D04-SIGN FY2025 (Systematic)
D04 County · est $1.4M
Bid dateThursday, October 17—
D04 County · est $1.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 21 more items below.
| Item | Quantity | R1Cleveland Barricading Systems LLC | R2Lake Erie Construction Company | R3M P Dory CO | % of bid |
|---|---|---|---|---|---|
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN, U | 40,261 FT | $7.05 | $9.00 | $12.50 | 23% |
| 630E80100 SIGN, FLAT SHEET | 26,314 SF | $10.32 | $12.00 | $15.00 | 22% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 8,053 SF | $19.30 | $21.90 | $22.00 | 13% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 5,065 SF | $16.85 | $25.00 | $23.50 | 7% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4,453 EACH | $13.00 | $10.00 | $12.00 | 5% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 95 EACH | $595 | $675 | $850 | 5% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA |
| Item | Quantity | R1Cleveland Barricading Systems LLC | R2Lake Erie Construction Company | R3M P Dory CO |
|---|---|---|---|---|
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 574.6 FT | $9.85 | $17.50 | $22.00 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 33 FT | $34.00 | $38.00 | $20.00 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 88 FT | $41.00 | $52.00 | $25.00 |
| 630E08004 ONE WAY SUPPORT, NO. 3 POST | 184 FT | $13.00 | $13.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 3,424 EACH |
| $13.65 |
| $15.00 |
| $15.00 |
| 4% |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 444 EACH | $102 | $110 | $175 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $44,250 | $30,600 | $12,500 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $29,500 | $50,000 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $27,000 | $5,900 | $12,500 | 2% |
| 630E08600 SIGN POST REFLECTOR | 827 EACH | $20.00 | $30.00 | $43.50 | 1% |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 455 EACH | $34.25 | $25.00 | $20.00 | 1% |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 84 EACH | $170 | $175 | $125 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 11 MNTH | $1,200 | $375 | $1,000 | 1% |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 1,650 FT | $6.60 | $8.40 | $12.50 | 1% |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 97 EACH | $88.00 | $65.00 | $315 | 1% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 6 EACH | $1,185 | $1,125 | $1,500 | 1% |
| 630E82000 SIGN BACKING ASSEMBLY | 45 EACH | $145 | $145 | $200 | 1% |
| 630E08600 SIGN POST REFLECTOR | 297 EACH | $20.00 | $30.00 | $45.00 | 0% |
| $15.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 6 EACH | $445 | $625 | $450 |
| 630E79000 SIGN HANGER ASSEMBLY, SPAN WIRE | 15 EACH | $270 | $375 | $575 |
| 630E79100 SIGN HANGER ASSEMBLY, MAST ARM | 20 EACH | $265 | $395 | $575 |
| 630E79600 SIGN SUPPORT ASSEMBLY, BRIDGE MOUNTED, TYPE 1 | 1 EACH | $815 | $950 | $1,200 |
| 630E79611 SIGN SUPPORT ASSEMBLY, BARRIER MOUNTED, AS PER PLA | 2 EACH | $678 | $975 | $850 |
| 630E80101 SIGN, FLAT SHEET, AS PER PLAN | 170.9 SF | $12.00 | $22.00 | $20.00 |
| 630E85000 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE | 15 EACH | $11.95 | $35.00 | $45.00 |
| 630E85001 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE, AS PER | 1 EACH | $68.35 | $85.00 | $125 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 170 EACH | $24.00 | $50.00 | $50.00 |
| 630E85101 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION, AS | 126 EACH | $24.65 | $55.00 | $50.00 |
| 630E85600 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND REERECTIO | 2 EACH | $335 | $475 | $650 |
| 630E86292 REMOVAL OF GROUND MOUNTED WOODEN BOX BEAM SUPPORT | 9 EACH | $230 | $295 | $315 |
| 630E97700 SIGNING, MISC.: REMOVAL OF POST REFLECTOR | 21 EACH | $13.00 | $10.00 | $20.00 |
| AA2 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 96 FT | $23.25 | $15.00 | $25.00 |
| AA2 630E80101 SIGN, FLAT SHEET, AS PER PLAN | 40 SF | $59.00 | $16.50 | $35.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,959 | $8,240 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN, U | 40,261 FT | $7.05 | $284k | 22% |
| 630E80100 SIGN, FLAT SHEET | 26,314 SF | $10.32 | $272k | 21% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 8,053 SF | $19.3 | $155k | 12% |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 5,065 SF | $16.85 | $85k | 7% |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4,453 EACH | $13 | $58k | 5% |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 95 EACH | $595 | $57k | 4% |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3,424 EACH | $13.65 | $47k | 4% |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 444 EACH | $101.5 | $45k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $44,250 | $44k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |