MEG-Racine Sidewalk Phase 2
MEG County · est $0.2M
Bid dateThursday, August 23—
MEG County · est $0.2M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 8 more items below.
| Item | Quantity | R1D V Weber Construction | R2Shelly & Sands INC | R3Native Construction LLC | R4York Paving CO INC | R5Shelly Company | % of bid |
|---|---|---|---|---|---|---|---|
| 608E12000 5" CONCRETE WALK | 5,723 SF | $11.00 | $7.00 | $9.00 | $9.75 | $8.00 | 24% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 897 FT | $37.85 | $41.00 | $25.00 | $48.00 | $37.75 | 13% |
| 610E13001 CELLULAR RETAINING WALL (CONCRETE), AS PER PLAN | 497 SF | $65.00 | $76.00 | $125 | $130 | $73.50 | 12% |
| 609E23000 COMBINATION CURB AND GUTTER, TYPE 4 |
| Item | Quantity | R1D V Weber Construction | R2Shelly & Sands INC | R3Native Construction LLC | R4York Paving CO INC | R5Shelly Company |
|---|---|---|---|---|---|---|
| 202E23010 PAVEMENT REMOVED, ASPHALT | 48 SY | $15.00 | $24.00 | $25.00 | $16.00 | $39.50 |
| 202E30204 STEPS REMOVED | 1 LS | $1,155 | $1,350 | $2,000 | $750 | $2,500 |
| 203E20000 EMBANKMENT | 29 CY | $15.00 | $13.00 | $39.00 | $24.00 | $66.50 |
| 690E50000 SPECIAL - MAILBOX SUPPORT | 2 EACH | $120 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 693 FT |
| $37.50 |
| $45.00 |
| $25.50 |
| $48.00 |
| $37.75 |
| 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $17,000 | $19,500 | $6,000 | $18,000 | $45,000 | 6% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 243 FT | $58.00 | $57.00 | $33.00 | $63.00 | $47.00 | 5% |
| 203E10000 EXCAVATION | 425 CY | $25.00 | $33.00 | $22.40 | $10.00 | $24.00 | 4% |
| 611E04400 12" CONDUIT, TYPE B | 92 FT | $98.00 | $71.00 | $90.00 | $52.00 | $105 | 3% |
| 625E25504 CONDUIT, 3", 725.051 | 591 FT | $13.50 | $10.50 | $10.00 | $15.00 | $23.50 | 3% |
| 611E98150 CATCH BASIN, NO. 3 | 3 EACH | $2,585 | $2,353 | $1,500 | $2,200 | $3,500 | 3% |
| 202E30000 WALK REMOVED | 3,185 SF | $2.25 | $2.45 | $3.50 | $3.75 | $1.60 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $7,000 | $10,000 | $40,000 | $4,200 | $13,500 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,000 | $2,465 | $7,500 | $5,500 | $6,000 | 2% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,375 | $1,490 | $3,400 | $7,640 | $1,500 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 4 CY | $600 | $615 | $700 | $600 | $825 | 1% |
| 608E52000 CURB RAMP | 156 SF | $15.00 | $49.00 | $25.50 | $22.00 | $26.50 | 1% |
| 608E53020 DETECTABLE WARNING | 74 SF | $30.00 | $28.00 | $35.00 | $52.00 | $32.00 | 1% |
| 202E98000 REMOVAL MISC.: CONCRETE BLOCK RETAINING WALL | 1 LS | $2,145 | $7,000 | $8,500 | $3,500 | $15,000 | 1% |
| 659E10000 SEEDING AND MULCHING | 536 SY | $3.50 | $5.00 | $3.30 | $2.75 | $3.79 | 1% |
| $225 |
| $140 |
| $444 |
| $145 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 92 FT | $10.00 | $38.00 | $45.00 | $10.00 | $22.75 |
| 659E20000 COMMERCIAL FERTILIZER | 0.07 TON | $800 | $865 | $800 | $800 | $691 |
| 659E31000 LIME | 0.11 ACRE | $200 | $195 | $310 | $900 | $155 |
| 659E35000 WATER | 3 MGAL | $1.00 | $1.25 | $3.00 | $1.00 | $1.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E12000 5" CONCRETE WALK | 5,723 SF | $11 | $63k | 24% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 897 FT | $37.85 | $34k | 13% |
| 610E13001 CELLULAR RETAINING WALL (CONCRETE), AS PER PLAN | 497 SF | $65 | $32k | 12% |
| 609E23000 COMBINATION CURB AND GUTTER, TYPE 4 | 693 FT | $37.5 | $26k | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $17,000 | $17k | 6% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 243 FT | $58 | $14k | 5% |
| 203E10000 EXCAVATION | 425 CY | $25 | $11k | 4% |
| 611E04400 12" CONDUIT, TYPE B | 92 FT | $98 | $9k | 3% |
| 625E25504 CONDUIT, 3", 725.051 | 591 FT | $13.5 | $8k | 3% |
| 611E98150 CATCH BASIN, NO. 3 | 3 EACH | $2,585 | $8k | 3% |