| Item | Quantity | R1Shelly & Sands INC | R2D G M INC | R3Allard Excavation LLC | % of bid |
|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 697 CY | $190 | $170 | $197 | 21% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 1,767 CY | $57.00 | $54.00 | $59.00 | 16% |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (200 CY | $240 | $215 | $235 | 8% |
| 304E20000 AGGREGATE BASE | 714 CY | $67.00 | $55.00 | $69.00 | 8% |
| 204E13000 EXCAVATION OF SUBGRADE | 1,767 CY | $25.00 | $20.00 | $25.00 | 7% |
| 619E16000 FIELD OFFICE, TYPE A | 12 MNTH | $3,200 | $500 | $1,200 | 6% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 142 CY | $245 | $225 |
| Item | Quantity | R1Shelly & Sands INC | R2D G M INC | R3Allard Excavation LLC |
|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" AND UNDER | 10 FT | $65.00 | $30.00 | $8.00 |
| 202E38000 GUARDRAIL REMOVED | 1,000 FT | $2.50 | $1.00 | $3.00 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 2 EACH | $200 | $250 | $154 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 3,150 SY | $1.40 | $3.30 | $3.10 |
| 659E20000 COMMERCIAL FERTILIZER | 0.43 TON | $1,400 | $1,500 | $2,950 |
| 659E31000 LIME | 0.65 ACRE |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $235 |
| 6% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 1,832 FT | $12.00 | $20.00 | $11.00 | 4% |
| 202E23000 PAVEMENT REMOVED | 2,303 SY | $9.00 | $20.00 | $6.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $52,643 | 3% |
| 203E10000 EXCAVATION | 663 CY | $30.00 | $40.00 | $16.00 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 825 FT | $19.80 | $15.00 | $14.16 | 3% |
| 611E07400 18" CONDUIT, TYPE B, 707.13 (0.079)GALVANIZED; 707 | 49 FT | $285 | $170 | $300 | 2% |
| 659E00300 TOPSOIL | 350 CY | $30.00 | $15.00 | $21.00 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,100 | $12,000 | $7,500 | 2% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 4 EACH | $2,500 | $2,250 | $2,200 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,000 | $6,500 | $18,438 | 1% |
| 203E20000 EMBANKMENT | 753 CY | $10.00 | $36.00 | $19.00 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,500 | $12,400 | $5,000 | 1% |
| 204E50000 GEOTEXTILE FABRIC | 3,533 SY | $1.50 | $1.35 | $1.00 | 1% |
| $150 |
| $300 |
| $1,500 |
| 659E35000 WATER | 17 MGAL | $1.00 | $1.00 | $20.00 |
| 670E00500 SLOPE EROSION PROTECTION | 1,162 SY | $2.50 | $2.50 | $1.70 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,000 | $2,000 | $2,344 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $4,800 | $3,000 | $13,800 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $2,200 | $3,000 | $2,750 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 6 SY | $200 | $150 | $111 |
| 602E20000 CONCRETE MASONRY | 0.3 CY | $5,000 | $3,500 | $2,911 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 147 FT | $28.00 | $20.00 | $41.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 3 EACH | $550 | $250 | $379 |
| 204E10000 SUBGRADE COMPACTION | 3,533 SY | $1.50 | $4.00 | $4.00 |
| 204E45000 PROOF ROLLING | 4 HOUR | $225 | $75.00 | $229 |
| 407E10000 TACK COAT | 552 GAL | $3.50 | $3.50 | $2.50 |
| 621E00100 RPM | 25 EACH | $113 | $113 | $150 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 25 EACH | $15.00 | $1.00 | $11.00 |
| 626E00112 BARRIER REFLECTOR, TYPE 3, BIDIRECTIONAL (POST MOU | 27 EACH | $12.00 | $10.00 | $9.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 114.6 FT | $15.00 | $15.00 | $13.00 |
| 630E80100 SIGN, FLAT SHEET | 43 SF | $20.00 | $25.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $20.00 | $15.00 | $31.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $20.00 | $15.00 | $31.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.35 MILE | $2,925 | $6,000 | $3,400 |
| 642E00300 CENTER LINE, TYPE 1 | 0.43 MILE | $4,450 | $3,500 | $3,200 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 20 HOUR | $90.00 | $50.00 | $75.00 |
| 614E13314 BARRIER REFLECTOR, TYPE 3, BIDIRECTIONAL | 21 EACH | $12.00 | $15.00 | $25.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,400 | $20,000 | $9,102 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,500 | $30,000 | $12,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 697 CY | $190 | $132k | 19% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 1,767 CY | $57 | $101k | 15% |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (200 CY | $240 | $48k | 7% |
| 304E20000 AGGREGATE BASE | 714 CY | $67 | $48k | 7% |
| 204E13000 EXCAVATION OF SUBGRADE | 1,767 CY | $25 | $44k | 6% |
| 619E16000 FIELD OFFICE, TYPE A | 12 MNTH | $3,200 | $38k | 6% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 142 CY | $245 | $35k | 5% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 1,832 FT | $12 | $22k | 3% |
| 202E23000 PAVEMENT REMOVED | 2,303 SY | $9 | $21k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 3% |