MOE-CR 81-01.50
MOE County · est $0.4M
Bid dateThursday, November 5—
MOE County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | R4George J Igel & CO INC | R5Suburban Maintenance & Construction | R6INC Mason Dixon Energy Services LLC | R7Dennison Bridge INC | R8Rock Forge Bridge Company, LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:HP14X89, FURNISHED | 1,080 FT | $42.00 | $50.00 | $50.00 | $60.00 | $50.00 | $51.00 | $50.00 | $48.00 | 18% |
| 524E94803 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK, AS PE | 459 FT | $90.00 | $84.00 | $85.00 | $85.00 |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | R4George J Igel & CO INC | R5Suburban Maintenance & Construction | R6INC Mason Dixon Energy Services LLC | R7Dennison Bridge INC | R8Rock Forge Bridge Company, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 203E20000 EMBANKMENT | 64 CY | $25.00 | $25.00 | $6.00 | $57.00 | $15.00 | $65.00 | $32.00 | $53.00 |
| 204E10000 SUBGRADE COMPACTION | 409 SY | $3.50 | $4.50 | $4.00 | $9.00 | $4.00 | $55.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $90.00 |
| $90.00 |
| $135 |
| $76.00 |
| 16% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 348 FT | $75.00 | $75.00 | $85.00 | $83.00 | $145 | $85.00 | $145 | $61.00 | 10% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 459 FT | $56.00 | $67.00 | $70.00 | $105 | $69.00 | $82.00 | $90.00 | $105 | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,000 | $15,000 | $21,000 | $15,000 | $21,000 | $5,000 | $25,000 | $24,400 | 9% |
| 511E71200 CONCRETE, MISC.:PRECAST CONCRETE LAGGING | 696 SF | $16.00 | $22.00 | $17.50 | $20.00 | $30.00 | $13.00 | $26.00 | $26.00 | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 55 CY | $200 | $440 | $306 | $445 | $450 | $255 | $500 | $510 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10,000 | $24,000 | $12,000 | $25,000 | $9,728 | $15,000 | $66,500 | 4% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 189 SY | $50.00 | $70.00 | $63.50 | $57.00 | $85.00 | $60.00 | $130 | $100 | 4% |
| 507E00400 STEEL PILES, MISC.:HP14X89, PLACED | 960 FT | $7.00 | $0.50 | $1.00 | $1.55 | $5.00 | $75.00 | $10.00 | $74.00 | 3% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 88 CY | $73.00 | $67.00 | $90.00 | $84.00 | $60.00 | $45.00 | $130 | $115 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 29 CY | $200 | $455 | $369 | $750 | $475 | $150 | $600 | $510 | 2% |
| 304E20000 AGGREGATE BASE | 64 CY | $80.00 | $85.00 | $103 | $190 | $65.00 | $90.00 | $130 | $120 | 2% |
| 606E15200 GUARDRAIL, TYPE MGS HALF POST SPACING WITH LONG PO | 162.5 FT | $30.00 | $38.50 | $9.50 | $29.60 | $50.00 | $60.00 | $35.00 | $33.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,500 | $2,870 | $2,200 | $3,000 | $10,000 | $5,964 | $6,000 | $4,750 | 2% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,000 | $2,200 | $531 | $2,500 | $2,200 | $2,200 | $2,500 | $2,490 | 2% |
| 203E10000 EXCAVATION | 181 CY | $19.00 | $21.00 | $20.00 | $37.00 | $20.00 | $80.00 | $25.00 | $55.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,000 | $6,000 | $4,500 | $4,000 | $10,000 | $1,000 | $3,000 | $4,420 | 1% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 25 CY | $120 | $215 | $296 | $180 | $70.00 | $60.00 | $110 | $130 | 1% |
| 204E13000 EXCAVATION OF SUBGRADE | 88 CY | $33.00 | $21.00 | $21.50 | $25.00 | $15.00 | $65.00 | $25.00 | $24.00 | 1% |
| $5.00 |
| $3.10 |
| 204E45000 PROOF ROLLING | 1 HOUR | $115 | $180 | $16.50 | $145 | $500 | $500 | $100 | $120 |
