GEA-US 322-05.76 Slope
GEA County · est $0.7M
Bid dateThursday, December 4—
GEA County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 34 more items below.
| Item | Quantity | R1Madex Construction CO | R2Shook Company LLC | R3Cook Paving & Construction CO INC | % of bid |
|---|---|---|---|---|---|
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $290,632 | $275,000 | $350,000 | 32% |
| 203E20000 EMBANKMENT | 2,907 CY | $37.53 | $50.00 | $40.00 | 12% |
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 637 SY | $134 | $135 | $120 | 9% |
| 609E26000 CURB, TYPE 6 | 780 FT | $66.84 | $50.00 | $50.00 | 6% |
| 203E10000 EXCAVATION | 1,478 CY | $33.25 | $35.00 | $55.00 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $41,004 | $75,000 | $65,000 | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $40,675 |
| Item | Quantity | R1Madex Construction CO | R2Shook Company LLC | R3Cook Paving & Construction CO INC |
|---|---|---|---|---|
| 202E32000 CURB REMOVED | 98 FT | $20.72 | $20.00 | $12.00 |
| 202E38000 GUARDRAIL REMOVED | 598 FT | $9.79 | $3.00 | $2.00 |
| 204E10000 SUBGRADE COMPACTION | 767 SY | $4.63 | $2.00 | $5.00 |
| 209E10000 DITCH CLEANOUT | 20 FT | $80.07 | $25.00 | $30.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, (MASH 2016) | 2 EACH | $3,474 | $3,000 | $3,000 |
| 623E40500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $47,829 |
| $50,000 |
| 4% |
| 304E20000 AGGREGATE BASE | 320 CY | $97.66 | $100 | $115 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $28,842 | $45,000 | $10,000 | 3% |
| 659E00300 TOPSOIL | 371 CY | $75.63 | $45.00 | $48.00 | 3% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 773 FT | $27.54 | $15.00 | $30.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 445 SY | $41.68 | $15.00 | $55.00 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 625 FT | $28.32 | $30.00 | $22.00 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $16,579 | $7,722 | $15,000 | 2% |
| 659E10000 SEEDING AND MULCHING | 3,338 SY | $4.63 | $3.00 | $1.15 | 2% |
| 423E00150 CRACK SEALING, TYPE IV | 1,300 LB | $11.58 | $7.50 | $6.00 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $14,579 | $15,000 | $50,000 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $11,113 | $10,000 | $35,000 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $1,621 | $1,231 | $1,000 | 1% |
| 611E05900 15" CONDUIT, TYPE B | 76 FT | $127 | $125 | $95.00 | 1% |
| 1 EACH |
| $1,737 |
| $1,500 |
| $800 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 7 EACH | $868 | $1,500 | $1,000 |
| 625E32000 GROUND ROD | 1 EACH | $70.53 | $150 | $400 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 1.11 CY | $1,158 | $200 | $450 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $289 | $50.00 | $400 |
| 659E14000 REPAIR SEEDING AND MULCHING | 167 SY | $2.32 | $1.00 | $2.00 |
| 659E15000 INTER-SEEDING | 167 SY | $2.32 | $0.10 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.46 TON | $1,158 | $1,000 | $1,200 |
| 659E31000 LIME | 0.69 ACRE | $579 | $1,000 | $300 |
| 659E35000 WATER | 28 MGAL | $28.95 | $1.00 | $10.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.2 CY | $4,795 | $5,000 | $3,000 |
| 611E06100 15" CONDUIT, TYPE C | 20 FT | $174 | $125 | $95.00 |
| 611E98180 CATCH BASIN, NO. 3A | 2 EACH | $4,139 | $3,500 | $6,000 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $6,947 | $7,000 | $5,000 |
| 621E00100 RPM, ONE-WAY (WHITE) | 16 EACH | $203 | $135 | $200 |
| 621E00100 RPM, TWO-WAY (YELLOW/YELLOW) | 11 EACH | $203 | $135 | $200 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $347 | $100 | $100 |
| 807E12010 WET REFLECTIVE EPOXY PAVEMENT MARKING, EDGE LINE, | 0.3 MILE | $10,421 | $6,300 | $12,000 |
| 807E12200 WET REFLECTIVE EPOXY PAVEMENT MARKING, CENTER LINE | 0.31 MILE | $13,895 | $6,300 | $13,000 |
| 850E10000 GROOVING FOR 4" RECESSED PAVEMENT MARKING | — | $9,263 | $6,500 | $4,000 |
| 850E10010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $10,421 | $6,500 | $4,200 |
| 850E20010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $16,211 | $6,500 | $4,200 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $116 | $50.00 | $85.00 |
| 616E10000 WATER | 18 MGAL | $17.37 | $1.00 | $55.00 |
| 630E97800 SIGNING, MISC.:ADDITIONAL SIGNS, GROUND MOUNTED, A | 300 SF | $2.00 | $28.72 | $37.50 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 4 MNTH | $937 | $1,500 | $2,500 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $3,895 | $2,200 | $2,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $2,895 | $2,200 | $2,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $290,632 | $291k | 29% |
| 203E20000 EMBANKMENT | 2,907 CY | $37.53 | $109k | 11% |
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 637 SY | $133.68 | $85k | 9% |
| 609E26000 CURB, TYPE 6 | 780 FT | $66.84 | $52k | 5% |
| 203E10000 EXCAVATION | 1,478 CY | $33.25 | $49k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $41,004 | $41k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $40,675 | $41k | 4% |
| 304E20000 AGGREGATE BASE | 320 CY | $97.66 | $31k | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $28,842 | $29k | 3% |
| 659E00300 TOPSOIL | 371 CY | $75.63 | $28k | 3% |