BEL-SR 148-08.45
BEL County · est $0.6M
Bid dateThursday, April 10—
BEL County · est $0.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 39 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Double B Excavating LLC | R3S.t.a.r.t., LLC | R4Lms Construction INC | R5V3 Construction Group LTD | R6Ed Wilson Services LLC | R7Tucson INC | R8Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 1,246 CY | $50.50 | $20.07 | $25.60 | $23.00 | $39.00 | $32.00 | $33.50 | $73.50 | 15% |
| 601E32004 ROCK CHANNEL PROTECTION, TYPE A WITH GEOTEXTILE FA | 1,027 CY | $59.00 | $91.53 | $74.10 | $112 | $120 | $160 |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Double B Excavating LLC | R3S.t.a.r.t., LLC | R4Lms Construction INC | R5V3 Construction Group LTD | R6Ed Wilson Services LLC | R7Tucson INC | R8Eclipse CO LLC |
|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $5,000 | $4,954 | $5,000 | $8,900 | $6,000 | $11,950 | $3,500 |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 99 FT | $48.00 | $12.15 | $65.21 | $8.00 | $47.00 | $38.00 | $20.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $114 |
| $200 |
| 15% |
| 611E16200 36" CONDUIT, TYPE A (706.01, 707.05 (0.109) GALVAN | 112 FT | $327 | $147 | $292 | $320 | $220 | $215 | $429 | $287 | 9% |
| 304E20000 AGGREGATE BASE | 278 CY | $125 | $79.14 | $102 | $135 | $110 | $100 | $140 | $105 | 8% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 252 SY | $120 | $29.77 | $75.97 | $60.00 | $37.00 | $95.00 | $101 | $140 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $5,000 | $35,050 | $30,000 | $10,100 | $7,000 | $25,000 | $12,309 | 7% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $21,000 | $130,000 | $20,189 | $500 | $34,400 | $15,000 | $24,100 | $60,000 | 5% |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 237 CY | $71.00 | $92.83 | $73.53 | $119 | $150 | $160 | $118 | $224 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $10,000 | $29,370 | $26,300 | $25,299 | $25,000 | $28,700 | $34,239 | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 50 CY | $295 | $200 | $378 | $450 | $320 | $495 | $447 | $378 | 4% |
| 203E35001 GRANULAR EMBANKMENT, AS PER PLAN | 139 CY | $102 | $86.34 | $91.80 | $143 | $100 | $90.00 | $115 | $143 | 3% |
| 602E98300 MASONRY, MISC.: HEADWALL, SLOPED & MITERED CONCRET | 2 EACH | $6,200 | $2,200 | $4,748 | $8,000 | $7,900 | $9,000 | $9,500 | $8,298 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $16,000 | $8,500 | $20,000 | $5,900 | $8,000 | $10,500 | $14,000 | 2% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 312.5 FT | $29.00 | $23.68 | $27.40 | $27.40 | $37.00 | $31.00 | $33.35 | $29.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 271 SY | $30.00 | $18.46 | $41.21 | $14.00 | $14.00 | $48.00 | $20.00 | $41.50 | 2% |
| 203E20000 EMBANKMENT | 82 CY | $94.00 | $24.40 | $37.71 | $47.00 | $37.00 | $50.00 | $53.00 | $61.00 | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 350 FT | $22.00 | $28.58 | $41.01 | $50.00 | $21.00 | $50.00 | $67.50 | $83.00 | 2% |
| 659E00300 TOPSOIL | 138 CY | $55.00 | $61.60 | $48.94 | $10.00 | $39.00 | $65.00 | $60.50 | $130 | 2% |
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 17 CY | $395 | $235 | $767 | $650 | $420 | $710 | $906 | $767 | 2% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $3,150 | $2,000 | $3,220 | $3,220 | $3,400 | $3,200 | $3,000 | $3,280 | 2% |
| $26.00 |
| 202E38000 GUARDRAIL REMOVED | 313 FT | $7.00 | $6.39 | $2.50 | $1.00 | $5.25 | $6.00 | $6.50 | $2.50 |
| 204E10000 SUBGRADE COMPACTION | 316 SY | $6.00 | $7.92 | $8.91 | $4.00 | $20.00 | $5.00 | $2.50 | $2.50 |
| 204E50001 GEOTEXTILE FABRIC, AS PER PLAN | 1,725 SY | $2.00 | $1.45 | $4.93 | $5.00 | $2.75 | $2.00 | $4.60 | $17.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $1,600 | $75.54 | $50.00 | $1,600 | $110 | $75.00 | $125 |
| 659E10000 SEEDING AND MULCHING | 1,240 SY | $3.00 | $4.84 | $1.78 | $2.00 | $4.25 | $2.00 | $4.90 | $4.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 62 SY | $3.00 | $5.17 | $2.07 | $2.00 | $9.50 | $4.00 | $0.75 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.17 TON | $1,250 | $2,647 | $1,155 | $1,500 | $2,100 | $3,000 | $1,750 | $892 |
