MRG-SR 60-12.89
MRG County · est $1.0M
Bid dateThursday, May 27—
MRG County · est $1.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 33 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly & Sands INC | R3George J Igel & CO INC | % of bid |
|---|---|---|---|---|---|
| 524E95000 DRILLED SHAFTS, MISC.: 42" PERMANENT CASING | 1,112 FT | $199 | $200 | $252 | 21% |
| 524E95000 DRILLED SHAFTS, MISC.: 36" PERMANENT CASING | 1,092 FT | $174 | $150 | $192 | 18% |
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES, W24X117 | 1,953 FT | $89.00 | $80.00 | $120 | 16% |
| 524E94805 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK, AS PER | 855 FT | $120 | $103 | $109 | 10% |
| 524E94803 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK, AS PE | 1,112 FT | $75.00 |
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly & Sands INC | R3George J Igel & CO INC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $2,000 | $10,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 5 FT | $108 | $50.00 | $22.00 |
| 202E38000 GUARDRAIL REMOVED | 465 FT | $2.80 | $3.00 | $2.80 |
| 203E20000 EMBANKMENT | 19 CY | $7.00 | $7.00 | $120 |
| 204E10000 SUBGRADE COMPACTION | 164 SY | $4.00 | $6.00 | $11.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $163 |
| $108 |
| 8% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,092 FT | $75.00 | $133 | $78.00 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $40,000 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,400 | $12,000 | $30,000 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 90 CY | $300 | $300 | $300 | 3% |
| 622E25051 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 8 EACH | $2,200 | $4,800 | $1,700 | 2% |
| 611E98011 CONCRETE BARRIER (TYPE D) INLET, AS PER PLAN | 4 EACH | $3,615 | $6,300 | $2,400 | 1% |
| 622E24001 CONCRETE BARRIER, TYPE D, AS PER PLAN | 139.5 FT | $99.00 | $170 | $90.00 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 530 FT | $25.00 | $24.00 | $21.00 | 1% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 28 CY | $450 | $450 | $400 | 1% |
| 451E14010 9" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 46 SY | $210 | $310 | $145 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,226 | $10,000 | $15,000 | 1% |
| 203E10000 EXCAVATION | 115 CY | $62.00 | $35.00 | $55.00 | 1% |
| 622E25001 CONCRETE BARRIER END SECTION, TYPE D, AS PER PLAN | 2 EACH | $3,525 | $4,500 | $5,300 | 1% |
| 512E10000 SEALING OF CONCRETE SURFACES | 331 SY | $20.00 | $11.00 | $11.00 | 1% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,750 | $2,200 | $2,200 | 1% |
| 330 FT |
| $8.00 |
| $10.00 |
| $3.50 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 75 FT | $42.00 | $42.00 | $42.00 |
| 606E35000 BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 1 EACH | $2,275 | $2,275 | $2,275 |
| 606E35100 BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $625 | $625 | $625 |
| 659E10000 SEEDING AND MULCHING | 294 SY | $5.00 | $5.00 | $4.75 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $610 | $610 | $550 |
| 659E31000 LIME | 0.06 ACRE | $80.00 | $80.00 | $100 |
| 659E35000 WATER | 0.79 MGAL | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 367.5 FT | $12.00 | $15.00 | $15.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 9 FT | $53.00 | $50.00 | $34.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $345 | $250 | $285 |
| 304E20000 AGGREGATE BASE | 28 CY | $115 | $110 | $120 |
| 407E20000 NON-TRACKING TACK COAT | 168 GAL | $4.25 | $3.00 | $10.00 |
| 408E10000 PRIME COAT | 112 GAL | $35.00 | $20.00 | $10.00 |
| 617E10100 COMPACTED AGGREGATE | 24 CY | $140 | $110 | $115 |
| 621E00100 RPM | 16 EACH | $140 | $140 | $140 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 16 EACH | $23.00 | $15.00 | $12.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 8 EACH | $10.00 | $10.00 | $10.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 4 EACH | $75.00 | $75.00 | $85.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.24 MILE | $3,850 | $3,850 | $3,850 |
| 642E00300 CENTER LINE, TYPE 1 | 0.12 MILE | $7,250 | $7,250 | $7,250 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $1,500 | $20,000 | $10,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BI-DIRECTIONAL | 11 EACH | $28.00 | $10.00 | $11.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 11 EACH | $38.00 | $14.00 | $18.00 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.22 MILE | $4,250 | $4,250 | $4,250 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 24 FT | $12.50 | $12.50 | $12.50 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,505 | $8,050 | $10,675 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 524E95000 DRILLED SHAFTS, MISC.: 42" PERMANENT CASING | 1,112 FT | $199 | $221k | 20% |
| 524E95000 DRILLED SHAFTS, MISC.: 36" PERMANENT CASING | 1,092 FT | $174 | $190k | 17% |
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES, W24X117 | 1,953 FT | $89 | $174k | 16% |
| 524E94805 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK, AS PER | 855 FT | $120 | $103k | 9% |
| 524E94803 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK, AS PE | 1,112 FT | $75 | $83k | 7% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,092 FT | $75 | $82k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,400 | $29k | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 90 CY | $300 | $27k | 2% |
| 622E25051 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 8 EACH | $2,200 | $18k | 2% |