MOT-Arlington/Upr Lewisbrg-Salem
MOT County · est $0.1M
Bid dateThursday, April 9—
MOT County · est $0.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 41 more items below.
| Item | Quantity | R1Brumbaugh Construction INC | R2Complete General Construction Company | R3Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 96 CY | $300 | $300 | $318 | 20% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $21,732 | $24,000 | $59,169 | 15% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $10,000 | $15,000 | 14% |
| 608E52001 CURB RAMP, AS PER PLAN | 558 SF | $28.00 | $21.00 | $20.00 | 11% |
| 202E23500 WEARING COURSE REMOVED, 1-1/2" | 2,293 SY | $5.75 | $4.50 |
| Item | Quantity | R1Brumbaugh Construction INC | R2Complete General Construction Company | R3Eclipse CO LLC |
|---|---|---|---|---|
| 202E23011 PAVEMENT REMOVED, ASPHALT, AS PER PLAN | 6 SY | $100 | $145 | $46.50 |
| 202E32501 CURB AND GUTTER REMOVED, AS PER PLAN | 98 FT | $10.00 | $15.00 | $17.00 |
| 204E10000 SUBGRADE COMPACTION | 22 SY | $14.00 | $5.00 | $7.50 |
| 608E10000 4" CONCRETE WALK | 45 SF | $20.00 | $14.00 | $16.00 |
| 659E00300 TOPSOIL | 7 CY | $50.00 | $92.00 | $102 |
| 659E10000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $5.00 |
| 9% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 8 EACH | $1,204 | $2,100 | $1,276 | 7% |
| 632E64020 PEDESTAL FOUNDATION | 4 EACH | $1,129 | $1,800 | $1,197 | 3% |
| 202E30801 TRAFFIC ISLAND REMOVED, AS PER PLAN | 15 SY | $250 | $42.00 | $145 | 3% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 37 FT | $100 | $82.00 | $71.50 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $10,000 | $12,000 | 2% |
| 254E01601 PATCHING PLANED SURFACE, AS PER PLAN | 115 SY | $25.00 | $15.00 | $16.00 | 2% |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: REMO | 5 EACH | $507 | $595 | $538 | 2% |
| 202E30000 WALK REMOVED | 359 SF | $6.00 | $6.00 | $4.50 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,000 | $1,020 | $6,500 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 197 GAL | $10.00 | $5.00 | $5.50 | 1% |
| 632E89900 PEDESTAL, 8', TRANSFORMER BASE | 3 EACH | $656 | $800 | $696 | 1% |
| 644E00600 CROSSWALK LINE | 537 FT | $3.50 | $3.50 | $3.00 | 1% |
| 621E00100 RPM | 3 EACH | $626 | $626 | $984 | 1% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 46 SY | $40.00 | $137 | $145 | 1% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 5 CY | $300 | $500 | $530 | 1% |
| 60 SY |
| $15.00 |
| $23.39 |
| $12.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.01 TON | $600 | $500 | $530 |
| 659E31000 LIME | 0.02 ACRE | $50.00 | $200 | $10.50 |
| 659E35000 WATER | 1 MGAL | $5.00 | $1.00 | $10.50 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 4 EACH | $250 | $680 | $819 |
| 304E20000 AGGREGATE BASE | 4 CY | $150 | $145 | $220 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 3 EACH | $250 | $245 | $382 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $250 | $665 | $819 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $50.00 | $28.00 | $18.50 |
| 644E00100 EDGE LINE, 4" | 0.01 MILE | $10,000 | $10,000 | $32,007 |
| 644E00300 CENTER LINE | 0.04 MILE | $13,000 | $13,000 | $33,661 |
| 644E00400 CHANNELIZING LINE, 8" | 127 FT | $2.00 | $2.00 | $1.00 |
| 644E00500 STOP LINE | 126 FT | $8.19 | $8.19 | $5.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 14 FT | $9.00 | $9.00 | $5.00 |
| 644E01300 LANE ARROW | 2 EACH | $145 | $145 | $159 |
| 625E25402 CONDUIT, 2", 725.05 | 84 FT | $7.90 | $25.00 | $8.50 |
| 625E29002 TRENCH, 24" DEEP | 84 FT | $12.40 | $24.00 | $13.00 |
| 625E31600 PULL BOX, MISC.: MODIFY EXISTING PULL BOX | 3 EACH | $104 | $475 | $110 |
| 625E32000 GROUND ROD | 4 EACH | $231 | $250 | $245 |
| 625E36000 PLASTIC CAUTION TAPE | 84 FT | $0.20 | $1.75 | $0.25 |
| 632E27200 LOOP DETECTOR TIE IN | 8 EACH | $127 | $165 | $135 |
| 632E40300 SIGNAL CABLE, 3 CONDUCTOR, NO. 14 AWG | 540 FT | $2.05 | $3.00 | $2.00 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 595 FT | $2.25 | $3.00 | $2.50 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: REMO | 1 EACH | $415 | $540 | $440 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: REMO | 5 EACH | $176 | $375 | $187 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: PEDESTAL POLE AND B | 1 EACH | $311 | $410 | $330 |
| 633E99000 CONTROLLER ITEM, MISC.: MODIFY EXISTING CONTROLLER | 1 EACH | $1,359 | $1,850 | $1,441 |
| 304E20000 AGGREGATE BASE | 10 CY | $65.00 | $145 | $153 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.04 MILE | $34,388 | $34,388 | $12,328 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.04 MILE | $34,388 | $34,388 | $11,772 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 127 FT | $1.00 | $1.00 | $0.50 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 127 FT | $0.90 | $0.90 | $0.50 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 126 FT | $2.50 | $2.50 | $2.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 126 FT | $2.50 | $2.50 | $2.50 |
| 614E27200 WORK ZONE CROSSWALK LINE, CLASS I, 642 PAINT | 537 FT | $1.50 | $1.50 | $2.00 |
| 614E27620 WORK ZONE CROSSWALK LINE, CLASS III, 642 PAINT | 537 FT | $1.50 | $1.50 | $2.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 96 CY | $300 | $29k | 17% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $21,732 | $22k | 13% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 12% |
| 608E52001 CURB RAMP, AS PER PLAN | 558 SF | $28 | $16k | 9% |
| 202E23500 WEARING COURSE REMOVED, 1-1/2" | 2,293 SY | $5.75 | $13k | 8% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 8 EACH | $1,204 | $10k | 6% |
| 632E64020 PEDESTAL FOUNDATION | 4 EACH | $1,129 | $5k | 3% |
| 202E30801 TRAFFIC ISLAND REMOVED, AS PER PLAN | 15 SY | $250 | $4k | 2% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 37 FT | $100 | $4k | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $4k | 2% |