GRE-Yellow Springs ADA Curb Ramp
GRE County · est $0.1M
Bid dateThursday, June 7—
GRE County · est $0.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 11 more items below.
| Item | Quantity | R1Fillmore Construction | R2Belgray, INC | R3L J Deweese CO INC | R4Axis Civil Construction LLC | R5A & B Asphalt Corporation | % of bid |
|---|---|---|---|---|---|---|---|
| 608E52001 CURB RAMP, AS PER PLAN | 3,983 SF | $13.50 | $14.00 | $21.30 | $16.50 | $22.00 | 40% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $17,500 | $14,139 | $12,500 | $15,000 | $17,227 | 13% |
| 644E00601 CROSSWALK LINE, AS PER PLAN, 24" | 2,376 FT | $6.00 | $5.15 | $5.50 | $8.00 | $5.00 | 10% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 |
| Item | Quantity | R1Fillmore Construction | R2Belgray, INC | R3L J Deweese CO INC | R4Axis Civil Construction LLC | R5A & B Asphalt Corporation |
|---|---|---|---|---|---|---|
| 204E10000 SUBGRADE COMPACTION | 78 SY | $3.00 | $32.00 | $2.25 | $2.00 | $2.25 |
| 608E53020 DETECTABLE WARNING | 16 SF | $40.00 | $24.00 | $48.00 | $50.00 | $75.00 |
| 407E10000 TACK COAT | 6 GAL | $10.00 | $2.50 | $45.00 | $5.00 | $4.18 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 1 EACH | $150 | $90.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 22 CY |
| $300 |
| $450 |
| $275 |
| $400 |
| $200 |
| 5% |
| 202E30000 WALK REMOVED | 2,696 SF | $2.00 | $3.00 | $3.70 | $3.00 | $7.75 | 4% |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 1,695 FT | $3.00 | $2.95 | $3.20 | $10.00 | $5.98 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $5,000 | $4,000 | $6,500 | $15,000 | $2,992 | 4% |
| 202E23011 PAVEMENT REMOVED, ASPHALT, AS PER PLAN | 89 SY | $50.00 | $70.00 | $13.25 | $25.00 | $55.57 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $2,000 | $3,600 | $2,500 | $802 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $1,200 | $1,000 | $5,000 | $4,500 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 7 CY | $400 | $500 | $410 | $425 | $256 | 2% |
| 202E32500 CURB AND GUTTER REMOVED | 384 FT | $6.00 | $27.00 | $23.00 | $12.00 | $25.00 | 2% |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 41 SF | $50.00 | $28.00 | $70.00 | $50.00 | $75.00 | 2% |
| 609E18001 COMBINATION CURB AND GUTTER, TYPE 3, AS PER PLAN | 35 FT | $50.00 | $54.00 | $55.55 | $65.00 | $28.50 | 1% |
| 832E30000 EROSION CONTROL | 1,734 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 608E10000 4" CONCRETE WALK | 152 SF | $10.00 | $12.00 | $14.15 | $8.25 | $15.00 | 1% |
| 304E20000 AGGREGATE BASE | 25 CY | $60.00 | $170 | $82.00 | $200 | $56.71 | 1% |
| 202E32000 CURB REMOVED | 223 FT | $6.00 | $16.00 | $21.20 | $12.00 | $25.00 | 1% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 20 FT | $50.00 | $52.00 | $51.75 | $65.00 | $28.50 | 1% |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 38 FT | $24.50 | $24.50 | $12.00 | $24.50 | $15.50 | 1% |
| $375 |
| $350 |
| $1,230 |
| 630E08600 SIGN POST REFLECTOR | 3 EACH | $75.00 | $75.00 | $45.00 | $75.00 | $10.00 |
| 630E80100 SIGN, FLAT SHEET | 6.3 SF | $30.00 | $30.00 | $25.00 | $30.00 | $26.25 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH | $30.00 | $30.00 | $15.00 | $30.00 | $110 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $90.00 | $90.00 | $65.00 | $90.00 | $110 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $40.00 | $40.00 | $35.00 | $40.00 | $110 |
| 644E00500 STOP LINE | 42 FT | $10.00 | $5.85 | $6.35 | $16.00 | $5.00 |
| 644E00600 CROSSWALK LINE | 116 FT | $5.00 | $3.35 | $3.60 | $8.00 | $7.55 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E52001 CURB RAMP, AS PER PLAN | 3,983 SF | $13.5 | $54k | 39% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $17,500 | $18k | 13% |
| 644E00601 CROSSWALK LINE, AS PER PLAN, 24" | 2,376 FT | $6 | $14k | 10% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 22 CY | $300 | $7k | 5% |
| 202E30000 WALK REMOVED | 2,696 SF | $2 | $5k | 4% |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 1,695 FT | $3 | $5k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $5,000 | $5k | 4% |
| 202E23011 PAVEMENT REMOVED, ASPHALT, AS PER PLAN | 89 SY | $50 | $4k | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $4k | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $4k | 3% |