HAM-US 27-10.18 Sidewalks
HAM County · est $0.8M
Bid dateThursday, April 4—
HAM County · est $0.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 45 more items below.
| Item | Quantity | R1Adleta INC | R2Sunesis Construction CO | R3Prus Construction Company | % of bid |
|---|---|---|---|---|---|
| 452E12020 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P W | 1,091 SY | $99.51 | $91.05 | $135 | 15% |
| 608E10000 4" CONCRETE WALK | 15,142 SF | $6.90 | $7.26 | $10.00 | 15% |
| 605E05100 4" SHALLOW PIPE UNDERDRAINS | 2,735 FT | $28.55 | $15.73 | $17.75 | 11% |
| 202E23000 PAVEMENT REMOVED, ASPHALT | 2,526 SY | $27.37 | $36.27 | $32.00 | 10% |
| 302E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 344 CY | $193 | $388 | $372 | 9% |
| 609E26000 CURB, TYPE 6 | 3,139 FT | $17.07 | $20.74 | $34.50 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,740 | $30,564 |
| Item | Quantity | R1Adleta INC | R2Sunesis Construction CO | R3Prus Construction Company |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $7,901 | $9,426 | $5,250 |
| 202E30000 WALK REMOVED | 1,950 SF | $2.73 | $2.31 | $4.20 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 36 FT | $98.15 | $14.09 | $56.00 |
| 202E98100 REMOVAL MISC.: 4" STEEL PIPE | 1 EACH | $156 | $49.94 | $250 |
| 202E98100 REMOVAL MISC.: BOLLARDS REMOVED | 2 EACH | $156 | $98.17 | $250 |
| 202E98100 REMOVAL MISC.: LANDSCAPE TIMBER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $120,000 |
| 4% |
| 203E20000 EMBANKMENT | 371 CY | $73.88 | $51.19 | $49.00 | 4% |
| 611E04400 12" CONDUIT, TYPE B | 114 FT | $224 | $162 | $215 | 4% |
| 202E32000 CURB REMOVED | 1,808 FT | $9.19 | $7.10 | $15.00 | 2% |
| 608E52000 CURB RAMP | 406 SF | $38.07 | $22.14 | $25.00 | 2% |
| 659E00300 TOPSOIL | 194 CY | $77.00 | $165 | $102 | 2% |
| 832E30000 EROSION CONTROL | 14,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 202E23000 PAVEMENT REMOVED, CONCRETE | 490 SY | $28.17 | $14.28 | $33.00 | 2% |
| 304E20000 AGGREGATE BASE | 117 CY | $114 | $283 | $128 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 51 CY | $248 | $625 | $650 | 2% |
| 659E10000 SEEDING AND MULCHING | 1,743 SY | $6.60 | $5.07 | $3.00 | 2% |
| 611E07900 18" CONDUIT, TYPE D | 36 FT | $296 | $147 | $130 | 2% |
| 442E20200 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 34 CY | $275 | $980 | $755 | 1% |
| 611E98150 CATCH BASIN, NO. 3 | 2 EACH | $4,333 | $6,626 | $5,480 | 1% |
| 1 EACH |
| $156 |
| $44.15 |
| $250 |
| 202E98100 REMOVAL MISC.: PARKING BLOCKS | 1 EACH | $156 | $44.15 | $250 |
| 203E10000 EXCAVATION | 83 CY | $61.69 | $110 | $69.00 |
| 204E10000 SUBGRADE COMPACTION | 878 SY | $5.38 | $37.45 | $2.50 |
| 204E45000 PROOF ROLLING | 40 HOUR | $84.38 | $376 | $100 |
| 659E20000 COMMERCIAL FERTILIZER | 0.24 TON | $1,760 | $1,400 | $975 |
| 659E31000 LIME | 0.36 ACRE | $1,540 | $450 | $110 |
| 659E35000 WATER | 4.7 MGAL | $220 | $1.00 | $11.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $5,500 | $1,625 | $1,400 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,750 | $2,640 | $7,300 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $2,750 | $6,661 | $8,250 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 80 FT | $34.27 | $63.20 | $45.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 5 EACH | $689 | $893 | $925 |
| 611E99700 SPECIAL - GAS VALVE BOX ADJUSTED TO GRADE | 11 EACH | $58.60 | $533 | $815 |
| 407E10000 TACK COAT FOR (0.06 GAL/SQ YD) | 42 GAL | $3.30 | $4.00 | $8.00 |
| 407E10000 TACK COAT FOR (0.09 GAL/SQ YD) | 63 GAL | $6.60 | $4.00 | $8.00 |
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 29 CY | $193 | $974 | $875 |
| 452E10020 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P W | 40 SY | $93.18 | $92.75 | $130 |
| 638E10400 FIRE HYDRANT ADJUSTED TO GRADE | 4 EACH | $540 | $2,071 | $950 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 17 EACH | $58.60 | $271 | $750 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 129.5 FT | $31.85 | $14.00 | $15.20 |
| 630E08600 SIGN POST REFLECTOR | 1 EACH | $112 | $45.00 | $48.60 |
| 630E80100 SIGN, FLAT SHEET | 16 SF | $37.15 | $19.00 | $20.50 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 12 EACH | $109 | $45.00 | $48.60 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $22.94 | $35.00 | $290 |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 4 EACH | $1,100 | $100 | $108 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 1 EACH | $28.19 | $15.00 | $16.20 |
| 630E89810 REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP | 2 EACH | $1,650 | $900 | $972 |
| 644E00104 EDGE LINE, 6" | 0.6 MILE | $10,428 | $9,480 | $6,632 |
| 644E00500 STOP LINE | 65 FT | $7.70 | $7.00 | $13.45 |
| 644E00620 CROSSWALK LINE, 12" | 134 FT | $3.85 | $3.50 | $6.75 |
| 644E00630 CROSSWALK LINE, 24" | 156 FT | $7.70 | $7.00 | $9.15 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 130 FT | $25.30 | $23.00 | $23.75 |
| 625E31506 PULL BOX REMOVED AND REPLACED | 2 EACH | $511 | $2,000 | $2,450 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $1,246 | $950 | $1,225 |
| 614E22200 WORK ZONE EDGE LINE, CLASS I, 4", 740.06, TYPE I | 0.6 MILE | $10,462 | $19,367 | $10,275 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 165 FT | $3.82 | $4.00 | $3.75 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,751 | $6,462 | $12,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,050 | $8,750 | $30,000 |
| 624E10000 MOBILIZATION | 1 LS | $3,240 | $63,734 | $40,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E12020 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P W | 1,091 SY | $99.51 | $109k | 13% |
| 608E10000 4" CONCRETE WALK | 15,142 SF | $6.9 | $104k | 13% |
| 605E05100 4" SHALLOW PIPE UNDERDRAINS | 2,735 FT | $28.55 | $78k | 10% |
| 202E23000 PAVEMENT REMOVED, ASPHALT | 2,526 SY | $27.37 | $69k | 8% |
| 302E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 344 CY | $192.5 | $66k | 8% |
| 609E26000 CURB, TYPE 6 | 3,139 FT | $17.07 | $54k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,740 | $31k | 4% |
| 203E20000 EMBANKMENT | 371 CY | $73.88 | $27k | 3% |
| 611E04400 12" CONDUIT, TYPE B | 114 FT | $223.56 | $25k | 3% |
| 202E32000 CURB REMOVED | 1,808 FT | $9.19 | $17k | 2% |