BRO-SR 32-11.93 Turn Lane
BRO County · est $0.8M
Bid dateThursday, June 4—
BRO County · est $0.8M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 53 more items below.
| Item | Quantity | R1Rack & Ballauer Excavating CO INC | R2Shelly Company | R3Eclipse CO LLC | R4John R Jurgensen Company | R5Fillmore Construction | % of bid |
|---|---|---|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 806 CY | $140 | $140 | $141 | $159 | $180 | 21% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 189 CY | $215 | $189 | $202 | $227 | $220 | 7% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 1,673 CY | $24.00 | $32.75 | $33.00 | $43.45 | $40.00 | 7% |
| 441E50300 |
| Item | Quantity | R1Rack & Ballauer Excavating CO INC | R2Shelly Company | R3Eclipse CO LLC | R4John R Jurgensen Company | R5Fillmore Construction |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,000 | $5,500 | $3,500 | $1,175 | $3,500 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 52 FT | $17.00 | $35.00 | $11.00 | $60.30 | $30.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 12 FT | $28.00 | $113 | $11.00 | $147 | $100 |
| 202E58000 MANHOLE REMOVED | 1 EACH | $1,200 | $1,200 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 448 (233 CY |
| $165 |
| $149 |
| $157 |
| $160 |
| $200 |
| 7% |
| 304E20000 AGGREGATE BASE | 819 CY | $45.00 | $41.50 | $46.50 | $58.99 | $50.00 | 7% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,021 FT | $16.50 | $20.00 | $17.00 | $16.50 | $17.50 | 6% |
| 832E30000 EROSION CONTROL | 27,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 5% |
| 659E00300 TOPSOIL | 567 CY | $46.00 | $32.25 | $40.00 | $51.08 | $20.00 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $24,000 | $19,000 | $30,000 | $20,000 | $13,350 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $19,500 | $41,899 | $27,610 | $35,000 | 4% |
| 204E13000 EXCAVATION OF SUBGRADE | 1,673 CY | $11.00 | $13.75 | $18.50 | $24.29 | $20.00 | 3% |
| 605E11110 6" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 1,786 FT | $10.00 | $13.00 | $12.00 | $14.45 | $14.00 | 3% |
| 614E23410 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 740.06, | 5,074 FT | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 | 3% |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 2.18 MILE | $8,030 | $8,030 | $8,271 | $8,030 | $8,100 | 3% |
| 203E10000 EXCAVATION | 731 CY | $22.00 | $20.25 | $18.50 | $24.18 | $20.00 | 3% |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 2,283 SY | $6.00 | $9.15 | $12.50 | $11.13 | $22.00 | 3% |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 1,499 FT | $8.50 | $12.00 | $10.00 | $10.86 | $10.00 | 2% |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 4,786 FT | $2.50 | $1.15 | $1.50 | $1.15 | $1.50 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $9,500 | $13,500 | $8,958 | $6,500 | 2% |
| 204E10000 SUBGRADE COMPACTION | 5,019 SY | $1.80 | $1.10 | $1.25 | $2.31 | $3.00 | 2% |
| $444 |
| $1,082 |
| $500 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $600 | $1,200 | $444 | $594 | $250 |
| 203E20000 EMBANKMENT | 185 CY | $19.00 | $19.25 | $35.00 | $15.00 | $40.00 |
| 204E45000 PROOF ROLLING | 3 HOUR | $175 | $180 | $190 | $192 | $100 |
| 204E50000 GEOTEXTILE FABRIC | 5,019 SY | $0.40 | $0.75 | $1.00 | $2.44 | $2.00 |
| 659E10000 SEEDING AND MULCHING | 5,097 SY | $1.25 | $1.60 | $1.00 | $0.82 | $1.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 255 SY | $1.00 | $3.00 | $0.50 | $0.50 | $1.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.72 TON | $800 | $500 | $515 | $500 | $605 |
| 659E31000 LIME | 1.06 ACRE | $50.00 | $75.00 | $206 | $200 | $75.00 |
| 659E35000 WATER | 29 MGAL | $10.00 | $5.00 | $1.00 | $1.00 | $1.00 |
| 670E00500 SLOPE EROSION PROTECTION | 835 SY | $2.50 | $1.85 | $2.00 | $1.75 | $3.00 |
| 670E00710 DITCH EROSION PROTECTION MAT, TYPE A | 153 SY | $3.15 | $2.00 | $2.00 | $1.75 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,235 | $1,235 | $4,000 | $1,235 | $5,500 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $3,000 | $1,080 | $3,000 | $2,280 | $7,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $6,000 | $6,883 | $2,500 | $5,976 | $10,000 |
