MEG-SR 124-63.33
MEG County · est $0.3M
Bid dateThursday, July 16—
MEG County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 2 more items below.
| Item | Quantity | R1Allard Excavation LLC | R2Alan Stone CO INC | R3J & J Bridge Company INC | R4R C Construction Company And Son INC | R5Shelly & Sands INC | R6Axis Civil Construction LLC | R7Ohio-west Virginia Excavating CO | R8Parker Corporation | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 601E27001 DUMPED ROCK FILL, TYPE C, AS PER PLAN | 2,450 CY | $55.77 | $46.70 | $80.00 | $60.00 | $75.00 | $74.00 | $57.40 | $90.00 | 52% |
| 203E10000 EXCAVATION | 2,285 CY | $12.36 | $22.35 | $15.00 | $10.00 | $17.00 |
| Item | Quantity | R1Allard Excavation LLC | R2Alan Stone CO INC | R3J & J Bridge Company INC | R4R C Construction Company And Son INC | R5Shelly & Sands INC | R6Axis Civil Construction LLC | R7Ohio-west Virginia Excavating CO | R8Parker Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 202E75254 GATE REMOVED FOR REUSE | 1 EACH | $100 | $573 | $500 | $1,000 | $100 | $300 | $72.00 | $100 |
| 642E00300 CENTER LINE, TYPE 1 | 0.08 MILE | $710 | $9,934 | $7,500 | $12,500 | $8,880 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $18.50 |
| $33.60 |
| $20.00 |
| 11% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $16,890 | $7,000 | $12,500 | $10,000 | $20,000 | $20,150 | $15,000 | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,110 | $41,725 | $23,600 | $35,000 | $30,000 | $22,000 | $71,300 | $30,000 | 9% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $15,000 | $7,948 | $2,000 | $8,500 | $6,000 | $500 | $4,550 | $100 | 6% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 145 SY | $65.27 | $64.08 | $60.00 | $90.00 | $40.00 | $85.00 | $93.20 | $90.00 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,120 | $13,911 | $5,000 | $1,500 | $18,250 | $12,000 | $37,100 | $50,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,010 | $5,067 | $1,000 | $10,000 | $10,000 | $5,000 | $1,800 | $15,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,060 | $2,000 | $10,000 | $15,000 | $2,500 | $3,500 | $5,810 | $15,000 | 1% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,750 | $7,153 | $2,000 | $4,500 | $2,000 | $2,500 | $14,275 | $5,000 | 1% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 1,090 SY | $1.37 | $4.47 | $1.00 | $5.00 | $1.34 | $3.50 | $2.50 | $1.00 | 1% |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.15 MILE | $8,425 | $9,537 | $7,500 | $12,500 | $8,425 | $13,500 | $9,500 | $7,000 | 0% |
| 611E01400 6" CONDUIT, TYPE E, 707.31 (PERFORATED) | 420 FT | $2.75 | $15.89 | $3.00 | $20.00 | $1.00 | $12.00 | $17.50 | $10.00 | 0% |
| 607E61111 GATE REBUILT, AS PER PLAN | 1 EACH | $1,000 | $995 | $500 | $3,000 | $75.00 | $400 | $375 | $300 | 0% |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 0% |
| 204E50001 GEOTEXTILE FABRIC, AS PER PLAN | 636 SY | $1.50 | $2.98 | $2.30 | $25.00 | $0.40 | $2.00 | $2.00 | $2.50 | 0% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.16 MILE | $4,755 | $5,365 | $3,500 | $12,500 | $4,755 | $4,755 | $5,400 | $6,250 | 0% |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 20 FT | $14.00 | $15.90 | $12.00 | $50.00 | $14.00 | $10.00 | $16.00 | $10.00 | 0% |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $250 | $348 | $300 | $275 | $450 | $300 | $185 | $250 | 0% |
| 611E01500 6" CONDUIT, TYPE F, 707.33 | 70 FT | $2.75 | $22.35 | $5.00 | $20.00 | $20.00 | $12.00 | $16.00 | $10.00 | 0% |
| $8,880 |
| $10,000 |
| $12,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 601E27001 DUMPED ROCK FILL, TYPE C, AS PER PLAN | 2,450 CY | $55.77 | $137k | 52% |
| 203E10000 EXCAVATION | 2,285 CY | $12.36 | $28k | 11% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $25k | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,110 | $23k | 9% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $15,000 | $15k | 6% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 145 SY | $65.27 | $9k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,120 | $6k | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,010 | $4k | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,060 | $3k | 1% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,750 | $3k | 1% |