HAN-SR 15-20.26
HAN County · est $0.3M
Bid dateThursday, July 31—
HAN County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 15 more items below.
| Item | Quantity | R1Advanced Excavating & Demolition | R2LLC Eagle Bridge CO | R3Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 249 CY | $205 | $205 | $219 | 24% |
| 304E20000 AGGREGATE BASE | 422 CY | $67.50 | $105 | $65.00 | 13% |
| 203E10000 EXCAVATION | 1,107 CY | $23.50 | $42.50 | $45.00 | 12% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 77 CY | $300 | $300 | $321 | 11% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 300 CY | $62.50 | $60.00 | $47.00 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $8,500 | $12,500 | $31,112 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS |
| Item | Quantity | R1Advanced Excavating & Demolition | R2LLC Eagle Bridge CO | R3Eclipse CO LLC |
|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 42 SY | $30.00 | $30.00 | $50.00 |
| 202E38000 GUARDRAIL REMOVED | 45 FT | $35.00 | $12.00 | $17.00 |
| 202E75000 FENCE REMOVED | 33 FT | $10.00 | $11.00 | $11.00 |
| 203E20000 EMBANKMENT | 10 CY | $35.00 | $42.50 | $63.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $285 | $135 | $242 |
| 616E10000 WATER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $8,000 |
| $7,500 |
| $4,248 |
| 4% |
| 204E13000 EXCAVATION OF SUBGRADE | 300 CY | $25.00 | $20.00 | $35.00 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,500 | $5,000 | $3,973 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,500 | $5,000 | $9,467 | 3% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 605E31100 AGGREGATE DRAINS | 240 FT | $18.00 | $12.00 | $12.00 | 2% |
| 204E50000 GEOTEXTILE FABRIC | 1,680 SY | $2.50 | $1.50 | $2.00 | 2% |
| 659E10000 SEEDING AND MULCHING | 975 SY | $3.10 | $6.00 | $4.50 | 1% |
| 607E15000 FENCE, TYPE 47 | 33 FT | $91.50 | $91.50 | $97.50 | 1% |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 86 FT | $32.50 | $32.50 | $35.00 | 1% |
| 659E00300 TOPSOIL | 106 CY | $26.00 | $15.00 | $74.50 | 1% |
| 204E10000 SUBGRADE COMPACTION | 2,286 SY | $0.95 | $4.00 | $1.50 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,000 | $1,000 | $1,410 | 1% |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $2,000 | $5,000 | $4,815 | 1% |
| 1 MGAL |
| $1.00 |
| $20.00 |
| $1.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 48 SY | $3.10 | $3.00 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.13 TON | $850 | $1,500 | $615 |
| 659E31000 LIME | 0.2 ACRE | $35.00 | $10.00 | $48.15 |
| 659E35000 WATER | 5 MGAL | $1.00 | $20.00 | $1.00 |
| 407E20000 NON-TRACKING TACK COAT | 176 GAL | $3.00 | $3.00 | $3.00 |
| 630E08600 SIGN POST REFLECTOR | 8 EACH | $45.00 | $45.00 | $48.00 |
| 630E80100 SIGN, FLAT SHEET | 26 SF | $40.00 | $40.00 | $43.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $15.00 | $15.00 | $16.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $25.00 | $25.00 | $27.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 249 CY | $205 | $51k | 23% |
| 304E20000 AGGREGATE BASE | 422 CY | $67.5 | $28k | 13% |
| 203E10000 EXCAVATION | 1,107 CY | $23.5 | $26k | 12% |
| 441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 77 CY | $300 | $23k | 10% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 300 CY | $62.5 | $19k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $8,500 | $9k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,000 | $8k | 4% |
| 204E13000 EXCAVATION OF SUBGRADE | 300 CY | $25 | $8k | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,500 | $7k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,500 | $7k | 3% |