Ohio DOT · bid history
| Result | Project | County | Let | Their bid | Winning bid |
|---|---|---|---|---|---|
| Rank 4of 6 | VIN-Tar Hollow CulvertDrainage | VIN | Apr 2026 | $456k | $400k |
| Wonof 2 | GAL-Mercerville Shared Use PathSafety | GAL | Feb 2026 | $911k | $911k |
| Wonof 4 | MEG-SR 733-01.13Drainage | MEG | Dec 2025 | $419k | $419k |
| Rank 6of 8 | WAS-Beverly SidewalkSafety | WAS | Aug 2025 | $447k | $326k |
| Wonof 5 | ROS-Tar Hollow SF Culverts FY25Drainage | ROS | May 2025 | $193k | $193k |
| Rank 2of 5 | WAS-SR 550-16.24Drainage | WAS | Apr 2025 | $545k | $514k |
| Rank 5of 7 | VIN-SR 328-08.97Earthwork | VIN | Jan 2025 | $195k | $156k |
| Wonof 4 | GAL-SR 218/VAR-14.77/VARDrainage | GAL | Jan 2025 | $998k | $998k |
| Rank 3of 6 | WAS-SR 339-08.64Drainage | WAS | Oct 2024 | $912k | $844k |
| Wonof 6 | MRG-SR 376-14.59Drainage | MRG | Jul 2024 | $336k | $336k |
| Rank 3of 4 | NOB-CR 250-00.04Drainage | NOB | Jun 2024 | $307k | $270k |
| Wonof 6 | ATH-Wallace O'Dowd WLAMaintenance | ATH | Apr 2024 | $303k | $303k |
| Wonof 5 | VIN-US 50-28.74Drainage | VIN | Mar 2024 | $520k | $520k |
| Wonof 4 | MEG-SR 689-01.87Drainage | MEG | Feb 2024 | $296k | $296k |
| Wonof 6 | HOC-SR 278-05.47Drainage | HOC | Jan 2024 | $328k | $328k |
| Wonof 7 | VIN-SR 328-06.42Drainage | VIN | Jan 2024 | $217k | $217k |
| Rank 2of 7 | HOC-SR 328-06.22Drainage | HOC | Jan 2024 | $267k | $258k |
| Wonof 4 | GAL-SR 218-09.28Drainage | GAL | May 2023 | $376k | $376k |
| Wonof 10 | HOC-SR 664-16.51Drainage | HOC | Mar 2023 | $449k | $449k |
| Wonof 5 | JAC-SR 279-08.76 Culvert ReplaceDrainage | JAC | Mar 2023 | $149k | $149k |
| Wonof 8 | NOB-SR 821-18.71Drainage | NOB | Feb 2023 | $196k | $196k |
| Rank 4of 4 | ATH-SR 329-01.00Earthwork | ATH | Feb 2023 | $496k | $422k |
| Wonof 8 | VIN-SR 93-12.16Drainage | VIN | Nov 2022 | $905k | $905k |
| Wonof 7 | VIN-SR 160-16.05Drainage | VIN | Oct 2022 | $621k | $621k |
| Rank 5of 8 | HOC-SR 180-05.36Drainage | HOC | Sep 2022 | $998k | $799k |
| Wonof 7 | D10-CR FY2023Drainage | D10 | Aug 2022 | $106k | $106k |
| Rank 2of 3 | NOB-/WAS-IR 77/SR 339-12.91/06.66Drainage | NOB | Jul 2022 | $207k | $187k |
| Rank 3of 5 | GAL-SR 554-10.17/12.63Drainage | GAL | May 2022 | $675k | $658k |
| Rank 6of 10 | MEG-SR 681-04.78Earthwork | MEG | May 2022 | $733k | $595k |
| Wonof 5 | ATH-SR 691-05.17Drainage | ATH | May 2022 | $408k | $408k |
| Wonof 4 | WAS-SR 7-28.97Drainage | WAS | Apr 2022 | $309k | $309k |
| Rank 4of 4 | MEG-Middleport/Pomeroy Path Ph 3Safety | MEG | Mar 2022 | $607k | $500k |
| Wonof 5 | MEG-SR 684-00.19Drainage | MEG | Mar 2022 | $299k | $299k |
| Wonof 2 | MEG-SR 681-21.81Drainage | MEG | Feb 2022 | $327k | $327k |
| Wonof 5 | JAC-SR 776-06.18 Bridge ReplacementBridge | JAC | Jan 2022 | $287k | $287k |
| Rank 2of 8 | MEG-SR 143-11.57Earthwork | MEG | Sep 2021 | $218k | $203k |
