D09-Guardrail Project FY2025
D09 County · est $0.7M
Bid dateThursday, January 16—
D09 County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 14 more items below.
| Item | Quantity | R1Pdk Construction INC | R2M P Dory CO | R3Lake Erie Construction Company | R4Cuyahoga Fence LLC | % of bid |
|---|---|---|---|---|---|---|
| 606E15050 GUARDRAIL, TYPE MGS | 12,887.5 FT | $16.86 | $19.00 | $19.60 | $21.50 | 37% |
| 203E40000 BORROW | 1,732 CY | $50.00 | $50.00 | $60.00 | $68.00 | 15% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 37 EACH | $2,180 | $2,500 | $2,750 | $2,650 | 14% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $53,300 | $5,000 | $18,500 | $25,000 | 9% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 1,725 FT | $18.26 | $20.50 | $22.40 | $24.50 | 5% |
| 202E38101 GUARDRAIL REMOVED FOR STORAGE, AS PER PLAN | 12,812.5 FT | $2.00 | $3.50 | $2.80 | $3.50 |
| Item | Quantity | R1Pdk Construction INC | R2M P Dory CO | R3Lake Erie Construction Company | R4Cuyahoga Fence LLC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $500 | $2,500 | $1,150 | $2,500 |
| 202E38001 GUARDRAIL REMOVED, AS PER PLAN | 100 FT | $1.60 | $3.00 | $3.00 | $2.00 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $150 | $120 | $150 | $150 |
| 606E13000 GUARDRAIL, TYPE 5 | 100 FT | $16.80 | $22.00 | $19.40 | $21.00 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4% |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 25 EACH | $1,000 | $900 | $825 | $1,300 | 4% |
| 659E10000 SEEDING AND MULCHING | 14,417 SY | $1.07 | $2.50 | $1.00 | $1.75 | 3% |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 50 EACH | $230 | $350 | $365 | $350 | 2% |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 100 FT | $108 | $112 | $128 | $125 | 2% |
| 606E26100 ANCHOR ASSEMBLY, TYPE E | 4 EACH | $2,180 | $2,450 | $2,725 | $2,550 | 1% |
| 624E10000 MOBILIZATION | 1 LS | $6,600 | $25,000 | $46,500 | $25,000 | 1% |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 2 EACH | $2,320 | $2,400 | $2,795 | $1,950 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,300 | $7,000 | $3,735 | $7,750 | 1% |
| 659E20000 COMMERCIAL FERTILIZER | 1.95 TON | $1,605 | $685 | $370 | $500 | 1% |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 4 EACH | $590 | $950 | $1,080 | $1,100 | 0% |
| 202E38000 GUARDRAIL REMOVED | 1,275 FT | $1.80 | $2.50 | $2.40 | $3.00 | 0% |
| 606E17350 GUARDRAIL, TYPE MGS, 25' LONG-SPAN | 100 FT | $22.38 | $28.00 | $22.00 | $25.00 | 0% |
| 209E60201 LINEAR GRADING, AS PER PLAN | 173 STA | $12.00 | $150 | $35.00 | $150 | 0% |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 12 EACH | $160 | $120 | $120 | $125 | 0% |
| 15 EACH |
| $100 |
| $100 |
| $150 |
| $150 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 5 EACH | $200 | $200 | $260 | $175 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 25 EACH | $50.00 | $50.00 | $120 | $75.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 721 SY | $1.07 | $1.00 | $0.50 | $0.50 |
| 659E31000 LIME | 3 ACRE | $214 | $155 | $50.00 | $75.00 |
| 659E35000 WATER | 78 MGAL | $1.00 | $10.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 626E00112 BARRIER REFLECTOR, TYPE 3 BI-DIRECTIONAL | 206 EACH | $9.00 | $12.00 | $13.00 | $13.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 100 FT | $13.00 | $15.00 | $12.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 25 EACH | $50.00 | $50.00 | $55.00 | $75.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 606E15050 GUARDRAIL, TYPE MGS | 12,887.5 FT | $16.86 | $217k | 36% |
| 203E40000 BORROW | 1,732 CY | $50 | $87k | 14% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 37 EACH | $2,180 | $81k | 13% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $53,300 | $53k | 9% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 1,725 FT | $18.26 | $31k | 5% |
| 202E38101 GUARDRAIL REMOVED FOR STORAGE, AS PER PLAN | 12,812.5 FT | $2 | $26k | 4% |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 25 EACH | $1,000 | $25k | 4% |
| 659E10000 SEEDING AND MULCHING | 14,417 SY | $1.07 | $15k | 3% |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 50 EACH | $230 | $12k | 2% |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING | 100 FT | $107.54 | $11k | 2% |