WAY-SR 57-10.32
WAY County · est $1.7M
Bid dateThursday, April 18—
WAY County · est $1.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 68 more items below.
| Item | Quantity | R1Fechko Excavating LLC | R2D L Smith Concrete LLC | R3Shelly & Sands INC | R4Tri-mor CORP | R5Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 888 CY | $163 | $170 | $166 | $180 | $170 | 13% |
| 452E11011 7" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 1,173 SY | $120 | $93.00 | $117 | $85.00 | $91.00 | 13% |
| 203E10000 EXCAVATION | 3,818 CY | $27.00 | $15.00 | $11.00 | $16.00 | $15.00 | 9% |
| 304E20000 AGGREGATE BASE | 1,366 CY | $75.00 | $74.00 | $80.00 | $90.00 | $78.00 | 9% |
| 442E10081 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 314 CY | $261 | $242 | $222 | $290 | $242 | 7% |
| 442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( |
| Item | Quantity | R1Fechko Excavating LLC | R2D L Smith Concrete LLC | R3Shelly & Sands INC | R4Tri-mor CORP | R5Eclipse CO LLC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $17,500 | $20,000 | $40,000 | $12,000 | $2,500 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 20 FT | $20.00 | $10.00 | $26.00 | $15.00 | $27.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $585 | $350 | $525 | $500 | $628 |
| 202E98100 REMOVAL MISC.: POST REMOVED | 2 EACH | $80.00 | $50.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 267 CY |
| $266 |
| $262 |
| $317 |
| $295 |
| $262 |
| 6% |
| 206E10500 CEMENT | 234 TON | $211 | $200 | $217 | $210 | $209 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $46,750 | $30,000 | $40,000 | $45,000 | $47,382 | 4% |
| 625E25500 CONDUIT, 3", 725.04 | 1,335 FT | $32.00 | $27.00 | $32.00 | $40.00 | $27.00 | 4% |
| 609E26000 CURB, TYPE 6 | 1,597 FT | $26.50 | $20.00 | $30.00 | $15.00 | $20.00 | 4% |
| 832E30000 EROSION CONTROL | 36,198 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 605E14000 6" BASE PIPE UNDERDRAINS | 2,997 FT | $12.00 | $13.50 | $15.00 | $12.00 | $28.00 | 3% |
| 625E10490 LIGHT POLE, CONVENTIONAL, AT12B30 | 12 EACH | $2,450 | $3,750 | $2,450 | $3,000 | $3,750 | 3% |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 12 EACH | $2,370 | $1,500 | $2,370 | $1,700 | $1,500 | 3% |
| 609E18000 COMBINATION CURB AND GUTTER, TYPE 3 | 797 FT | $34.00 | $27.00 | $52.00 | $26.50 | $27.00 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $25,000 | $50,000 | $35,000 | $30,000 | 2% |
| 203E20000 EMBANKMENT | 2,587 CY | $10.00 | $31.00 | $7.00 | $12.00 | $12.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 5,554 SY | $4.55 | $2.00 | $8.00 | $9.00 | $9.00 | 2% |
| 206E15020 CEMENT STABILIZED SUBGRADE, 14 INCHES DEEP | 7,742 SY | $3.10 | $4.06 | $4.00 | $5.00 | $7.00 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $23,350 | $40,000 | $30,000 | $18,000 | $22,000 | 2% |
| $70.00 |
| $200 |
| $138 |
| 203E35141 GRANULAR MATERIAL, TYPE E, AS PER PLAN | 76 CY | $120 | $130 | $130 | $150 | $160 |
| 204E10000 SUBGRADE COMPACTION | 192 SY | $3.90 | $2.00 | $6.00 | $2.00 | $1.00 |
| 204E45000 PROOF ROLLING | 11 HOUR | $150 | $350 | $250 | $150 | $323 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 7 EACH | $2,000 | $1,500 | $1,350 | $1,000 | $2,019 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 1 EACH | $100 | $2,000 | $164 | $300 | $206 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $3,000 | $2,000 | $750 | $2,325 | $3,689 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $3,000 | $2,000 | $850 | $2,325 | $3,689 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 1 EACH | $260 | $250 | $352 | $225 | $302 |
| 206E11000 CURING COAT | 7,742 SY | $1.10 | $1.15 | $1.00 | $1.25 | $1.00 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 125 SY | $125 | $115 | $90.00 | $100 | $51.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 29 CY | $135 | $210 | $127 | $125 | $122 |
| 659E00300 TOPSOIL | 1,025 CY | $20.00 | $45.00 | $14.00 | $45.00 | $84.00 |
| 659E10000 SEEDING AND MULCHING | 9,216 SY | $2.00 | $2.50 | $1.00 | $2.00 | $0.82 |
| 659E14000 REPAIR SEEDING AND MULCHING | 461 SY | $2.00 | $0.80 | $2.00 | $2.00 | $1.80 |
| 659E15000 INTER-SEEDING | 461 SY | $1.80 | $0.10 | $2.00 | $2.00 | $1.80 |
| 659E20000 COMMERCIAL FERTILIZER | 1.29 TON | $950 | $850 | $920 | $1,500 | $860 |
| 659E31000 LIME | 1.9 ACRE | $25.00 | $10.00 | $165 | $1,500 | $155 |
| 659E35000 WATER | 26 MGAL | $20.00 | $1.00 | $1.00 | $90.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 373 SY | $4.00 | $2.75 | $2.00 | $22.00 | $1.50 |
| 670E00720 DITCH EROSION PROTECTION MAT, TYPE B | 531 SY | $4.00 | $2.75 | $2.00 | $4.00 | $1.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,965 | $2,000 | $2,100 | $2,200 | $2,026 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $10,560 | $4,400 | $5,700 | $5,800 | $9,074 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $8,300 | $8,250 | $8,900 | $9,200 | $8,507 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 928 SY | $5.00 | $7.95 | $3.00 | $20.00 | $3.10 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 4 CY | $1,800 | $3,200 | $1,700 | $3,500 | $1,572 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 322 FT | $19.50 | $13.50 | $18.00 | $12.00 | $31.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 135 FT | $22.00 | $16.00 | $17.00 | $12.00 | $34.00 |
| 611E04900 12" CONDUIT, TYPE D | 88 FT | $32.00 | $81.00 | $58.00 | $85.00 | $85.00 |
| 611E19200 42" CONDUIT, TYPE A, 706.02 | 47 FT | $355 | $460 | $544 | $430 | $413 |
| 611E20700 48" CONDUIT, TYPE A, 706.02 | 28 FT | $450 | $710 | $545 | $530 | $453 |
| 611E98700 INLET, SIDE DITCH | 1 EACH | $1,450 | $1,400 | $1,200 | $2,000 | $5,268 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 6 EACH | $300 | $785 | $420 | $475 | $585 |
| 407E20000 NON-TRACKING TACK COAT | 769 GAL | $3.25 | $2.75 | $3.05 | $4.00 | $2.75 |
| 411E10001 STABILIZED CRUSHED AGGREGATE, AS PER PLAN | 44 CY | $82.00 | $65.00 | $100 | $125 | $270 |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 233 FT | $37.25 | $20.00 | $63.00 | $17.00 | $20.00 |
| 609E31001 COMBINATION CURB AND GUTTER, TYPE 9, AS PER PLAN | 314 FT | $26.00 | $25.00 | $36.00 | $16.00 | $25.00 |
