MOE-SR 26-22.01
MOE County · est $1.1M
Bid dateThursday, November 8—
MOE County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 43 more items below.
| Item | Quantity | R1Alan Stone CO INC | R2Ohio-west Virginia Excavating CO | R3Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X229 | 1,796 FT | $125 | $160 | $129 | 26% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,770 FT | $61.00 | $88.00 | $97.00 | 12% |
| 524E94805 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK, AS PER | 617 FT | $124 | $125 | $175 | 9% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE PANEL NO.1 | 287 EACH | $231 | $300 | $315 | 8% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 879 FT | $74.00 | $96.00 | $156 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $51,000 | $40,000 | $40,000 | 6% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS |
| Item | Quantity | R1Alan Stone CO INC | R2Ohio-west Virginia Excavating CO | R3Shelly & Sands INC |
|---|---|---|---|---|
| 202E23010 PAVEMENT REMOVED, ASPHALT | 408 SY | $10.00 | $15.00 | $15.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 71 FT | $36.00 | $25.00 | $12.00 |
| 202E38200 GUARDRAIL REMOVED FOR REUSE | 587.5 FT | $6.00 | $5.00 | $3.50 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 16 FT | $159 | $35.00 | $35.00 |
| 203E10000 EXCAVATION | 135 CY | $22.00 | $25.00 | $18.00 |
| 203E20000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $40,000 |
| $43,400 |
| $39,880 |
| 5% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 390 CY | $79.00 | $100 | $115 | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 106 CY | $266 | $200 | $253 | 3% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 395 CY | $70.00 | $90.00 | $80.00 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 87 CY | $286 | $200 | $272 | 3% |
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X131 | 295 FT | $70.00 | $90.00 | $71.00 | 2% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 35 CY | $550 | $600 | $350 | 2% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 536 FT | $34.00 | $15.00 | $9.00 | 2% |
| 202E98100 REMOVAL MISC.: EXISTING PILES | 44 EACH | $398 | $75.00 | $225 | 2% |
| 524E94803 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK, AS PE | 169 FT | $94.00 | $110 | $180 | 2% |
| 622E41000 PORTABLE BARRIER, 32" | 590 FT | $18.00 | $15.00 | $25.00 | 1% |
| 204E13000 EXCAVATION OF SUBGRADE | 395 CY | $26.00 | $22.00 | $30.00 | 1% |
| 304E20000 AGGREGATE BASE | 110 CY | $93.00 | $100 | $80.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $7,500 | $37,570 | 1% |
| 583 CY |
| $12.00 |
| $40.00 |
| $13.00 |
| 204E10000 SUBGRADE COMPACTION | 640 SY | $2.50 | $2.50 | $3.50 |
| 204E45000 PROOF ROLLING | 1 HOUR | $170 | $145 | $200 |
| 204E50000 GEOTEXTILE FABRIC | 400 SY | $2.00 | $2.00 | $1.00 |
| 606E16550 GUARDRAIL REBUILT, TYPE 5, USING 9 FOOT POSTS | 587.5 FT | $17.00 | $14.00 | $15.50 |
| 601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE C | 7 CY | $471 | $105 | $325 |
| 659E10000 SEEDING AND MULCHING | 759 SY | $3.00 | $4.00 | $2.70 |
| 659E20000 COMMERCIAL FERTILIZER | 0.1 TON | $2,772 | $600 | $685 |
| 659E31000 LIME | 0.16 ACRE | $735 | $350 | $150 |
| 659E35000 WATER | 4 MGAL | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 8,000 EACH | $1.00 | $1.00 | $1.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $200 | $2,500 | $850 |
| 511E52100 CLASS QC FS CONCRETE | 26 CY | $175 | $300 | $160 |
| 602E20000 CONCRETE MASONRY | 1 CY | $1,967 | $1,000 | $1,800 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 102 FT | $11.00 | $25.00 | $25.00 |
| 611E10200 24" CONDUIT, TYPE A | 45 FT | $161 | $100 | $110 |
| 611E13200 30" CONDUIT, TYPE A | 49 FT | $162 | $125 | $135 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 6 EACH | $312 | $200 | $300 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 46 CY | $93.00 | $150 | $90.00 |
| 407E20000 NON-TRACKING TACK COAT | 226 GAL | $3.50 | $7.00 | $3.00 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (27 CY | $273 | $250 | $260 |
| 621E00100 RPM | 26 EACH | $130 | $150 | $200 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 26 EACH | $11.00 | $10.00 | $7.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 BI-DIRECTIONAL | 25 EACH | $9.00 | $12.00 | $8.50 |
| 642E00094 EDGE LINE, 6" | 0.36 MILE | $2,600 | $4,000 | $2,500 |
| 642E00290 CENTER LINE | 0.18 MILE | $4,600 | $7,500 | $4,500 |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 2 EACH | $2,300 | $2,500 | $2,250 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $5,000 | $3,000 | $29,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 13 EACH | $53.00 | $40.00 | $9.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 13 EACH | $53.00 | $15.00 | $14.00 |
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W30X124, AS PER | 1,029 FT | $5.00 | $10.00 | $5.00 |
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W30X132, AS PER | 64 FT | $10.00 | $20.00 | $12.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 536 FT | $8.50 | $9.85 | $5.00 |
| 524E95000 DRILLED SHAFTS, MISC.: EXTENSION | 98 FT | $65.00 | $175 | $190 |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE PANEL NO.2 | 1 EACH | $1,559 | $1,000 | $1,200 |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE PANEL NO.3 | 1 EACH | $1,559 | $1,100 | $1,200 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,500 | $14,800 | $8,750 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,000 | $2,000 | $7,293 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X229 | 1,796 FT | $125 | $225k | 22% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,770 FT | $61 | $108k | 11% |
| 524E94805 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK, AS PER | 617 FT | $124 | $77k | 8% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE PANEL NO.1 | 287 EACH | $231 | $66k | 7% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 879 FT | $74 | $65k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $51,000 | $51k | 5% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $40,000 | $40k | 4% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 390 CY | $79 | $31k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 106 CY | $266 | $28k | 3% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 395 CY | $70 | $28k | 3% |