| 605E13410 6" UNCLASSIFIED PIPE UNDERDRAINS WITH GEOTEXTILE F | 49 FT | $20.00 | $14.50 | $9.50 | $23.61 | $20.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 81 FT | $20.00 | $21.00 | $14.00 | $33.64 | $20.00 |
| 611E01500 6" CONDUIT, TYPE F | 44 FT | $20.00 | $48.00 | $14.50 | $42.33 | $20.00 |
| 611E04400 12" CONDUIT, TYPE B | 16 FT | $110 | $153 | $85.50 | $212 | $90.00 |
| 611E05900 15" CONDUIT, TYPE B, 706.02 | 6 FT | $165 | $188 | $213 | $425 | $100 |
| 611E10400 24" CONDUIT, TYPE B, 706.02 | 36 FT | $180 | $250 | $186 | $309 | $150 |
| 611E13400 30" CONDUIT, TYPE B, 707.12 | 12 FT | $195 | $224 | $208 | $592 | $200 |
| 611E98410 CATCH BASIN, NO. 8 | 1 EACH | $5,200 | $5,450 | $3,137 | $5,193 | $3,500 |
| 611E98504 CATCH BASIN, NO. 2-2C | 1 EACH | $1,650 | $4,050 | $2,508 | $3,235 | $5,000 |
| 611E99574 MANHOLE, NO. 3 (60") | 1 EACH | $6,000 | $4,350 | $4,719 | $4,495 | $6,000 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $500 | $775 | $456 | $977 | $1,000 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1 1/2") | 1,064 SY | $7.00 | $5.45 | $5.50 | $11.85 | $12.65 |
| 407E10000 TACK COAT | 617 GAL | $1.00 | $1.75 | $2.00 | $4.00 | $4.00 |
| 621E00100 RPM | 66 EACH | $41.25 | $41.25 | $42.50 | $41.25 | $42.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 26 EACH | $15.00 | $10.00 | $11.00 | $20.84 | $10.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 482 FT | $9.50 | $11.00 | $10.00 | $9.50 | $10.00 |
| 630E08600 SIGN POST REFLECTOR | 18 EACH | $30.00 | $55.00 | $31.00 | $30.00 | $30.00 |
| 630E80100 SIGN, FLAT SHEET | 228 SF | $15.00 | $16.00 | $15.50 | $15.00 | $15.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 8 EACH | $15.00 | $35.00 | $15.50 | $15.00 | $15.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 8 EACH | $25.00 | $50.00 | $26.00 | $25.00 | $25.00 |
| 644E00104 EDGE LINE, 6" | 2.15 MILE | $3,125 | $3,125 | $3,219 | $3,125 | $3,200 |
| 644E00204 LANE LINE, 6" | 1.82 MILE | $1,210 | $1,210 | $1,247 | $1,210 | $1,210 |
| 644E00404 CHANNELIZING LINE, 12" | 1,836 FT | $1.25 | $1.25 | $1.50 | $1.25 | $1.25 |
| 644E00720 CHEVRON MARKING | 586 FT | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 644E00900 ISLAND MARKING | 156 SF | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 644E01300 LANE ARROW | 14 EACH | $75.00 | $75.00 | $77.50 | $75.00 | $100 |
| 644E01510 DOTTED LINE, 6" | 525 FT | $1.15 | $1.15 | $1.00 | $1.15 | $1.25 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 32 HOUR | $70.00 | $70.00 | $67.00 | $75.00 | $100 |
| 614E12336 WORK ZONE IMPACT ATTENUATOR (UNIDIRECTIONAL) | 2 EACH | $1,900 | $2,250 | $1,957 | $1,900 | $1,900 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 44 EACH | $10.00 | $8.00 | $10.50 | $10.00 | $10.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 44 EACH | $13.00 | $12.00 | $13.50 | $13.00 | $13.00 |
| 614E20210 WORK ZONE LANE LINE, CLASS I, 6", 740.06, TYPE I | 0.14 MILE | $4,100 | $4,100 | $4,223 | $4,100 | $4,100 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,500 | $4,640 | $4,779 | $3,350 | $10,950 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $3,750 | $12,500 | $4,430 | $5,800 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $1,200 | $2,000 | $630 | $3,192 | $1,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 806 CY | $140 | $113k | 17% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 189 CY | $215 | $41k | 6% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 1,673 CY | $24 | $40k | 6% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (233 CY | $165 | $38k | 6% |
| 304E20000 AGGREGATE BASE | 819 CY | $45 | $37k | 5% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,021 FT | $16.5 | $33k | 5% |
| 832E30000 EROSION CONTROL | 27,000 EACH | $1 | $27k | 4% |
| 659E00300 TOPSOIL | 567 CY | $46 | $26k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $24,000 | $24k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $20k | 3% |