| 625E00450 CONNECTION, FUSED PULL APART | 12 EACH | $165 | $170 | $165 | $200 | $170 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 20 EACH | $145 | $160 | $145 | $177 | $160 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 5,220 FT | $3.00 | $3.30 | $3.00 | $4.00 | $3.30 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 1,008 FT | $0.80 | $1.50 | $0.80 | $1.00 | $1.50 |
| 625E26250 LUMINAIRE, CONVENTIONAL, TYPE III, SOLID STATE (LE | 12 EACH | $455 | $380 | $455 | $550 | $380 |
| 625E29002 TRENCH, 24" DEEP | 1,335 FT | $4.00 | $8.00 | $4.00 | $5.00 | $8.00 |
| 625E30706 PULL BOX, 725.08, 24" | 17 EACH | $860 | $1,000 | $860 | $1,040 | $1,000 |
| 625E32000 GROUND ROD | 14 EACH | $225 | $300 | $225 | $300 | $300 |
| 625E34000 POWER SERVICE | 1 EACH | $3,800 | $2,700 | $3,800 | $3,000 | $2,700 |
| 625E34450 CONTROL CENTER CABINET, COMPLETE | 1 EACH | $4,200 | $5,000 | $4,200 | $5,100 | $5,000 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 1,335 FT | $0.20 | $2.00 | $0.20 | $0.50 | $2.00 |
| 625E39000 TEMPORARY LIGHTING | 1 LS | $2,000 | $18,000 | $2,000 | $2,400 | $18,000 |
| 621E00100 RPM | 67 EACH | $92.50 | $100 | $43.00 | $45.00 | $41.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 450 FT | $17.00 | $11.40 | $26.00 | $15.00 | $22.52 |
| 630E80100 SIGN, FLAT SHEET | 314 SF | $22.50 | $27.50 | $26.00 | $16.00 | $26.26 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 46 EACH | $10.00 | $35.20 | $16.00 | $33.00 | $15.63 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 33 EACH | $15.00 | $45.95 | $22.00 | $45.00 | $20.85 |
| 644E00104 EDGE LINE, 6" | 0.8 MILE | $4,920 | $4,920 | $2,900 | $3,100 | $2,800 |
| 644E00300 CENTER LINE | 0.26 MILE | $9,225 | $9,225 | $4,000 | $4,500 | $4,000 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 274 FT | $7.35 | $7.35 | $7.00 | $8.00 | $7.00 |
| 644E01514 DOTTED LINE, 8" | 166 FT | $3.70 | $3.70 | $3.00 | $5.00 | $3.00 |
| 644E20800 YIELD LINE | 63 FT | $9.85 | $9.85 | $7.00 | $7.00 | $6.00 |
| 661E30000 EVERGREEN SHRUB, 12" HEIGHT (ARCADIA JUNIPER) | 5 EACH | $300 | $200 | $300 | $315 | $286 |
| 661E99930 PLANTING, MISC.: WEED BARRIER | 478 SY | $4.60 | $1.50 | $3.00 | $2.00 | $3.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 16 SNMT | $950 | $1,000 | $1,000 | $1,150 | $1,035 |
| 616E10000 WATER | 26 MGAL | $20.00 | $1.00 | $84.00 | $100 | $24.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,700 | $22,500 | $8,000 | $15,000 | $21,000 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $1,100 | $1,000 | $3,400 | $1,950 | $650 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 888 CY | $163 | $145k | 10% |
| 452E11011 7" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 1,173 SY | $120 | $141k | 10% |
| 203E10000 EXCAVATION | 3,818 CY | $27 | $103k | 7% |
| 304E20000 AGGREGATE BASE | 1,366 CY | $75 | $102k | 7% |
| 442E10081 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 314 CY | $261 | $82k | 6% |
| 442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 267 CY | $266 | $71k | 5% |
| 206E10500 CEMENT | 234 TON | $210.5 | $49k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $46,750 | $47k | 3% |
| 625E25500 CONDUIT, 3", 725.04 | 1,335 FT | $32 | $43k | 3% |
| 609E26000 CURB, TYPE 6 | 1,597 FT | $26.5 | $42k | 3% |