| 659E31000 LIME | 0.26 ACRE | $150 | $769 | $185 | $1,200 | $1,300 | $2,000 | $850 | $156 |
| 659E35000 WATER | 10 MGAL | $1.00 | $20.00 | $1.00 | $10.00 | $160 | $30.00 | $1.00 | $1.00 |
| 660E25000 SODDING STAKED | 10 SY | $100 | $40.00 | $48.34 | $20.00 | $74.00 | $42.00 | $43.50 | $30.00 |
| 660E30000 SODDING UNSTAKED | 51 SY | $35.00 | $31.38 | $37.71 | $12.00 | $53.00 | $30.00 | $38.75 | $15.75 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/4" | 239 SY | $15.00 | $24.27 | $18.00 | $30.00 | $37.00 | $55.00 | $21.25 | $18.00 |
| 407E10000 TACK COAT | 49 GAL | $5.00 | $71.43 | $4.00 | $3.50 | $1.00 | $6.00 | $4.75 | $4.00 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (13 CY | $450 | $231 | $584 | $575 | $470 | $660 | $690 | $584 |
| 621E00100 RPM | 6 EACH | $475 | $58.34 | $814 | $475 | $670 | $520 | $561 | $475 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 6 EACH | $40.00 | $33.34 | $37.20 | $20.00 | $110 | $45.00 | $17.00 | $27.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 48.5 FT | $8.00 | $8.25 | $41.30 | $22.00 | $23.00 | $60.00 | $14.25 | $24.00 |
| 630E08600 SIGN POST REFLECTOR | 4 EACH | $25.00 | $37.50 | $129 | $44.50 | $47.00 | $275 | $30.00 | $47.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 4 EACH | $50.00 | $25.00 | $127 | $65.00 | $68.00 | $400 | $60.00 | $60.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $10.00 | $25.00 | $21.46 | $20.00 | $21.00 | $375 | $12.00 | $20.00 |
| 646E10010 EDGE LINE, 6" | 0.08 MILE | $24,000 | $4,375 | $42,685 | $15,000 | $15,800 | $50,000 | $27,850 | $60,000 |
| 646E10200 CENTER LINE | 0.04 MILE | $34,000 | $7,500 | $56,980 | $40,000 | $21,500 | $66,000 | $39,910 | $60,000 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 2 EACH | $2,000 | $2,000 | $3,929 | $2,500 | $4,200 | $11,000 | $11,575 | $5,600 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 15 CY | $350 | $187 | $274 | $100 | $530 | $200 | $445 | $1,550 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BI-DIRECTIONAL | 8 EACH | $40.00 | $77.50 | $40.00 | $40.00 | $56.00 | $45.00 | $48.00 | $40.00 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 15 EACH | $45.00 | $167 | $44.00 | $44.00 | $62.00 | $45.00 | $52.00 | $44.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 23 EACH | $35.00 | $109 | $34.00 | $34.00 | $48.00 | $40.00 | $40.50 | $34.00 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.12 MILE | $6,700 | $2,500 | $6,650 | $6,650 | $9,300 | $10,000 | $7,850 | $6,650 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.18 MILE | $15,000 | $2,083 | $14,250 | $14,250 | $20,000 | $17,000 | $16,820 | $14,250 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.24 MILE | $3,500 | $2,500 | $3,300 | $3,300 | $4,600 | $9,000 | $3,895 | $3,300 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.38 MILE | $10,000 | $1,974 | $9,750 | $9,750 | $13,700 | $14,000 | $11,510 | $9,750 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 20 FT | $15.00 | $30.00 | $14.00 | $14.00 | $20.00 | $8.00 | $16.55 | $14.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,500 | $5,000 | $3,543 | $10,000 | $4,700 | $8,000 | $15,510 | $12,000 |
| 616E10000 WATER | 5 MGAL | $10.00 | $50.00 | $2.00 | $10.00 | $260 | $20.00 | $1.00 | $88.50 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $1,000 | $1,250 | $3,000 | $1,500 | $2,600 | $2,100 | $1,500 | $879 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,400 | $8,000 | $4,598 | $2,000 | $8,900 | $11,000 | $11,500 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E10000 EXCAVATION | 1,246 CY | $50.5 | $63k | 13% |
| 601E32004 ROCK CHANNEL PROTECTION, TYPE A WITH GEOTEXTILE FA | 1,027 CY | $59 | $61k | 12% |
| 611E16200 36" CONDUIT, TYPE A (706.01, 707.05 (0.109) GALVAN | 112 FT | $327 | $37k | 7% |
| 304E20000 AGGREGATE BASE | 278 CY | $125 | $35k | 7% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 252 SY | $120 | $30k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $30k | 6% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $21,000 | $21k | 4% |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 237 CY | $71 | $17k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $15k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 50 CY | $295 | $15k | 3% |