| 204E50000 GEOTEXTILE FABRIC | 176 SY | $2.00 | $1.50 | $2.50 | $3.63 | $2.50 | $2.25 | $3.00 | $1.70 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 1 EACH | $2,500 | $2,350 | $3,200 | $2,480 | $3,000 | $2,300 | $2,800 | $2,800 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $250 | $120 | $312 | $200 | $150 | $130 | $150 | $550 |
| 659E00300 TOPSOIL | 65 CY | $23.00 | $19.00 | $50.00 | $45.00 | $55.00 | $35.00 | $45.00 | $57.00 |
| 659E10000 SEEDING AND MULCHING | 589 SY | $4.50 | $4.55 | $4.00 | $5.05 | $5.00 | $2.50 | $7.00 | $5.70 |
| 659E14000 REPAIR SEEDING AND MULCHING | 29 SY | $0.50 | $0.70 | $13.00 | $2.00 | $1.00 | $3.50 | $7.00 | $1.10 |
| 659E20000 COMMERCIAL FERTILIZER | 0.08 TON | $700 | $665 | $726 | $1,000 | $500 | $500 | $1,000 | $565 |
| 659E31000 LIME | 0.13 ACRE | $100 | $140 | $929 | $300 | $200 | $180 | $250 | $225 |
| 659E35000 WATER | 6 MGAL | $1.00 | $1.00 | $0.01 | $100 | $1.00 | $20.00 | $1.00 | $1.10 |
| 670E00710 DITCH EROSION PROTECTION MAT, TYPE A | 159 SY | $5.50 | $2.15 | $6.00 | $8.00 | $5.00 | $1.72 | $9.00 | $5.70 |
| 832E30000 EROSION CONTROL | 2,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $150 | $250 | $346 | $300 | $500 | $300 | $300 | $975 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 36 FT | $6.00 | $4.00 | $16.50 | $15.00 | $5.00 | $5.50 | $20.00 | $140 |
| 407E20000 NON-TRACKING TACK COAT | 39 GAL | $7.00 | $3.00 | $4.00 | $2.00 | $5.00 | $3.00 | $5.00 | $4.50 |
| 617E10100 COMPACTED AGGREGATE | 21 CY | $45.00 | $120 | $153 | $150 | $60.00 | $50.00 | $125 | $170 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 BI-DIRECTIONAL | 4 EACH | $8.00 | $8.00 | $13.00 | $7.50 | $13.00 | $7.50 | $10.00 | $8.50 |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 10 SY | $50.00 | $240 | $280 | $16.00 | $250 | $80.00 | $300 | $220 |
| 614E11630 INCREASED BARRIER DELINEATION | 200 FT | $2.75 | $0.50 | $0.70 | $2.45 | $2.00 | $2.50 | $5.00 | $3.10 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 18 FT | $14.00 | $17.00 | $3.50 | $37.00 | $25.00 | $5.00 | $15.00 | $16.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,500 | $8,500 | $5,100 | $6,500 | $5,000 | $3,500 | $10,000 | $5,190 |
| 616E10000 WATER | 1 MGAL | $10.00 | $15.00 | $1.50 | $200 | $1.00 | $20.00 | $1.00 | $565 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 200 FT | $12.00 | $25.00 | $25.50 | $35.00 | $18.00 | $20.00 | $30.00 | $61.00 |
| 512E10000 SEALING OF CONCRETE SURFACES | 96 SY | $15.00 | $15.00 | $11.50 | $12.00 | $18.00 | $12.00 | $30.00 | $19.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 148 FT | $7.00 | $3.50 | $9.50 | $9.00 | $8.00 | $7.00 | $10.00 | $26.00 |
| 518E40012 6" NON-PERFORATED CORRUGATED PLASTIC PIPE | 10 FT | $7.00 | $25.00 | $25.00 | $29.00 | $8.00 | $8.00 | $20.00 | $78.00 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 2 CY | $250 | $1,000 | $158 | $700 | $500 | $200 | $200 | $2,340 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $4,300 | $7,000 | $5,400 | $5,000 | $5,800 | $5,000 | $2,280 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:HP14X89, FURNISHED | 1,080 FT | $42 | $45k | 16% |
| 524E94803 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK, AS PE | 459 FT | $90 | $41k | 15% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 348 FT | $75 | $26k | 9% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 459 FT | $56 | $26k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,000 | $23k | 8% |
| 511E71200 CONCRETE, MISC.:PRECAST CONCRETE LAGGING | 696 SF | $16 | $11k | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 55 CY | $200 | $11k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 4% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 189 SY | $50 | $9k | 3% |
| 507E00400 STEEL PILES, MISC.:HP14X89, PLACED | 960 FT | $7 | $7k | 2% |