DAR-Tecumseh Trail RSF Ph 1
DAR County · est $0.2M
Bid dateThursday, April 9—
Awarded toHENRY W BERGMAN INC$146,026.6
DAR County · est $0.2M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 860E10010 THINLAY ASPHALT CONCRETE, TYPE LTPAVEMENT Section 2 - PAVEMENT - Totals Awd $127,925.60 2 $138,519.30 | 325 CY | $350 | $114k | 78% |
| 422E25000 EMULSION, CHIP SEALPAVEMENT | 1,096 GAL | $8.6 | $9k | 6% |
| 608E53021 DETECTABLE WARNING, AS PER PLANROADWAY Section 1 - ROADWAY - Totals Awd $6,600.00 2 $9,702.00 | 66 SF | $100 | $7k | 5% |
| 624E10000 MOBILIZATIONINCIDENTALS | 1 LS | $6,000 | $6k | 4% |
| 407E20000 NON-TRACKING TACK COATPAVEMENT | 875 GAL | $4 | $4k | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $3k | 2% |
| 614E11000 MAINTAINING TRAFFICINCIDENTALS | 1 LS | $2,500 | $3k | 2% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE APAVEMENT | 2,500 SY | $0.5 | $1k | 1% |
| 832E30000 EROSION CONTROLINCIDENTALS Section 3 - INCIDENTALS - Totals Awd $11,501.00 2 $8,001.00 | 1 EACH | $1 | $1 | 0% |
ODOT bid tab line items with each bidder’s unit price. Top 9items by winning bid’s extended amount.
| Item | Quantity | R1Henry W Bergman INC | R2Walls Bros Asphalt CO INC | % of bid |
|---|---|---|---|---|
| 860E10010 THINLAY ASPHALT CONCRETE, TYPE LTPAVEMENT Section 2 - PAVEMENT - Totals Awd $127,925.60 2 $138,519.30 | 325 CY | $350 | $368 | 78% |
| 422E25000 EMULSION, CHIP SEALPAVEMENT | 1,096 GAL | $8.60 | $5.80 | 6% |
| 608E53021 DETECTABLE WARNING, AS PER PLANROADWAY Section 1 - ROADWAY - Totals Awd $6,600.00 2 $9,702.00 | 66 SF | $100 | $147 | 5% |
| 624E10000 MOBILIZATIONINCIDENTALS | 1 LS | $6,000 | $1,500 | 4% |
| 407E20000 NON-TRACKING TACK COATPAVEMENT | 875 GAL | $4.00 | $6.50 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $500 | 2% |
| 614E11000 MAINTAINING TRAFFICINCIDENTALS | 1 LS | $2,500 | $6,000 | 2% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE APAVEMENT | 2,500 SY | $0.50 | $2.75 | 1% |
| 832E30000 EROSION CONTROLINCIDENTALS Section 3 - INCIDENTALS - Totals Awd $11,501.00 2 $8,001.00 | 1 EACH | $1.00 | $1.00 | 0% |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →