HAR-SR 67-Sidewalks
HAR County · est $1.0M
Bid dateThursday, April 9—
Awarded toD L SMITH CONCRETE LLC$1.07M
HAR County · est $1.0M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 21,461 SF | $9 | $193k | 18% |
| 452E13011 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 1,031 SY | $120 | $124k | 12% |
| 624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $174,680.00 2 $150,580.00 | 1 LS | $83,000 | $83k | 8% |
| 202E23000 PAVEMENT REMOVED | 2,245 SY | $25 | $56k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $45,000 | $45k | 4% |
| 659E00300 TOPSOIL | 661 CY | $55 | $36k | 3% |
| 301E56100 ASPHALT CONCRETE BASE, PG64-22, (449), (DRIVEWAYS) | 55 CY | $565 | $31k | 3% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $104,170.10 2 $98,996.00 | 30,000 EACH | $1 | $30k | 3% |
| 203E10000 EXCAVATION | 919 CY | $30 | $28k | 3% |
| 611E01800 8" CONDUIT, TYPE B | 288 FT | $85 | $24k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 77 more items below.
| Item | Quantity | R1D L Smith Concrete LLC | R2Helms And Sons Excavating | % of bid |
|---|---|---|---|---|
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 21,461 SF | $9.00 | $10.00 | 23% |
| 452E13011 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 1,031 SY | $120 | $123 | 15% |
| 624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $174,680.00 2 $150,580.00 | 1 LS | $83,000 | $50,000 | 10% |
| 202E23000 PAVEMENT REMOVED | 2,245 SY | $25.00 | $13.00 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $45,000 | $22,500 | 5% |
| 659E00300 TOPSOIL | 661 CY | $55.00 | $50.00 | 4% |
| 301E56100 ASPHALT CONCRETE BASE, PG64-22, (449), (DRIVEWAYS) | 55 CY | $565 | $292 | 4% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $104,170.10 2 $98,996.00 | 30,000 EACH | $1.00 | $1.00 | 4% |
| 203E10000 EXCAVATION | 919 CY | $30.00 | $38.00 | 3% |
| 611E01800 8" CONDUIT, TYPE B | 288 FT | $85.00 | $101 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $22,500 | $15,000 | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 1,013 SF | $22.00 | $27.00 | 3% |
| 442E22420 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 24 CY | $885 | $715 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $21,000 | $30,240 | 3% |
| 304E20000 AGGREGATE BASE | 322 CY | $60.00 | $112 | 2% |
| 442E22120 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 17 CY | $1,025 | $720 | 2% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 199 CY | $80.00 | $117 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $15,000 | 2% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 25 CY | $565 | $360 | 2% |
| 611E98470 CATCH BASIN, NO. 2-2B | 3 EACH | $4,500 | $3,775 | 2% |
| Item | Quantity | R1D L Smith Concrete LLC | R2Helms And Sons Excavating |
|---|---|---|---|
| 202E30000 WALK REMOVED | 107 SF | $3.00 | $8.00 |
| 202E32000 CURB REMOVED | 423 FT | $12.00 | $14.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 97 FT | $20.00 | $84.00 |
| 202E58100 CATCH BASIN REMOVED | 5 EACH | $800 | $1,450 |
| 202E98200 REMOVAL MISC.:CONDUIT | 10 FT | $100 | $75.00 |
| 203E20000 EMBANKMENT | 167 CY | $35.00 | $18.00 |
| 204E10000 SUBGRADE COMPACTION | 221 SY | $13.50 | $2.00 |
| 608E41000 CONCRETE STEPS, TYPE B | 24 FT | $165 | $450 |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 60 CY | $50.00 | $150 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET Section 1 - ROADWAY - Totals Awd $349,980.50 2 $367,542.00 | 1 EACH | $225 | $300 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 3,732 SY | $3.00 | $2.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 187 SY | $5.00 | $2.00 |
| 659E15000 INTER-SEEDING | 187 SY | $5.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.5 TON | $790 | $900 |
| 659E31000 LIME | 0.77 ACRE | $30.00 | $50.00 |
| 659E35000 WATER | 21 MGAL | $1.00 | $1.50 |
| 670E00500 SLOPE EROSION PROTECTION | 1,138 SY | $5.00 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,900 | $1,650 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,720 | $6,650 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $9,000 | $15,500 |
| 611E00900 6" CONDUIT, TYPE B | 24 FT | $75.00 | $147 |
| 611E03100 10" CONDUIT, TYPE B | 26 FT | $90.00 | $237 |
| 611E97200 CONDUIT, MISC.:TYPE B FOR DRAINAGE DISCHARGE | 10 EACH | $150 | $207 |
| 611E97200 CONDUIT, MISC.:TYPE C FOR DRAINAGE DISCHARGE | 10 EACH | $125 | $227 |
| 611E97200 CONDUIT, MISC.:TYPE E FOR DRAINAGE DISCHARGE | 10 EACH | $100 | $207 |
| 611E97200 CONDUIT, MISC.:TYPE F FOR DRAINAGE DISCHARGE | 10 EACH | $100 | $207 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 2 EACH | $950 | $1,925 |
| 611E98690 CATCH BASIN, MISC.:YPE 1 CATCH BASIN, AS PER PLAN | 2 EACH | $6,200 | $6,340 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 3 EACH | $525 | $1,125 |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE | 3 EACH | $845 | $2,100 |
| 611E99720 INSPECTION WELL | 1 EACH | $800 | $1,500 |
| 611E99900 DRAINAGE STRUCTURE, MISC.:ARD DRAIN, AS PER PLAN Section 3 - DRAINAGE - Totals Awd $71,080.00 2 $93,288.00 | 2 EACH | $2,500 | $3,500 |
| 407E20000 NON-TRACKING TACK COAT | 60 GAL | $5.00 | $8.00 |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 9 CY | $1,025 | $422 |
| 442E22400 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 13 CY | $885 | $350 |
| 452E10011 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 52 SY | $110 | $112 |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 215 FT | $55.00 | $83.00 |
| 609E98000 CURB, MISC.:CURB REPLACED (IN-KIND), AS PER PLAN Section 4 - PAVEMENT - Totals Awd $282,505.00 2 $274,196.00 | 13 FT | $85.00 | $83.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE Section 5 - WATER WORK - Totals Awd $1,050.00 2 $6,875.00 | 5 EACH | $210 | $1,375 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 173 FT | $14.00 | $20.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 6 EACH | $175 | $263 |
| 630E80100 SIGN, FLAT SHEET | 54 SF | $28.00 | $43.00 |
| 630E80500 SIGN, DOUBLE FACED, STREET NAME | 6 EACH | $125 | $188 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 17 EACH | $25.00 | $38.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $75.00 | $113 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 10 EACH | $25.00 | $38.00 |
| 643E30000 REMOVAL OF PAVEMENT MARKING | 163 FT | $20.00 | $6.00 |
| 644E00300 CENTER LINE | 0.01 MILE | $10,000 | $15,000 |
| 644E00500 STOP LINE | 54 FT | $9.00 | $18.00 |
| 644E00620 CROSSWALK LINE, 12" Section 6 - TRAFFIC CONTROL - Totals Awd $12,600.00 2 $18,313.00 | 424 FT | $5.00 | $15.00 |
| 611E00400 4" CONDUIT, TYPE E | 40 FT | $1.00 | $7.50 |
| 625E25408 CONDUIT, 2", 725.051 | 80 FT | $10.00 | $16.00 |
| 625E25504 CONDUIT, 3", 725.051 | 19 FT | $12.00 | $18.00 |
| 625E25909 CONDUIT, JACKED OR DRILLED, 725.052, AS PER PLAN, | 81 FT | $50.00 | $80.00 |
| 625E29000 TRENCH | 99 FT | $12.00 | $19.00 |
| 625E30700 PULL BOX, 725.08, 18" | 2 EACH | $1,300 | $1,900 |
| 625E32000 GROUND ROD | 6 EACH | $400 | $425 |
| 625E36010 UNDERGROUND WARNING MARKING TAPE | 99 FT | $2.00 | $3.00 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 10 EACH | $830 | $1,300 |
| 632E20751 ACCESSIBLE PEDESTRIAN PUSHBUTTON, AS PER PLAN | 10 EACH | $1,025 | $1,935 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 10 EACH | $20.00 | $24.00 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 1,293 FT | $4.00 | $6.00 |
| 632E64020 PEDESTAL FOUNDATION | 6 EACH | $1,200 | $2,835 |
| 632E65400 LOOP DETECTOR LEAD-IN CABLE, 2 CONDUCTOR, NO. 12 A | 1,277 FT | $3.00 | $4.00 |
| 632E70401 CONDUIT RISER, 2" DIAMETER, AS PER PLAN, TYPE B | 1 EACH | $800 | $695 |
| 632E70601 CONDUIT RISER, 3" DIAMETER, AS PER PLAN, TYPE A | 1 EACH | $1,000 | $2,250 |
| 632E70601 CONDUIT RISER, 3" DIAMETER, AS PER PLAN, TYPE C | 1 EACH | $1,500 | $3,240 |
| 632E89900 PEDESTAL, 8', TRANSFORMER BASE | 5 EACH | $1,300 | $2,043 |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 2 EACH | $2,500 | $9,450 |
| 632E90400 SIGNALIZATION, MISC.:PEDESTRIAN PEDESTAL, REMOVED | 1 EACH | $800 | $1,575 |
| 632E90500 SIGNALIZATION, MISC.:UNLASH AND RELASH MESSENGER W | 311 FT | $9.00 | $11.00 |
| 633E99000 CONTROLLER ITEM, MISC.:REWIRE/REPROGRAM CONTROLLER | 2 EACH | $1,800 | $4,230 |
| 898E10001 WIRELESS MAGNETOMETER DETECTION SYSTEM, AS PER PLA Section 7 - TRAFFIC SIGNALS - Totals Awd $72,856.00 2 $137,332.00 | 2 EACH | $2,200 | $4,590 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $80.00 | $115 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $1,025 | $250 |
| 623E40900 MONUMENT, MISC.:POST CONSTRUCTION MONUMENT VERIFIC | 1 EACH | $2,650 | $15,000 |
| 623E40900 MONUMENT, MISC.:RECONSTRUCTION MONUMENT VERIFICATI | 1 EACH | $2,650 | $15,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →