GEA-Maple Highlands Trail II
GEA County · est $1.6M
Bid dateThursday, February 27—
GEA County · est $1.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 91 more items below.
| Item | Quantity | R1S E T INC | R2Lockhart Concrete CO | R3Eclipse CO LLC | R4Karvo Companies INC | R5Perk Company INC | % of bid |
|---|---|---|---|---|---|---|---|
| 624E10001 MOBILIZATION, AS PER PLAN | 1 LS | $134,466 | $30,000 | $62,913 | $148,000 | $40,000 | 12% |
| 203E10001 EXCAVATION, AS PER PLAN | 5,654 CY | $21.00 | $30.00 | $20.00 | $13.75 | $29.50 | 11% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 1,509 CY | $75.00 | $50.00 | $71.75 | $77.00 | $66.00 | 10% |
| 690E98200 SPECIAL - TRAIL NODE PAVEMENT | 5,381 SF |
| Item | Quantity | R1S E T INC | R2Lockhart Concrete CO | R3Eclipse CO LLC | R4Karvo Companies INC | R5Perk Company INC |
|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $16,500 | $49,000 | $41,141 | $35,400 | $20,800 |
| 202E98000 REMOVAL MISC.:SITE DEMOLITION | 1 LS | $3,200 | $49,000 | $52,000 | $25,000 | $31,570 |
| 202E98100 REMOVAL MISC.:EXISTING UTILITY POLE AND LIGHT FIXT | 2 EACH | $900 | $6,500 | $6,760 | $1,500 | $1,500 |
| 202E98200 REMOVAL MISC.:RELOCATE LITTLE FREE LIBRARY | 1 FT | $500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $17.00 |
| $18.00 |
| $26.00 |
| $36.00 |
| $33.65 |
| 8% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 345 CY | $260 | $270 | $198 | $246 | $235 | 8% |
| 690E98100 SPECIAL - SANDSTONE SEATWALL | 112 FT | $740 | $580 | $690 | $675 | $581 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 363 CY | $193 | $200 | $151 | $183 | $160 | 6% |
| AB3 611E04400 12" CONDUIT, TYPE B, RCP (ALTERNATE 3) | 333 FT | $135 | $60.00 | $86.00 | $89.00 | $95.00 | 4% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (219 CY | $195 | $250 | $172 | $185 | $165 | 4% |
| 832E30000 EROSION CONTROL | 41,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 638E98600 WATER WORK, MISC.:4" HDPE WATER LINE | 485 FT | $80.00 | $45.00 | $72.00 | $86.00 | $44.90 | 3% |
| 690E98000 SPECIAL - TWO SIDED PITCHED ROOF KIOSK | 2 EACH | $18,500 | $2,750 | $15,620 | $9,300 | $8,950 | 3% |
| AB3 611E00900 6" CONDUIT, TYPE B, PVC, SDR 35 (ALTERNATE 3) | 344 FT | $105 | $20.00 | $62.00 | $117 | $190 | 3% |
| 690E98000 SPECIAL - FLUSH RESTROOM | 1 EACH | $28,500 | $100,000 | $134,698 | $132,000 | $115,000 | 3% |
| 690E98200 SPECIAL - BIORETENTION CELL | 3,268 SF | $8.00 | $8.80 | $16.50 | $20.70 | $21.00 | 2% |
| 607E98000 FENCE, MISC.:TIMBER RAIL (44") | 474 FT | $54.00 | $20.00 | $68.75 | $64.50 | $61.50 | 2% |
| AA1 204E30041 GRANULAR MATERIAL, TYPE E, AS PER PLAN (ALTERNATE | 381 CY | $65.00 | $40.00 | $68.75 | $62.00 | $68.00 | 2% |
| 652E10000 PLACING STOCKPILED TOPSOIL | 1,710 CY | $14.00 | $5.00 | $11.25 | $10.50 | $16.25 | 2% |
| 690E98700 SPECIAL - PLANTING SOIL MIX | 449 CY | $48.00 | $48.00 | $88.50 | $45.63 | $45.63 | 2% |
| 203E20001 EMBANKMENT, AS PER PLAN | 2,654 CY | $8.00 | $20.00 | $15.50 | $8.50 | $22.50 | 2% |
| $1,500 |
| $3,265 |
| $600 |
| $1,200 |
| 204E10000 SUBGRADE COMPACTION | 9,004 SY | $2.00 | $30.00 | $1.25 | $0.80 | $2.75 |
| 204E45001 PROOF ROLLING, AS PER PLAN | 2 HOUR | $280 | $100 | $211 | $200 | $175 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 790 FT | $3.50 | $2.00 | $1.50 | $2.00 | $3.00 |
| 625E10500 LIGHT POLE, MISC.:ARBY'S LIGHT POLE MODIFICATION | 1 EACH | $3,200 | $2,800 | $3,053 | $1,500 | $1,500 |
| 625E10500 LIGHT POLE, MISC.:ARBY'S LIGHT POLE RELOCATION | 2 EACH | $4,800 | $3,400 | $5,887 | $4,200 | $4,200 |
| 625E98200 LIGHTING, MISC.:POWER SERVICE | 1 LS | $13,500 | $8,500 | $16,796 | $2,800 | $2,800 |
| 690E98000 SPECIAL - ARBY'S LIT SIGN RELOCATION | 1 EACH | $3,100 | $3,600 | $3,016 | $5,600 | $5,600 |
| 690E98000 SPECIAL - BIKE RACK | 3 EACH | $600 | $1,500 | $527 | $630 | $1,200 |
| 690E98000 SPECIAL - DRINKING FOUNTAIN | 1 EACH | $6,200 | $3,850 | $7,027 | $7,400 | $7,800 |
| 690E98000 SPECIAL - MILLSTONE SIGN | 1 EACH | $3,200 | $7,500 | $13,286 | $22,500 | $11,062 |
| 690E98000 SPECIAL - REINSTALLATION OF SALVAGED DRINKING FOUN | 1 EACH | $2,500 | $2,600 | $3,408 | $12,300 | $1,750 |
| 690E98000 SPECIAL - STEEL BOLLARD | 4 EACH | $920 | $500 | $214 | $820 | $850 |
| 690E98000 SPECIAL - TRASH RECEPTACLE | 2 EACH | $3,200 | $900 | $1,923 | $2,450 | $4,136 |
| 690E98000 SPECIAL - WHEELSTOP | 10 EACH | $160 | $100 | $176 | $138 | $175 |
| 690E98400 SPECIAL - ARBY'S DUMPSTER PAD | 1 LS | $5,000 | $5,000 | $9,072 | $8,600 | $7,400 |
| 690E98400 SPECIAL - ARBY'S SHED RELOCATION | 1 LS | $600 | $3,500 | $1,649 | $2,500 | $1,500 |
| 690E98400 SPECIAL - REPURPOSED BOULDER RETAINING WALL | 1 LS | $5,500 | $2,500 | $5,619 | $16,200 | $8,060 |
| 690E98400 SPECIAL - REPURPOSED BOULDERS LOCATED ON SITE | 1 LS | $4,000 | $4,500 | $3,846 | $7,400 | $4,100 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 12 CY | $135 | $100 | $141 | $285 | $685 |
| 616E10000 WATER | 20 MGAL | $2.00 | $50.00 | $24.25 | $50.00 | $10.00 |
| 651E10000 TOPSOIL STOCKPILED | 1,710 CY | $8.00 | $5.00 | $8.25 | $10.50 | $17.00 |
| 659E00501 SEEDING AND MULCHING, CLASS 1, AS PER PLAN | 2,814 SY | $2.50 | $2.00 | $3.00 | $1.89 | $9.75 |
| 832E15001 STORM WATER POLLUTION PREVENTION PLAN, AS PER PLAN | 1 LS | $1,800 | $1,600 | $1,872 | $1,250 | $1,600 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,500 | $1,320 | $5,991 | $3,960 | $2,160 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $15,500 | $1,500 | $5,720 | $8,281 | $660 |
| 202E58001 MANHOLE REMOVED, AS PER PLAN | 1 EACH | $1,100 | $500 | $852 | $650 | $725 |
| 602E20000 CONCRETE MASONRY | 2 CY | $2,100 | $2,500 | $1,491 | $2,300 | $3,130 |
| 605E05201 4" UNCLASSIFIED PIPE UNDERDRAINS, AS PER PLAN | 1,113 FT | $12.00 | $12.00 | $9.50 | $20.00 | $16.00 |
| 611E98470 CATCH BASIN, NO. 2-2B | 8 EACH | $1,500 | $1,200 | $1,639 | $1,500 | $2,930 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $2,100 | $1,200 | $1,728 | $1,600 | $4,500 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 4 EACH | $300 | $750 | $346 | $750 | $1,200 |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 1 EACH | $400 | $750 | $871 | $1,000 | $1,750 |
