MRG-SR 669-10.85
MRG County · est $0.5M
Bid dateThursday, May 17—
MRG County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 21 more items below.
| Item | Quantity | R1George J Igel & CO INC | R2Alan Stone CO INC | R3Ohio-west Virginia Excavating CO | R4Suburban Maintenance & Construction | R5Kokosing Construction Company INC | R6Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W21X101 | 1,640 FT | $77.00 | $66.00 | $87.25 | $64.75 | $85.00 | $70.00 | 29% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 934 FT | $76.00 | $74.00 | $105 | $150 | $142 | $117 | 16% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 749 FT | $90.00 | $76.00 |
| Item | Quantity | R1George J Igel & CO INC | R2Alan Stone CO INC | R3Ohio-west Virginia Excavating CO | R4Suburban Maintenance & Construction | R5Kokosing Construction Company INC | R6Shelly & Sands INC |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,500 | $3,000 | $3,500 | $15,000 | $2,000 | $5,500 |
| 202E38000 GUARDRAIL REMOVED | 370 FT | $1.60 | $3.00 | $5.00 | $2.00 | $4.00 | $1.60 |
| 203E10000 EXCAVATION | 7 CY | $60.00 | $25.00 | $44.00 | $15.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $90.00 |
| $65.00 |
| $110 |
| $90.00 |
| 16% |
| 610E50000 RETAINING WALL, MISC.:RECAST CONCRETE PANEL | 120 EACH | $220 | $198 | $298 | $200 | $195 | $477 | 6% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 70 CY | $270 | $275 | $325 | $400 | $295 | $400 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $40,289 | $45,000 | $30,000 | $36,642 | $17,500 | 3% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 16 CY | $930 | $594 | $350 | $300 | $740 | $525 | 3% |
| 622E41000 PORTABLE BARRIER, 32" | 460 FT | $23.50 | $23.00 | $24.00 | $34.00 | $20.00 | $25.00 | 2% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $10,550 | $7,000 | $1,750 | $8,000 | $1.00 | $50,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $8,000 | $5,500 | $7,500 | $3,800 | $9,300 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $31,000 | $20,325 | $42,000 | $20,000 | $20,000 | 2% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 96 CY | $94.00 | $340 | $104 | $65.00 | $94.00 | $92.00 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $8,500 | $2,144 | $2,000 | $5,000 | $4,600 | $12,000 | 2% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 105 SY | $80.00 | $190 | $99.00 | $150 | $100 | $90.00 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 312.5 FT | $21.20 | $25.00 | $27.00 | $21.20 | $22.38 | $21.20 | 2% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 2 EACH | $2,480 | $2,310 | $3,000 | $2,500 | $3,800 | $2,480 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,475 | $2,500 | $8,000 | $15,000 | $2,200 | $4,090 | 1% |
| 617E10100 COMPACTED AGGREGATE | 19 CY | $190 | $112 | $145 | $150 | $240 | $150 | 1% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 203E20000 EMBANKMENT | 68 CY | $40.00 | $17.00 | $24.00 | $15.00 | $77.00 | $20.00 | 1% |
| $50.00 |
| $50.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 1 EACH | $2,285 | $2,362 | $2,500 | $2,285 | $1,960 | $2,285 |
| 659E10000 SEEDING AND MULCHING | 278 SY | $5.65 | $4.50 | $7.00 | $4.00 | $7.00 | $5.25 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $675 | $2,772 | $1,700 | $500 | $625 | $625 |
| 659E31000 LIME | 0.06 ACRE | $155 | $735 | $3,000 | $500 | $150 | $145 |
| 659E35000 WATER | 1 MGAL | $1.00 | $36.00 | $117 | $1.00 | $1.00 | $1.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $250 | $323 | $250 | $250 | $400 | $275 |
| 407E20000 NON-TRACKING TACK COAT | 142 GAL | $10.50 | $4.50 | $10.00 | $3.00 | $3.45 | $3.00 |
| 621E00100 RPM | 17 EACH | $95.00 | $203 | $105 | $198 | $90.00 | $165 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 17 EACH | $10.00 | $12.00 | $18.00 | $50.00 | $12.00 | $20.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 9 EACH | $7.00 | $9.00 | $8.00 | $7.00 | $7.00 | $7.00 |
| 642E00094 EDGE LINE, 6" | 0.26 MILE | $675 | $3,674 | $4,000 | $3,500 | $7,235 | $3,500 |
| 642E00290 CENTER LINE | 0.13 MILE | $1,200 | $6,823 | $7,500 | $6,500 | $5,550 | $6,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BI-DIRECTIONAL | 10 EACH | $10.50 | $48.00 | $22.00 | $45.00 | $6.50 | $7.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 10 EACH | $18.50 | $48.00 | $27.00 | $45.00 | $17.00 | $10.00 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.2 MILE | $4,400 | $6,403 | $7,200 | $6,100 | $7,250 | $6,100 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 22 FT | $20.00 | $25.00 | $27.00 | $23.50 | $5.45 | $23.50 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 232 FT | $4.50 | $7.50 | $4.00 | $10.00 | $6.00 | $3.00 |
| 518E40012 6" NON-PERFORATED CORRUGATED PLASTIC PIPE | 3 FT | $55.00 | $82.00 | $18.00 | $10.00 | $58.00 | $60.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W21X101 | 1,640 FT | $77 | $126k | 28% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 934 FT | $76 | $71k | 16% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 749 FT | $90 | $67k | 15% |
| 610E50000 RETAINING WALL, MISC.:RECAST CONCRETE PANEL | 120 EACH | $220 | $26k | 6% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 70 CY | $270 | $19k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $15k | 3% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 16 CY | $930 | $15k | 3% |
| 622E41000 PORTABLE BARRIER, 32" | 460 FT | $23.5 | $11k | 2% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $10,550 | $11k | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $10k | 2% |