $870 |
| 625E98000 LIGHTING, MISC.: REMOVAL OF UNDERPASS LIGHTING COM | 22 EACH | $70.00 | $100 | $408 |
| 625E98200 LIGHTING, MISC.: TEST CIRCUITS | 1 LS | $550 | $650 | $4,220 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 32 EACH | $185 | $215 | $168 |
| 630E87520 REMOVAL OF POLE MOUNTED SIGN AND REERECTION | 32 EACH | $88.00 | $75.00 | $281 |
| 630E97800 SIGNING, MISC.: ADDITIONAL SIGNS, GROUND MOUNTED, | 100 SF | $26.00 | $25.00 | $47.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 625E10495 LIGHT POLE, LOW MAST, AS PER PLAN B, ALM45 | 59 EACH | $3,325 | $196k | 23% |
| 625E10495 LIGHT POLE, LOW MAST, AS PER PLAN A, ALM40 | 49 EACH | $3,800 | $186k | 22% |
| 625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA | 59 EACH | $940 | $55k | 6% |
| 625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA | 56 EACH | $940 | $53k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $46,165 | $46k | 5% |
| 625E34001 POWER SERVICE, AS PER PLAN A | 3 EACH | $14,250 | $43k | 5% |
| 625E75401 LIGHT POLE REMOVED, AS PER PLAN | 104 EACH | $400 | $42k | 5% |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 14,313 FT | $1.5 | $21k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 625E29002 TRENCH, 24" DEEP | 1,525 FT | $13 | $20k | 2% |