BEL-SR 647-03.29
BEL County · est $0.7M
Bid dateThursday, February 27—
BEL County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Alan Stone CO INC | R2Ohio-west Virginia Excavating CO | R3Craig Edward Susany INC | R4Dennison Bridge INC | R5Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:STEEL PILES W16x57, FURNISHED | 2,920 FT | $41.00 | $45.00 | $46.00 | $50.00 | $41.00 | 21% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 2,619 FT | $45.00 | $35.00 | $56.00 | $65.00 | $58.00 | 20% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 1,080 FT | $90.00 | $95.00 | $75.00 | $75.00 | $102 | 17% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $45,000 | $58,000 | $20,000 | $20,000 | $51,701 | 8% |
| 507E00400 STEEL PILES, MISC.:STEEL PILES W16x40, FURNISHED | 1,225 FT | $30.00 | $33.00 | $29.00 | $39.00 | $30.00 | 6% |
| Item | Quantity | R1Alan Stone CO INC | R2Ohio-west Virginia Excavating CO | R3Craig Edward Susany INC | R4Dennison Bridge INC | R5Shelly & Sands INC |
|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 206 SY | $15.00 | $50.00 | $25.00 | $25.00 | $42.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 70 FT | $30.00 | $21.00 | $10.00 | $30.00 | $15.00 |
| 202E38000 GUARDRAIL REMOVED | 387.5 FT | $5.00 | $5.00 | $2.00 | $2.00 | $2.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 30" DIAMETER, UN | 420 FT | $60.00 | $84.00 | $76.00 | $85.00 | $86.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $23,500 | $16,500 | $20,000 | $16,000 | $35,000 | 4% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 146 SY | $150 | $150 | $180 | $210 | $90.00 | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 600 FT | $22.00 | $22.00 | $16.00 | $12.00 | $30.00 | 2% |
| 611E07400 18" CONDUIT, TYPE B | 50 FT | $220 | $200 | $450 | $300 | $325 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1 1/4" DEPTH) | 325 SY | $30.00 | $12.00 | $21.00 | $22.00 | $20.00 | 2% |
| 606E15151 GUARDRAIL, TYPE MGS HALF POST SPACING, AS PER PLAN | 287.5 FT | $30.00 | $32.00 | $30.00 | $31.00 | $29.50 | 1% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 26 CY | $320 | $355 | $500 | $500 | $600 | 1% |
| 690E98600 SPECIAL - DRILLING THROUGH OBSTRUCTIONS | 10 HOUR | $700 | $550 | $300 | $400 | $800 | 1% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $3,300 | $3,500 | $2,600 | $2,500 | $3,100 | 1% |
| 304E20000 AGGREGATE BASE | 50 CY | $130 | $150 | $150 | $145 | $165 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,200 | $2,500 | $1,000 | $2,000 | $2,200 | 1% |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 17 CY | $350 | $420 | $500 | $700 | $600 | 1% |
| 530E50010 SPECIAL - RETAINING WALL, CAST-IN-PLACE CONCRETE L | 27 SF | $200 | $150 | $250 | $100 | $125 | 1% |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $5,000 | $2,700 | $3,500 | $4,500 | $4,500 | 1% |
| $500 |
| $1,500 |
| $500 |
| $1,000 |
| $175 |
| 202E98000 REMOVAL MISC.:RETAINING WALL | 1 LS | $4,600 | $1,500 | $1,000 | $2,500 | $11,000 |
| 204E10000 SUBGRADE COMPACTION | 230 SY | $4.00 | $6.00 | $2.00 | $3.00 | $8.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 100 FT | $25.00 | $23.00 | $22.00 | $23.00 | $24.50 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 2 EACH | $200 | $400 | $100 | $200 | $210 |
| 601E34200 ROCK CHANNEL PROTECTION, TYPE C WITHOUT FILTER | 2 CY | $300 | $900 | $250 | $400 | $300 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 361 SY | $4.00 | $7.00 | $7.00 | $10.00 | $8.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E06020 4" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 305 FT | $7.00 | $15.00 | $16.00 | $25.00 | $20.00 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 12 FT | $40.00 | $32.00 | $16.00 | $30.00 | $45.00 |
| 611E99711 PRECAST REINFORCED CONCRETE OUTLET, AS PER PLAN | 1 EACH | $350 | $800 | $200 | $400 | $350 |
| 407E10000 TACK COAT | 49 GAL | $5.00 | $9.00 | $8.00 | $4.00 | $4.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 29 GAL | $5.00 | $9.00 | $20.00 | $50.00 | $55.00 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (8 CY | $440 | $550 | $500 | $600 | $600 |
| 621E00100 RPM | 9 EACH | $350 | $350 | $325 | $500 | $325 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 9 EACH | $20.00 | $40.00 | $10.00 | $20.00 | $25.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 9 EACH | $10.00 | $12.00 | $11.00 | $12.00 | $10.00 |
| 646E10010 EDGE LINE, 6" | 0.12 MILE | $10,500 | $17,000 | $26,750 | $27,500 | $24,000 |
| 646E10200 CENTER LINE | 0.06 MILE | $5,000 | $28,000 | $48,500 | $50,000 | $44,500 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $250 | $400 | $600 | $225 | $500 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.06 MILE | $10,000 | $10,000 | $64,600 | $10,000 | $9,750 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.12 MILE | $5,000 | $5,000 | $32,325 | $5,500 | $5,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,000 | $8,500 | $18,000 | $8,000 | $5,100 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:STEEL PILES W16x57, FURNISHED | 2,920 FT | $41 | $120k | 19% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 2,619 FT | $45 | $118k | 19% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 1,080 FT | $90 | $97k | 16% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $45,000 | $45k | 7% |
| 507E00400 STEEL PILES, MISC.:STEEL PILES W16x40, FURNISHED | 1,225 FT | $30 | $37k | 6% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 30" DIAMETER, UN | 420 FT | $60 | $25k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $23,500 | $24k | 4% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 146 SY | $150 | $22k | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 600 FT | $22 | $13k | 2% |
| 611E07400 18" CONDUIT, TYPE B | 50 FT | $220 | $11k | 2% |