HAM-Mt. Healthy SRTS 2017
HAM County · est $0.2M
Bid dateThursday, January 14—
HAM County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 17 more items below.
| Item | Quantity | R1Adleta INC | R2Prus Construction Company | R3Tri-state Concrete Construction INC | R4R A Miller Construction CO | % of bid |
|---|---|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 3,884 SF | $8.17 | $7.75 | $6.50 | $6.00 | 21% |
| 608E52001 CURB RAMP, AS PER PLAN | 1,911 SF | $16.49 | $22.00 | $25.50 | $22.00 | 21% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $19,715 | $13,000 | $20,000 | $20,000 | 13% |
| 625E31506 PULL BOX REMOVED AND REPLACED | 6 EACH | $2,153 | $2,500 | $1,000 | $1,845 | 9% |
| 203E10000 EXCAVATION | 103 CY | $73.64 | $95.00 | $138 | $62.00 | 5% |
| 609E26000 CURB, TYPE 6 | 89 FT | $52.92 | $40.00 | $65.00 | $44.00 | 3% |
| Item | Quantity | R1Adleta INC | R2Prus Construction Company | R3Tri-state Concrete Construction INC | R4R A Miller Construction CO |
|---|---|---|---|---|---|
| 202E30200 STEPS REMOVED | 9 FT | $25.14 | $30.00 | $60.00 | $61.00 |
| 202E32000 CURB REMOVED | 199 FT | $7.29 | $22.00 | $28.50 | $14.00 |
| 202E98100 REMOVAL MISC.: INSPECTION WELL | 4 EACH | $87.65 | $400 | $575 | $516 |
| 203E20000 EMBANKMENT | 5 CY | $33.94 | $100 | $125 | $30.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 5 CY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 642E00600 CROSSWALK LINE, TYPE 1 | 1,420 FT | $3.28 | $3.30 | $3.12 | $4.00 | 3% |
| 202E30000 WALK REMOVED | 977 SF | $4.61 | $5.00 | $5.50 | $3.00 | 3% |
| 202E30001 WALK REMOVED, AS PER PLAN | 772 SF | $5.66 | $10.00 | $7.95 | $5.00 | 3% |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 1,398 FT | $2.47 | $2.50 | $2.35 | $3.00 | 2% |
| 659E00300 TOPSOIL | 58 CY | $57.54 | $100 | $85.00 | $78.00 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,333 | $4,500 | $4,500 | $15,000 | 2% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 611E99720 INSPECTION WELL | 4 EACH | $651 | $1,000 | $850 | $1,381 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 20 HOUR | $126 | $100 | $85.00 | $85.00 | 2% |
| 638E10900 SERVICE BOX ADJUSTED TO GRADE | 8 EACH | $304 | $200 | $375 | $1,216 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $2,213 | $3,000 | $10,000 | $12,158 | 1% |
| 202E98200 REMOVAL MISC.:CONDUIT | 40 FT | $53.89 | $10.00 | $15.50 | $25.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $1,715 | $3,000 | $3,500 | $2,700 | 1% |
| 202E23000 PAVEMENT REMOVED | 46 SY | $33.65 | $70.00 | $135 | $65.00 | 1% |
| $46.75 |
| $100 |
| $125 |
| $30.00 |
| 608E40000 CONCRETE STEPS, TYPE A | 12 FT | $61.04 | $300 | $60.00 | $61.00 |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 20 SF | $21.12 | $150 | $150 | $88.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 2 EACH | $354 | $700 | $65.00 | $219 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 523 SY | $1.83 | $8.00 | $3.00 | $4.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 26 SY | $8.52 | $8.00 | $1.00 | $4.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.07 TON | $4,725 | $1,000 | $2,500 | $2,000 |
| 659E31000 LIME | 0.11 ACRE | $735 | $1,000 | $500 | $304 |
| 659E35000 WATER | 3 MGAL | $1.33 | $10.00 | $100 | $61.00 |
| 611E97400 CONDUIT, MISC.: TYPE F FOR DRAINAGE DISCHARGE CONT | 40 FT | $17.23 | $100 | $35.00 | $65.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $843 | $800 | $850 | $948 |
| 642E00500 STOP LINE, TYPE 1 | 23 FT | $6.55 | $6.50 | $6.24 | $8.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,209 | $2,500 | $2,500 | $5,957 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 3,884 SF | $8.17 | $32k | 20% |
| 608E52001 CURB RAMP, AS PER PLAN | 1,911 SF | $16.49 | $32k | 20% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $19,715 | $20k | 12% |
| 625E31506 PULL BOX REMOVED AND REPLACED | 6 EACH | $2,153 | $13k | 8% |
| 203E10000 EXCAVATION | 103 CY | $73.64 | $8k | 5% |
| 609E26000 CURB, TYPE 6 | 89 FT | $52.92 | $5k | 3% |
| 642E00600 CROSSWALK LINE, TYPE 1 | 1,420 FT | $3.28 | $5k | 3% |
| 202E30000 WALK REMOVED | 977 SF | $4.61 | $5k | 3% |
| 202E30001 WALK REMOVED, AS PER PLAN | 772 SF | $5.66 | $4k | 3% |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 1,398 FT | $2.47 | $3k | 2% |