Figure 0.1 · BRIEFING
BID #260202 · ODOTRESULT · awarded Apr 23

HAN-McComb Ped Improvements

HAN County · est $0.2M

Bid dateThursday, April 23
Awarded toADVANCED EXCAVATING & DEMOLITION$206,097
read → connected → answeredcassandri

Project scope

Bid form · ODOT

35ITEMS
  • Curb, Walk & Ramp17%
  • Earthwork14%
  • Mobilization & General14%
  • Erosion & Landscaping11%
  • Signs11%
  • Maintaining Traffic11%
  • Other20%

Top items by winning bid

ItemQtyUnit priceExtended%
630E97700 SIGNING, MISC.:SOLAR POWERED RECTANGULAR RAPID FLA6 EACH$8,750$53k25%
608E10001 4" CONCRETE WALK, AS PER PLAN1,915 SF$19$36k18%
609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN181 FT$78$14k7%
609E26001 CURB, TYPE 6, AS PER PLAN195 FT$65$13k6%
614E11000 MAINTAINING TRAFFIC1 LS$10,000$10k5%
608E52001 CURB RAMP, AS PER PLAN391 SF$25$10k5%
202E30000 WALK REMOVED992 SF$7$7k3%
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$6,500$7k3%
253E01000 PAVEMENT REPAIR Section 3 - PAVEMENT - Totals Awd $5,100.00 2 $3,300.006 SY$850$5k2%
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $9,127.00 2 $12,960.555,000 EACH$1$5k2%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 15 more items below.

Rank 1Advanced Excavating & Demolition$206kRank 2LLC Fenson Contracting LLC$229k
ItemQuantityR1Advanced Excavating & DemolitionR2LLC Fenson Contracting LLC
630E97700 SIGNING, MISC.:SOLAR POWERED RECTANGULAR RAPID FLA6 EACH$8,750$10,150
608E10001 4" CONCRETE WALK, AS PER PLAN1,915 SF$19.00$16.00
609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN181 FT$78.00$75.00
609E26001 CURB, TYPE 6, AS PER PLAN195 FT$65.00$65.00
614E11000 MAINTAINING TRAFFIC1 LS$10,000$14,000
608E52001 CURB RAMP, AS PER PLAN391 SF$25.00$28.00
202E30000 WALK REMOVED992 SF$7.00$13.25
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$6,500$7,250
253E01000 PAVEMENT REPAIR Section 3 - PAVEMENT - Totals Awd $5,100.00 2 $3,300.006 SY$850$550
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $9,127.00 2 $12,960.555,000 EACH$1.00$1.00
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$5,000$2,500
624E10000 MOBILIZATION1 LS$5,000$10,000
630E80100 SIGN, FLAT SHEET197 SF$22.00$25.50
202E32500 CURB AND GUTTER REMOVED123 FT$30.00$15.00
512E74500 REMOVAL OF EXISTING PAVEMENT MARKING181 FT$20.00$25.00
644E00630 CROSSWALK LINE, 24" Section 5 - TRAFFIC CONTROL - Totals Awd $62,668.00 2 $72,671.30416 FT$8.00$9.20
202E23000 PAVEMENT REMOVED83 SY$30.00$80.00
659E00300 TOPSOIL30 CY$75.00$150
608E53020 DETECTABLE WARNING40 SF$50.00$28.00
900E17000 SPECIAL - PRECONSTRUCTION VIDEO Section 7 - INCIDENTALS - Totals Awd $28,510.00 2 $34,800.001 LS$2,000$950
Show all 35 line items
ItemQuantityR1Advanced Excavating & DemolitionR2LLC Fenson Contracting LLC
201E11000 CLEARING AND GRUBBING1 LS$1,500$3,800
203E10000 EXCAVATION19 CY$70.00$65.00
623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R1 LS$1,500$1,500
623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND Section 1 - ROADWAY - Totals Awd $97,527.00 2 $103,147.001 LS$1,500$1,500
659E10000 SEEDING AND MULCHING265 SY$7.00$12.75
659E14000 REPAIR SEEDING AND MULCHING14 SY$1.50$5.70
659E35000 WATER2 MGAL$0.50$1.00
638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN Section 4 - WATER WORK - Totals Awd $1,500.00 2 $750.002 EACH$750$375
630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST78 FT$14.00$16.50
630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION2 EACH$75.00$90.00
642E00701 TRANSVERSE/DIAGONAL LINE, TYPE 1, AS PER PLAN (4"480 FT$2.00$2.30
644E00500 STOP LINE38 FT$8.00$9.20
607E30000 FENCE, SNOW115 FT$11.00$8.00
614E12461 WORK ZONE MARKING SIGN, AS PER PLAN Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $1,665.00 2 $1,380.004 EACH$100$115
616E10000 WATER2 MGAL$5.00$50.00

Project details

Description
HAN-McComb Ped Improvements
Type of work
Safety

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →