WOO-IR 475-00.39 Slide Repair
WOO County · est $0.5M
Bid dateThursday, November 9—
WOO County · est $0.5M
Bid form · ODOT
| Item |
|---|
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 6 more items below.
| Item | Quantity | R1E S Wagner Company | R2Miller Bros Const INC | R3Vernon Nagel INC | R4Eclipse CO LLC | R5Madex Construction CO | % of bid |
|---|---|---|---|---|---|---|---|
| 203E40000 BORROW | 3,714 CY | $28.72 | $25.00 | $32.00 | $36.50 | $35.15 | 40% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $37,100 | $5,500 | $2,500 | $5,000 | $3,239 | 14% |
| 832E30000 EROSION CONTROL | 29,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 11% |
| 659E00300 TOPSOIL | 619 CY | $35.00 | $25.00 | $30.00 | $82.00 | $69.13 | 8% |
| 203E10000 EXCAVATION | 885 CY | $14.05 | $27.00 | $18.00 | $33.75 | $30.70 | 5% |
| 203E35130 GRANULAR MATERIAL, TYPE D |
| Item | Quantity | R1E S Wagner Company | R2Miller Bros Const INC | R3Vernon Nagel INC | R4Eclipse CO LLC | R5Madex Construction CO |
|---|---|---|---|---|---|---|
| 202E38200 GUARDRAIL REMOVED FOR REUSE | 105 FT | $2.00 | $2.00 | $4.00 | $3.00 | $14.98 |
| 202E38700 GUARDRAIL POST REMOVED | 14 EACH | $25.00 | $25.00 | $25.00 | $26.25 | $56.18 |
| 202E42810 ANCHOR ASSEMBLY REMOVED FOR REUSE, TYPE E | 1 EACH | $195 | $195 | $250 | $184 | $315 |
| 659E20000 COMMERCIAL FERTILIZER | 0.75 TON |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 288 CY |
| $38.91 |
| $67.00 |
| $60.00 |
| $77.00 |
| $90.68 |
| 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10,000 | $10,000 | $25,603 | $29,538 | 4% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $7,249 | $54,000 | $60,000 | $23,000 | $26,554 | 3% |
| 659E10000 SEEDING AND MULCHING | 5,571 SY | $0.93 | $0.90 | $3.00 | $0.92 | $3.02 | 2% |
| 203E35110 GRANULAR MATERIAL, TYPE B | 101 CY | $48.65 | $60.00 | $68.00 | $90.00 | $98.55 | 2% |
| 203E20000 EMBANKMENT | 4,598 CY | $1.00 | $10.00 | $24.00 | $26.50 | $26.63 | 2% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $950 | $1,000 | $1,000 | $1,101 | $1,158 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $3,020 | $3,200 | $13,000 | $4,863 | 1% |
| 606E16050 GUARDRAIL REBUILT, TYPE MGS | 105 FT | $24.00 | $24.00 | $24.00 | $26.25 | $22.47 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,500 | $5,000 | $6,500 | $9,750 | $11,579 | 1% |
| 606E27860 ANCHOR ASSEMBLY REBUILT, MGS TYPE E | 1 EACH | $2,420 | $2,420 | $2,420 | $2,573 | $1,887 | 1% |
| 606E17901 GUARDRAIL POST, AS PER PLAN | 14 EACH | $75.00 | $75.00 | $75.00 | $73.50 | $89.88 | 0% |
| 616E10000 WATER | 5 MGAL | $200 | $60.00 | $10.00 | $202 | $35.32 | 0% |
| 659E14000 REPAIR SEEDING AND MULCHING | 279 SY | $3.22 | $0.75 | $1.30 | $0.53 | $4.11 | 0% |
| 614E12600 REPLACEMENT DRUM | 5 EACH | $96.00 | $64.00 | $64.00 | $57.75 | $75.26 | 0% |
| $620 |
| $600 |
| $800 |
| $630 |
| $1,505 |
| 659E31000 LIME | 1.15 ACRE | $5.17 | $5.00 | $35.00 | $5.26 | $327 |
| 659E35000 WATER | 31 MGAL | $10.33 | $10.00 | $1.00 | $1.06 | $26.71 |
| Qty |
|---|
| Unit price |
|---|
| Extended |
|---|
| % |
|---|
| 203E40000 BORROW | 3,714 CY | $28.72 | $107k | 40% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $37,100 | $37k | 14% |
| 832E30000 EROSION CONTROL | 29,000 EACH | $1 | $29k | 11% |
| 659E00300 TOPSOIL | 619 CY | $35 | $22k | 8% |
| 203E10000 EXCAVATION | 885 CY | $14.05 | $12k | 5% |
| 203E35130 GRANULAR MATERIAL, TYPE D | 288 CY | $38.91 | $11k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 4% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $7,249 | $7k | 3% |
| 659E10000 SEEDING AND MULCHING | 5,571 SY | $0.93 | $5k | 2% |
| 203E35110 GRANULAR MATERIAL, TYPE B | 101 CY | $48.65 | $5k | 2% |