| Rank 3of 3 | ATH-US 50-38.09Drainage | ATH | Jul 2021 | $182k | $114k |
| Wonof 4 | NOB-SR 146-07.15Drainage | NOB | Jul 2021 | $63k | $63k |
| Rank 2of 6 | MOE-Monroe Lake ODNR Slip RepairEarthwork | MOE | Jul 2021 | $59k | $49k |
| Wonof 10 | WAS-SR 550-09.21Earthwork | WAS | Jul 2021 | $139k | $139k |
| Rank 6of 9 | MRG-SR 266-11.46Drainage | MRG | Mar 2021 | $731k | $661k |
| Wonof 5 | ATH-SR 56-04.97Earthwork | ATH | Mar 2021 | $191k | $191k |
| Rank 4of 6 | D10-Culverts FY2021Drainage | D10 | Feb 2021 | $336k | $198k |
| Rank 3of 10 | MOE-WNF Drainage Improvement Ph1Drainage | MOE | Feb 2021 | $414k | $350k |
| Rank 2of 4 | VIN-SR 677-03.02Drainage | VIN | Jan 2021 | $450k | $356k |
| Wonof 10 | HOC-SR 56-17.47Drainage | HOC | Nov 2020 | $246k | $246k |
| Wonof 10 | NOB-SR 146-13.17Drainage | NOB | Sep 2020 | $279k | $279k |
| Rank 3of 8 | GAL-SR 141-04.52Drainage | GAL | Aug 2020 | $690k | $662k |
| Rank 2of 7 | NOB-SR 821-14.09Drainage | NOB | Aug 2020 | $387k | $339k |
| Rank 8of 8 | MEG-SR 124-63.33Earthwork | MEG | Jul 2020 | $422k | $262k |
| Wonof 6 | GAL-SR 218-07.87 & VarDrainage | GAL | Jun 2020 | $481k | $481k |
| Rank 2of 6 | VIN-SR 124-05.09Drainage | VIN | May 2020 | $309k | $298k |
| Rank 3of 5 | MEG-Middleport Trail Phase 2Safety | MEG | May 2020 | $177k | $172k |
| Wonof 5 | D10-Culverts FY2020BDrainage | D10 | Apr 2020 | $222k | $222k |
| Wonof 5 | MEG-SR 7-18.70Earthwork | MEG | Apr 2020 | $125k | $125k |
| Rank 3of 5 | WAS-SR 555-05.62Earthwork | WAS | Apr 2020 | $550k | $497k |
| Wonof 8 | D10-Culverts FY2020ADrainage | D10 | Mar 2020 | $145k | $145k |
| Wonof 6 | MRG-SR 555-16.94Bridge | MRG | Mar 2020 | $94k | $94k |
| Rank 2of 9 | NOB-SR 340 4.100Earthwork | NOB | Feb 2020 | $342k | $319k |
| Rank 6of 8 | GAL-US 35 14.800Earthwork | GAL | Feb 2020 | $640k | $469k |
| Rank 7of 8 | ATH-SR 124-01.60Earthwork | ATH | Feb 2020 | $2.09M | $1.61M |
| Rank 5of 5 | WAS-US 50-05.50Earthwork | WAS | Nov 2018 | $622k | $321k |
| Wonof 5 | NOB-SR 313-00.67Earthwork | NOB | Oct 2018 | $160k | $160k |
| Wonof 3 | D10-Culvert FY 2018Drainage | D10 | Jun 2018 | $1.79M | $1.79M |
| Wonof 5 | ATH-SR 329-05.44Earthwork | ATH | May 2018 | $310k | $310k |
| Wonof 10 | JAC-SR 279-09.94Drainage | JAC | Apr 2018 | $159k | $159k |
| Wonof 8 | ATH-US 50-16.65Earthwork | ATH | Apr 2018 | $113k | $113k |
| Rank 5of 8 | JAC-SR 327/SR 776-00.76/10.76Drainage | JAC | Mar 2018 | $1.18M | $990k |
| Rank 5of 8 | MEG-SR 124-55.30Drainage | MEG | Feb 2018 | $1.42M | $886k |
| Wonof 10 | MRG-CR 85-W3.80Drainage | MRG | Feb 2018 | $204k | $204k |
| Rank 2of 9 | HOC-SR-SR 374-21.98Drainage | HOC | Feb 2018 | $409k | $407k |
Source: public.bid_results, ODOT bid tabs. Bidder strings are normalized to upper-case but not yet entity-resolved, so related firms (e.g. "Shelly Company" vs "Shelly & Sands") are shown separately.