| 611E98690 CATCH BASIN, MISC.:CATCH BASIN REMOVED AND REINSTA | 3 EACH | $1,600 | $1,500 | $1,707 | $2,500 | $3,050 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $1,800 | $2,000 | $3,206 | $5,000 | $5,500 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 11 EACH | $950 | $400 | $346 | $580 | $1,200 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 1 EACH | $1,400 | $400 | $456 | $1,100 | $1,750 |
| 611E99900 DRAINAGE STRUCTURE, MISC.:YARD DRAIN WITH INTERLOC | 3 EACH | $2,200 | $500 | $1,633 | $875 | $2,050 |
| 407E20000 NON-TRACKING TACK COAT | 510 GAL | $3.35 | $3.00 | $2.00 | $3.20 | $3.00 |
| 451E10011 6" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, AS P | 21 SY | $159 | $70.00 | $107 | $165 | $119 |
| 452E10011 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 36 SY | $101 | $100 | $91.75 | $81.00 | $125 |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 1,790 SF | $9.00 | $6.00 | $7.50 | $8.50 | $11.50 |
| 608E52000 CURB RAMP | 86 SF | $28.00 | $12.00 | $29.50 | $44.30 | $115 |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 96 SF | $63.00 | $30.00 | $25.75 | $94.00 | $115 |
| 608E98000 WALKWAY, MISC.:DECORATIVE CONCRETE WALK | 445 SF | $12.00 | $15.00 | $13.75 | $14.00 | $12.50 |
| 609E26000 CURB, TYPE 6 | 1,170 FT | $18.00 | $30.00 | $24.00 | $33.00 | $29.75 |
| 690E98400 SPECIAL - EXISTING PARKING LOT RECONFIGURATION | 1 LS | $2,800 | $3,000 | $14,799 | $9,700 | $4,500 |
| AA1 204E13000 EXCAVATION OF SUBGRADE (ALTERNATE 1) | 381 CY | $18.00 | $25.00 | $22.75 | $40.00 | $35.00 |
| 638E04901 1" COPPER SERVICE BRANCH, AS PER PLAN | 49 FT | $60.00 | $35.00 | $55.50 | $133 | $240 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 222 FT | $15.00 | $10.00 | $16.00 | $12.50 | $14.00 |
| 630E80100 SIGN, FLAT SHEET | 216 SF | $19.00 | $15.00 | $24.00 | $18.75 | $18.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $79.00 | $75.00 | $95.75 | $75.00 | $75.00 |
| 630E85200 REMOVAL OF GROUND MOUNTED SIGN AND DELIVERY | 2 EACH | $42.00 | $45.00 | $51.25 | $40.00 | $40.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $42.00 | $35.00 | $25.50 | $20.00 | $40.00 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 3 EACH | $159 | $65.00 | $122 | $95.00 | $150 |
| 630E97700 SIGNING, MISC.:ACCESSIBLE PARKING SIGNAGE | 2 EACH | $528 | $125 | $818 | $640 | $500 |
| 642E01190 PARKING LOT STALL MARKING | 786 FT | $2.00 | $1.25 | $4.75 | $0.35 | $2.00 |
| 642E01700 HANDICAP SYMBOL MARKING | 2 EACH | $150 | $150 | $156 | $25.00 | $140 |
| 644E00601 CROSSWALK LINE, AS PER PLAN | 110 FT | $26.00 | $5.00 | $51.50 | $36.00 | $25.00 |
| 644E01410 WORD ON PAVEMENT, 96" | 2 EACH | $210 | $300 | $260 | $250 | $200 |
| 644E20800 YIELD LINE | 28 FT | $8.00 | $10.00 | $15.50 | $11.00 | $8.00 |
| 690E98000 SPECIAL - RECTANGULAR RAPID FLASHING BEACON | 1 EACH | $8,800 | $2,200 | $13,000 | $4,500 | $15,750 |
| 690E98400 SPECIAL - PARKING LOT EXPANSION PAVEMENT MARKINGS | 1 LS | $1,300 | $3.00 | $3,729 | $2,250 | $1,200 |
| 661E00501 MULCH, AS PER PLAN | 86 CY | $45.00 | $62.00 | $130 | $42.44 | $42.44 |
| 661E14000 PERENNIALS, Calamagrostis x acutifolia 'Karl Foers | 131 EACH | $12.00 | $22.00 | $24.75 | $17.10 | $17.10 |
| 661E14000 PERENNIALS, Hemerocallis 'Gentle Shepherd', Clump, | 79 EACH | $14.00 | $23.00 | $24.75 | $15.68 | $15.68 |
| 661E14000 PERENNIALS, Hemerocallis 'Happy Returns Daylily, C | 795 EACH | $13.00 | $20.00 | $19.50 | $15.68 | $15.68 |
| 661E14000 PERENNIALS, Liatris spicata 'Blazing Star', Clump, | 52 EACH | $13.00 | $23.00 | $24.75 | $15.68 | $15.68 |
| 661E14000 PERENNIALS, Sporobolus heterolepsis, Clump, #2 CON | 1,056 EACH | $15.00 | $24.00 | $33.75 | $15.68 | $15.68 |
| 661E20000 DECIDUOUS SHRUB, 15" HEIGHT, Spiraea japonica 'Tra | 89 EACH | $53.00 | $56.00 | $75.50 | $74.85 | $74.85 |
| 661E20020 DECIDUOUS SHRUB, 18" HEIGHT, Hydrangea quercifolia | 39 EACH | $43.00 | $48.00 | $78.00 | $14.76 | $14.76 |
| 661E20020 DECIDUOUS SHRUB, 18" HEIGHT, Itea virginica 'Virgi | 27 EACH | $39.00 | $45.00 | $70.25 | $40.90 | $40.90 |
| 661E30020 EVERGREEN SHRUB, 15" HEIGHT, Juniperus chinensis ' | 120 EACH | $37.00 | $43.00 | $69.00 | $65.81 | $65.81 |
| 661E30120 EVERGREEN SHRUB, 6' HEIGHT, Thuja plicata 'Viresce | 34 EACH | $196 | $277 | $286 | $374 | $374 |
| 661E40080 DECIDUOUS TREE, 2" CALIPER, Acer rubrum 'Red Maple | 9 EACH | $450 | $382 | $505 | $299 | $299 |
| 661E40080 DECIDUOUS TREE, 2" CALIPER, Pyrus calleryana 'Reds | 12 EACH | $400 | $345 | $403 | $257 | $257 |
| 661E40080 DECIDUOUS TREE, 2" CALIPER, Ulmus americana 'Valle | 6 EACH | $445 | $402 | $507 | $374 | $374 |
| 661E99900 PLANTING, MISC.:, Narcissus 'Dutch Master', BULB; | 2,856 EACH | $2.00 | $2.40 | $7.00 | $1.16 | $1.16 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $14,500 | $39,000 | $37,912 | $10,000 | $23,150 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,000 | $59,000 | $48,200 | $34,000 | $11,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $17,500 | $49,000 | $36,790 | $16,900 | $11,500 |
| 619E16000 FIELD OFFICE, TYPE A | 8 MNTH | $900 | $500 | $950 | $2,000 | $2,500 |
| AB3 611E01200 6" CONDUIT, TYPE D, HDPE (ALTERNATE 3) | 34 FT | $21.00 | $20.00 | $50.50 | $16.50 | $64.00 |
| AB3 611E01401 6" CONDUIT, TYPE E, AS PER PLAN, PERFORATED PVC (A | 143 FT | $18.00 | $20.00 | $18.25 | $26.50 | $55.00 |
| AB3 611E04400 12" CONDUIT, TYPE B, HDPE (ALTERNATE 3) | 129 FT | $120 | $50.00 | $80.75 | $89.00 | $85.50 |
| AB3 611E04600 12" CONDUIT, TYPE C, HDPE (ALTERNATE 3) | 122 FT | $90.00 | $55.00 | $70.00 | $53.40 | $74.00 |
| AB3 611E04900 12" CONDUIT, TYPE D, RCP ALTERNATE 3) | 153 FT | $115 | $60.00 | $74.25 | $93.00 | $81.00 |
| AB3 611E07900 18" CONDUIT, TYPE D, RCP (ALTERNATE 3) | 64 FT | $121 | $70.00 | $82.25 | $117 | $110 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 624E10001 MOBILIZATION, AS PER PLAN | 1 LS | $134,466 | $134k | 8% |
| 203E10001 EXCAVATION, AS PER PLAN | 5,654 CY | $21 | $119k | 7% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 1,509 CY | $75 | $113k | 7% |
| 690E98200 SPECIAL - TRAIL NODE PAVEMENT | 5,381 SF | $17 | $91k | 6% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 345 CY | $260 | $90k | 6% |
| 690E98100 SPECIAL - SANDSTONE SEATWALL | 112 FT | $740 | $83k | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 363 CY | $193 | $70k | 4% |
| AB3 611E04400 12" CONDUIT, TYPE B, RCP (ALTERNATE 3) | 333 FT | $135 | $45k | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (219 CY | $195 | $43k | 3% |
| 832E30000 EROSION CONTROL | 41,000 EACH | $1 | $41k | 3% |