| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X117 | 1,110 FT | $75.00 | $60.00 | $59.00 | 25% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 549 FT | $103 | $95.00 | $91.00 | 17% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 493 FT | $78.00 | $90.00 | $85.00 | 11% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $34,000 | $21,000 | $40,657 | 10% |
| 610E50000 RETAINING WALL, MISC.:PRECAST CONCRETE PANEL 1 | 128 EACH | $250 | $235 | $211 | 10% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 57 CY | $215 | $470 | $494 | 4% |
| 624E10000 MOBILIZATION | 1 LS |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,000 | $6,500 | $6,000 |
| 202E23000 PAVEMENT REMOVED | 48 SY | $23.00 | $50.00 | $65.00 |
| 202E38000 GUARDRAIL REMOVED | 163 FT | $6.00 | $2.50 | $3.00 |
| 202E38200 GUARDRAIL REMOVED FOR REUSE | 62.5 FT | $13.00 | $3.50 | $4.50 |
| 203E10000 EXCAVATION | 54 CY | $18.00 | $13.50 | $94.00 |
| 203E20000 EMBANKMENT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $10,000 |
| $10,000 |
| $25,516 |
| 3% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 94 CY | $100 | $125 | $134 | 3% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 4 EACH | $2,000 | $1,950 | $2,047 | 2% |
| 622E41000 PORTABLE BARRIER, 32" | 640 FT | $12.50 | $16.00 | $15.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,000 | $3,332 | $2,500 | 2% |
| 611E07200 18" CONDUIT, TYPE A, 706.02 | 47 FT | $120 | $140 | $203 | 2% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 65 SY | $82.00 | $115 | $128 | 2% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 14 CY | $350 | $425 | $579 | 1% |
| 606E15050 GUARDRAIL, TYPE MGS | 162.5 FT | $30.00 | $24.00 | $26.00 | 1% |
| 621E00100 RPM | 13 EACH | $300 | $400 | $420 | 1% |
| 524E95000 DRILLED SHAFTS, MISC.:EXTENSION | 22 FT | $165 | $590 | $69.00 | 1% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 11 CY | $325 | $1,200 | $1,260 | 1% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | 1% |
| 659E10000 SEEDING AND MULCHING | 534 SY | $5.00 | $3.80 | $3.00 | 1% |
| 138 CY |
| $18.83 |
| $20.00 |
| $10.00 |
| 204E10000 SUBGRADE COMPACTION | 91 SY | $8.00 | $5.00 | $2.50 |
| 606E16050 GUARDRAIL REBUILT, TYPE MGS | 62.5 FT | $16.00 | $18.00 | $19.00 |
| 601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE C | 17 CY | $125 | $200 | $225 |
| 659E20000 COMMERCIAL FERTILIZER | 0.07 TON | $200 | $690 | $3,961 |
| 659E31000 LIME | 0.11 ACRE | $350 | $150 | $764 |
| 659E35000 WATER | 2 MGAL | $1.00 | $1.00 | $21.00 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 58 FT | $20.00 | $25.00 | $44.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $1,500 | $1,000 | $416 |
| 602E20000 CONCRETE MASONRY | 0.4 CY | $1,300 | $1,800 | $2,110 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 4 EACH | $250 | $250 | $317 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 21 CY | $125 | $95.00 | $90.00 |
| 304E20000 AGGREGATE BASE, 6" THICK | 8 CY | $175 | $120 | $137 |
| 407E20000 NON-TRACKING TACK COAT | 117 GAL | $7.00 | $4.00 | $4.50 |
| 408E10000 PRIME COAT | 89 GAL | $8.00 | $3.00 | $16.00 |
| 617E10100 COMPACTED AGGREGATE | 15 CY | $150 | $120 | $114 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 13 EACH | $20.00 | $15.00 | $11.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 5 EACH | $15.00 | $7.50 | $8.00 |
| 630E08600 SIGN POST REFLECTOR | 2 EACH | $75.00 | $42.00 | $45.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $60.00 | $50.00 | $103 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 2 EACH | $60.00 | $150 | $208 |
| 642E00094 EDGE LINE, 6" | 0.19 MILE | $4,200 | $4,000 | $4,199 |
| 642E00290 CENTER LINE | 0.09 MILE | $8,300 | $8,000 | $8,397 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $2,500 | $17,100 | $7,000 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 14 EACH | $50.00 | $8.00 | $53.00 |
| 614E13360 OBJECT MARKER, TWO WAY, BI-DIRECTIONAL | 12 EACH | $23.00 | $15.00 | $53.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,300 | $8,900 | $8,236 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 201 FT | $8.00 | $4.00 | $9.00 |
| 518E40012 6" NON-PERFORATED CORRUGATED PLASTIC PIPE | 40 FT | $8.00 | $30.00 | $59.00 |
| 610E50000 RETAINING WALL, MISC.:PRECAST CONCRETE PANEL 2 | 3 EACH | $650 | $425 | $276 |
| 610E50000 RETAINING WALL, MISC.:PRECAST CONCRETE PANEL 3 | 1 EACH | $1,500 | $1,772 | $2,273 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,000 | $6,500 | $4,724 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X117 | 1,110 FT | $75 | $83k | 22% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 549 FT | $103 | $57k | 15% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 493 FT | $78 | $38k | 10% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $34,000 | $34k | 9% |
| 610E50000 RETAINING WALL, MISC.:PRECAST CONCRETE PANEL 1 | 128 EACH | $250 | $32k | 9% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 57 CY | $215 | $12k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 94 CY | $100 | $9k | 3% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 4 EACH | $2,000 | $8k | 2% |
| 622E41000 PORTABLE BARRIER, 32" | 640 FT | $12.5 | $8k | 2% |